Scrap from vendor Reconsilation

Dear all ,
Here i am performimg scrap transfer posting from Vendor.
MB1B -  542  mvmnt , here it is not against the PO as system is not taking the same againt PO , but against vendor code.
Now can i reconsile with the same , if yes pl guide with procedure ?
Regards

Dear Pankaj,
What if sending material code (RM) is same as the returning material (Scrap)code.
What if the matrial is coming back from vendor without processing.
I think in that case we have to reconcille the s/c challan with reference to the 542 movt type document
regards,
sujit

Similar Messages

  • Return of scrap from vendor Sub contracting

    Dear gurus
    Pls advice me on how to map this scenario
    we are sending two raw materials to subcontractor for a semi finished product. during the process scrap is also generated which is of value to the organization and they need to receive it from the sub contractor.
    now hot to work on this scenario
    your valuable advice is greatly appreciated
    regards
    John

    Hi,
    create a material master record for the scrap material. Maintain the scrap material with a negative quantity either in the BOM or in the material components while creating the subcontracting PO.
    Post the components to Vendor's stock with movement type 541. Later send the materials to vendor physically. While receiving the materials (Goods Receipt) w.r.t.the sub contracting PO with MT 101, the following postings happen,
    components will be posted with movement type 543 ( - ) and the scrap with MT 545 'O' (stock category) [MT 545 - material lying at Vendor's location]. Later u can take back this scrap material from the vendor with movement type 542. This is the complete procedure in terms of goods movements.
    Don't forget to Reward, if found useful.
    Regards,
    Varma

  • Scrap from vendor

    Dear all ,
    i have craeted Sub contracting PO for SFG .
    BOm of SFG contains Rm & scap item with - qty .
    After PO creation MB1b for PO with 541 item .
    Only Rm can be sent against the PO . After that , at time of GR 101 mvmt for SFG and Whr the scrap is going ?
    Why i cant receive the same ?
    Regards

    Hi,
    scrap should be entered in BOM as -ve qty...
    While you recieve the end product(finished) scrap will be accumulated in vendor's place with the movement type 545 O-.
    You have to reverse manually using 542 mvt type...
    If its accumulation and over accumulation - 545
    If cumulated qty is less you can do subsequwnt adjustment using 121 and indirectly 546 gets hit..
    Reg,
    Deepak

  • Scenario of Import P.O from same material get money from vendor and custome

    Hi Experts,
    My client is procuring certain material Quantity 10 by Import, As when he recieve the 10 Quantity material he founds 8 Quantity is to be Okay and the other 2 founds to be damaged, As it is import material he cannot return it to import vendor, in this situation he takes the photocopy of the 2 damaged material and get debits from vendor without actual returning to import vendor apart from this the damaged goods he sells for lower price.
    So from the same material he gets the money double time one from Vendor and other from Customer.
    How to MAP this Scenario in SAP ?
    Plaese advice.
    Best Regards
    Javeed Ahamed

    Hi Javeed,
    Are u using QM module?  If u are using, u can activate quality inspection for this material.  You can do 101 movement for total qty i.e. 10 nos.
    Then in usage decision, you can accept 8 nos and reject and scrap 2 nos. 
    If u are not using QM module, u can still post 101 movement for 10 numbers.  Then you can screap 2 nos with movement type 551.
    Hope this will resolve ur problem.
    Award points if found useful

  • Withdraw stock from vendor blocked stock

    Hi
    There are stocks at vendor in Restricted status.
    I wanted to withdraw this stock for scrapping.  But movment type 555 do not have option to withdraw from vendor restricted stock.
    Can you please help me to remove the stock ? to unristricted/scrapping.
    Warm Regards
    Chetan.

    hi chetan,
    As per u narrated the stock is at vendor but in restricted stock. it means under vendor liabilities.. but now u want to scrapp it correct??
    as per my knolwedge the restricted stock should have liabilities at your side then only u can scrapp it. for that u have to move the vendor stock to unres. one and then receive it to scrap.
    please find your self and try.
    regards,
    ninad kshirsagar

