Hi Gurus,
i have some doubts about production order scheduling. i have run a scenario OF MTO to Understand The Scheduling. i had created a BOM with  two components. The inhouse production Time of header Material is 3 days.and the scheduling Margin key is op2   flt aft1  flt bfr 1    rl per 2
after creating a sales order i had run MRP in MD50 by selecting scheduling 1 Basic Date Determination. it has taken the 3 days of in house production time and praposed dates.18th as starting date and 20th as finish date.and planed opening period is in past. and it has not praposed any scheduled dates in planned orders.
if i convert the planned order in to production order it is praposing the scheduled dates.
scenario 2.
if i run the mrp for the same order by taking scheduling type as 2 lead time scheduling.       in planned order itself it is showing sheduled start date and scheduled finsh date. (which not shown in basic date run).
1.so is it mean that what ever the scheduling type we are using in MRP run is only applicable to create Planned orders only while convrting the planned orders in to production order dates will be re detemind. is this currect or wrong?
2.in which scheduling type system will not consider the scheduling margin key?
please help me to understand these questions.
Thanks&regards,
Venkat Bolla.

Hi Venkat,
When MRP is run with '1' Basic Scheduling - Schedule Margin Key is not considered. As you rightly observed it considers the Inhouse Production days mentioned in materials master for fixing the start date. This is exactly to days.
When MRP is run with '2' Lead Time Scheduling - Schedule Margin Key is considered. Dates are calculated from Routing and Capacity requirement calculations are also done. Here calculation are exact to the seconds.
Schedule Margin Key takes effect only for lead time scheduling. Production dates are calculated from the float times of the SMK in the material master and times from the individual operations maintained in routing.
When planned order derived from Basic scheduling is converted to production order it is subjected to lead time scheduling and thus production dates are calculated
Refer to the below discussions on the same topic.
http://scn.sap.com/thread/1535577
http://scn.sap.com/thread/1554548
Thanks & Regards,
Ramagiri

Similar Messages

  • Production scheduling profile for production order type 10 does not exist – SAP Message No.10085

    When i tried to make confirmation for Production Order through CO15 transaction , i receive the following error message “ Production scheduling profile for production order type 10 does not exist – SAP Message No.10085 “
    In Work Scheduling view, Production Scheduling Profile is maintained as per OPKP only.
    How to check whether production scheduling profile is maintained for relevant order type 10.
    To do this , i went to OPKP & KOT2_OPA transactions but i don’t know how to check. I guide me through with a screen shot.
    Also, pls explain about  “Order Type 10” and how it is linked with material and order execution.
    Looking for a detailed explanation with screen shots , since i am new to SAP.
    Thanks With Regards,
    Dinesh Kumar V.

    Hello Dinesh,
    Please check the order type dependent parameter in OPL8 here you will get the Substitute Scheduler
    Then go to OPCH and check valid production scheduling profile assign here as per OPKP to your production scheduler for your plant.
    Production order have Order category as 10  Process Order  40 in standard SAP you can check this in OPJH.
    Best Regards,
    R.Brahmankar

  • Production scheduling profile for production order type 10 does not exist

    Kindly suggest me how to resolve this error
    Production scheduling profile for production order type 10 does not exist

    Hi Archana,
    Go to material master-work scheduling view and check what is the production scheduling profile maintained for the same materisl -plant combination.
    then go to OPKP and check if production scheduliong profile is maintained for relevent order type 10 in custmizing. If not maintain one and it should resolve the error.

  • Error in scheduling parameters for production orders

    Hi Guys,
    Greeting for the day u2026u2026u2026.
    I am trying to create production orders creation for own order  type ex MM01, but I am getting error message as u201C scheduling parameters are not defined for the order type u201C even though I have maintained following parameters as below,
    Production scheduler      -
    xxxxx,
    Detailed scheduling -
    check box of scheduling ticked,
    Rough cut scheduling    --- scheduling id u201301, scheduling and generate capa requi,, boxes     ticked,
    Adjust scheduling  -- requi to operation  date,
    Scheduling control for detailed scheduling ---backwards and check box of auto scheduling ticked
    Operation segment ---setup,
    All operation in order will be reduce
    Do not reduce,
    Could any one light on this issue,
    Thanks in advance,
    Mohan

    Hi,
      This error will come if you have not maintained Define scheduling parameters for production orders.
    Check this order type whether linked with respective plant in OPU3.*And give production scheduler * mark ie, all.*
    And in Define production scheduling profile - OPKP, link your order type in the page below.
    In material master work scheduling view, input production sch profile or prod scheduler.
    Regards,
    Dharma

  • Output type for production order

    Hi, when we save the production order, we wants to transfer the prod order header details in legacy system thru idocs. Trying to define output type for production orders in NACE t-code, could not find production order option there. Pls advise in this case how to define the output type for production order so that the header data will be taken by idoc and transfered to legacy. Pls advise.

    Hi,
    production orders don't have output types like SD orders.
    But they have status control and events. Look into the object type BUS2005 in transaction SWO1. There you find the events which are fired by SAP, eg. ProductionOrder.Released.
    Which Idoc type do you want to use?
    I think you have to programm your own method for the Idoc creation. Put it into a workflow task and assign it to the event.
    Regards
    Michael

  • Configure another Inspection Type for Production Order

    Hi QM Gurus,
       I have one scenario, my client wants to have another inspection type for inspection lot origin goods receipt from production because they have this requirement that for some materials they need to have a status profile that will be active for inspection type standard 04. And there are also some materials from goods receipt from production that does not need status profile. Since the only thing that we could assign as specific status profile is to its inspection type. Hence, i need to create another inspection type for lot origin goods receipt from production aside from inspection type 04 that will create automatic inspection lots with different status profiles.I try this in configuration but no inspection lots has been made for new inspection type assigned to LOt origin 04 and also assigned in the material master inspection set-up. How will i do this???
    Thanks.
    Regards,
    Matildo, Edsel
    QM Consultant

    Hello Edsel,
    you can configure for example an inspection type 0401 and activate this inspection type for the inspection origin 04 in customizing. Please look at the following customizing items:
    Transaction QCC3
    -> Inspection Lot Creation
    - Maintain Inspection Types
    - Maintain Inspection Lot Origins and Assign Inspection Types
    By activating the correspondent inspection type in the material master you can decide which inspection type is used. If you need both then you could think about using the exit QAAT0001 to assign the correspondent inspection type.
    Regards
    Isabelle

  • Production Order   : OUTPUT Type Configuration for Production Order  as EDI

    Dear SDN All ,
      OUTPUT Type Configuration for Production Order.
    <b>Doubt in third Point</b>
    We have found the IDoc " LOIPRO01 " for Production Order
    (Please confirm that this IDoc can be used for outbound IDoc for Production Order)
    And foloowing
    <b>1. Defining the Output Type for Particular Application.
       T-Code: “NACE”</b>
      A. Output type have created upder application "ME" description : "Inventory Management"
      B.  " ZEDI "  created for getting output as EDI type
         ZEDI is copied from "WF01" output type. and
         Transmision mediam as "EDI"          
         Program : RSNASTED
         Form Routine :  EDI_PROCESSING
              (Please confirm is this for IDoc creation)
    <b>2. Partner profile creation:</b>
      A. Partner profile created under logical system and
      B. and In outbound parameter declared as "LOIPRO"(This is for sending the IDoc "LOIPRO01" to XI system).
    <b>3. Customization for output type for Proction Order -- (For CO02,CO08)</b>   ---
       A. But only one functional customization is remaining to do, for getting the IDoc while saving the Production Order in T-Code "CO02" and "CO08"
            <i>For Example:
                in sales order transaction va02 (in DBI 450 client) and select any Sales order.
                & select following menu path.
                 Extras --- > Output -
    > Header -
    > output
               Here we can set our output type "that U defined in NACE Transaction-Code"</i>
    <b> Like the same way I want to set output type  for CO02, CO08 transaction.</b>
    But I couldn't find the menu Item in Co02 and Co08 for setting the output.(like VA03)
    Please help me out for setting the output type for Production Order Creation.
    Thanks in advance,
    Dhanabal T
    Message was edited by: Dhanabal T

    Hello.
    I have a similar requirement. Did you guys find the solution?

  • IDoc Configuration for Production Order Creation and Change

    Hi All,
    Please Help me out for IDoc Configuration for Production Order Creation and Change
    I have found the IDoc for Production Order
    Messgae Type : LOIPRO and IDoc type : LOIPRO01
    Actually my requirment is to send the (LOIPRO01 )IDoc from SAP R/3 to XI system ,when ever the Production Order Created and Changed,
    I have done following Configurations:
    1. RFC Destination created for XI system
    2. PORT was created for XI
    3. Partner profile created WE20 and LOIPRO01 IDoc is added in OutBound Perameter.
    I need to know how to do the followning.
    1. How do i configure the outbound Production order idocs when Production Order is created or changed.
    2. in NACE (Output control) which is the Application for Production Order.
    3. How can I set IDoc as output Type for Production Order Creation.
    Thanks in advance
    Dhanabal T

    Hi Michal,
    I know that it is the old thread but still want to get clarified from you out of curiosity.
    Unlike other IDOC, i actiavated change pointers for LOIPRO
    1.message and idoc type is linked
    2.function module , message type , idoc type is linked
    function module used is CLOI_MASTERIDOC_CREATE_LOIPRO
    3.BD64, distribution model is created and distributed
    4. port and partner profile is in place.
    5. IDOC is not getting generated after creating the process order.
    do we need to activate the change documents for the message type in BD52,
    if yes can you please provide the object types for the same.
    or i am missing something else. please guide me in this regards.
    Thanks in advance for your time.
    S.Janagar

  • Output ytype for production order ?

    Hello,
    What is the output type for production order. ? i have to attached customized forms for it.
    Thanks,
    Shehryar Dahar

    Hi,
    You can check in the Table T685/ T685T by entering the KVEWE = 'O' (output)
    I don't find any std output type for production order in those tables.
    May be you have to define you own Z type and use .
    Even you can check the table TNAPR (which stores NACE  T code entries).
    Regards,
    Anji

  • Scheduling parameters are not defined for production orders

    Hi All,
             when i convert the planned order to production order  i got this massage popup coming  Scheduling parameters are not defined for production orders . please let me know this .

    Hi,
    One of major customization steps for the order type is missing. Run OPU3 and maintain settings for the order type you are using. You may copy settings from an older type.
    Regards.

  • Print indicator assigned to the MM movement type 101 F ( GR for Production Order )

    Hello!
    I'd like to know how to assign a print indicator to the movement type GR for Production Order 101_F
    When I use the IMG path : Material management/ Inventory Management and Physical Inventory/ Print Control/ Maintain Print Indicator for Goods Receipt Document, I can only assign the movement type 101 (Goods receipt) but not the movement 101_F.
    Thank you for your help!
    Charlotte

    Hello Dev!
    The movement 101 F is Goods Receipt for Production Order. The letter "F" corresponds to the movement indicator.
    I'd like to dissociate the movements types 101 and 101_F to have only one printed label.
    Regards,
    Charlotte

  • Specific process code for Production order message type LOIPRO

    Hello,
    Is there any specific process code for Production order message type LOIPRO.
    Request you to reply.
    Thanks
    Prashanth

    Hi Prashanth,
    sorry for last thread ... that not contain full information ...
    For message type LOIPRO you can use process code APLI.
    In IDOC PARTNER definition, the partner is linked with an IDOC TYPE and PROCESS CODE for inbound processing. This process code is in turn linked with a FUNCTION MODULE to process the IDoc such as IDOC_INPUT_INVOIC_MRM (Reff..  http://searchsap.techtarget.com/expert/KnowledgebaseAnswer/0,289625,sid21_cid519558,00.html)
    Regards,
    Amit

  • Best practice - material staging for production order

    Hi Experts,
    could any of You pls, support me with some hints of best practice how to handle material staging WM-PP interface in a certain case?
    Up till now we had a system, where production had no separate location in IM, but one location existed including raw material wh and production. In the same time in WM we had separate storage types for production and raw materials u2013 hence we did material staging transferring goods only inside one IM location between different WM storage types. The material staging should be done based on separate prd. orders.
    Now this need to be changed and separate location need to be handled in IM for production u2013 which means the staging should be done between different IM locations and WM administration also need to be handled.
    Up till now we used LP10 for staging, then LB13 for TO creation etc. We can keep going like that, but if do so, there is another step required in IM u2013 movement 311, where material numbers and qty need to be added manually to finish the whole procedure. I would like to avoid this u2013 which makes the administrational procedure quite long.
    I have been checking the following possibilities:
    1.     Set released order parts-staging at control cycle and use MF60 for staging u2013 but I can not select requirements based on pro ordders here (only able to find demand if component including into selection)
    2.     Two step transfer 313/315 u2013 but this not a supported procedure u2013 313 TI /TO / 315
    3.     Try to find solution how to create 311 movement based on TO or based on WM stock at certain storage type / dynamic bin.
    I have failed.
    So, could any of You pls, support me with some useful ideas, how to handle material staging where 311 included and definetly the last step of procedure, but administrator does not need to enter items manually one by one in MIGO.
    All answers will be appreciated

    Hi,
    Storage location control should be able to take care of your problem.
    If you want to stage the material to a different IM location then the WM location then make the following settings
    If location xxxx is your WM location and location yyyy is your Production location.
    You have defined Production storage type ZZZ for production storage location YYYY and have maintained the supply area for the same
    In WM configuration - For interfaces - IM interface-Control of Assignment "Plant / Stor.Loc. - Whse Number"
    Assign location XXXX as the Standard Location. Maintain entry donot copy sloc in TR for location YYYY
    In WM configuration - For interfaces - IM interface-  Storage Location control for WH
    This entry ensures that there will be a WM tarnsfer Posting between your WM and Production storage Location automatically when you confirm your TO. You can have this done via a btach job also if you want cumulative posting. (schedule job RLLQ0100)

  • WM Material Staging  for Production Order

    Hi,
    In the process order txn Cor3, Go to > List > WM pick list>  the initial screen is  Display WM Material Staging  for Production Order. In the All parts tab, could you please help me on how to be able to populate the fields in the  BSI, Category and Storage Bin. Your help is greatly appreciated.
    Thanks

    Dear Ellen,
    If you set the cursor on 'BSI' field and push F1 you'll get an explanation about the meaning of each category.
    '"<i>1" pick list item
    This materials are picked according to the required quantity specified in the production order.
    '2': Crate or kanban parts
    These materials are always removed from the warehouse in full cases. These can be ordered, for example, as soon as a case of needed parts is emptied in production.
    '3': Release order parts
    Release order parts are scheduled individually and the quantities are supplied manually to replenishment storage bins based on the requirements of production orders and the stock levels in the scheduled production supply areas.
    "0" not relevant to WM-PP
    These materials are not relevant for WM production supply and cannot be requested using the WM system.</i>'
    For instance:
    You can set raw materials / SFG as pick parts if warehouse workers have to collect those parts from high racks (from different places) and they have to provide an exact qty for the PrdOrd.
    We use '4' (manual staging) for huge alu rolls that are near the machine and WH workers have nothing to do with it - the operators, who deal with the machine, have to put the new rolls on it.
    When we issue the PrdOrd the requirements of this material won't appear in LB10 since WH has nothing to do with them.
    'Storage bin' filed will contain a value automatically, if your settings are proper.
    E.g. you have to define the default 'stock removal' & 'stock placement' storage type on WM view of material master.
    Additionally you have to define control cycles for materials you use for your production. (LPK1)
    The control cycle says from which storage type & bin you want to consume the components.
    BR
    Csaba

  • Template allocation enviornment 12 for production order not working

    Dear experts,
    i have more than 6 activity type in routing and the base will be machin hour qty means all my activity Fiance, HR,IT and quality ase will be machin hr qty defined in routing and rate will be different in kp26 for hr,IT<QC and finance.
    so i am planning for templete allocation and i m using production order.
    In templete allocation there are different enviornment for plan and actual for production order.
    For planning i have created environment 0
    Based on cost center and activity tpe ( all my activity-HR,IT,QC,Finance and one common cost center)-seperate line for each activity and plan qty is machin.I wrote the logic and same is working also.
    but for actaual .i have chosen enviornment 12 becoz i m using production order and logic will be actual machin hour qty.
    request you to guide me on actual environment based on machin hour actual qty
    regards
    RR

    dear friend,
    for the first issue please run OPU3 for your plant/prod.order type and
    set MORE days in 'Start in the Past' field
    or
    go back to your prod.order (run CO02 ) and REDUCE days in past
    for the second issue please run CR02 and fix the time (Scheduling tab)