  • Regarding rejection of material from vendor

    Hi All
    My scenario is like this
    My semi finished material is come from vendor after that i put that material on production after doing all process production done the GR for that material as finished goods. This material goes into quality and here I come to know that the material is rejecting because of vendor. But the GR is done on finished material code so I have to do the material to material transfer by movement type 309. And then reject the material on vendor coz Material code for vendor material is different and material code after production is different
    I want to ask is their any other process to map this scenario
    Regards
    Sachin

    Hi,
    Sorry for replying late.
    Pl. I am not worring about points. My only concern is I should share my knowledge and improve knowledge by following the others inputs.
    Whatever the quantity you have to reject against a particular vendor, can be enterered in the complaint quantity.
    You have to enter the FG material no., in which you are rejecting in the parent material field.
    In the child material field, you have to enter the material no. which you have recd. from the vendor (refer BOM)
    After that, you have to scrap the material by using T code QM10.
    Then for Return delivery process, pl. discuss with your MM counterpart and for Debit to supplier pl. involve FI/CO counterpart.
    My suggestion is that, First write down the Business Process Procedure for material defect found out during processing. i.e your current problem process.
    Madhava

  • Copy Trading Partner to Asset line items from Vendor line items in F-90

    Dear Friends,
    I want to copy trading partner field from Vendor line item to other line items like Asset and Tax in T.code - F-90
    Client want to use Transaction type - 100
    Is it feasible?
    Thanks in advance

    try:
    1) substitution - tcode OBBH
    or
    2) open FI - menu FIBF tcode BF44
        - event 1120 or 1130
    A.

  • Payment Term from Vendor is not going to Freight PO

    Hello All,
    I am not MM consulting but I need to solve a problem.
    As we know when I save a shipment cost document SAP creates a automatically PO for carrier as the configuration.
    I have the payment terms registered in the Vendor Master (Carrier) but when I save my ship cost document and the system creates the PO the payment terms it is not appearing in the PO and consequently is not going to MIRO.
    How should I do to take the Vendor Payment Term to the Freight PO?
    Thanks
    Marcos

    Hi,
       Ensure that the payment terms is maintained in the purchasing view in MK02 for the same purchasing organization.
       If its maintained, the same will be displayed in the automatic PO as well. If its not copied, please create a normal PO in ME21N and check whether the payment term is displayed in header - Delivery / Invoice tab.
       If you are in old release, refer the note: 358506 - Auto Service PO Creation - Passing Values into the Function
       If you are using TM system, refer the note: 1897588 - Payment terms not copied from Vendor master to PO
        If the notes are not valid, then you may check for OSS notes or raise an OSS ticket to SAP.
    Regards,
    AKPT

  • Report for replacement stock to be recived from vendor

    Hi
    I HAVE ONE ISSUE ON ABOUT VENDOR REPLACEMENT STOCK REPORT
    EX:.. i have done GR for material-A qty 100...and ihave done MIRO for this ..pur.order..
    after 20 days i have return the materai-A ..qty 25..(without cancel the MIRO) with movement tuype 122..but this material should be return from vedor.(subsequent deliver).after some days or weeks ..( bcoz money has already paid to vendor)...like this we many materials ..
    for this... i want report for replacement material will be recived from vendor
    regards
    sesidhar

    Hi
    already i have done MIRO..
    then return to vendor qty 25..(through MIRO...w/o creadit memo
    thne again recive the replacement material ..through MIGO (subsequent delivery)
    in this case ..need to create credit memo..?
    if yes.. pls...send me procedure.
    regards
    sesidhar

  • Difference in GR qty from vendor wrt PO.

    Hello All,
    Suppose i order for 100 kg material from vendor A...But wen i received the goods it is 95 kg of material...
    So how to map this scenario in SAP..?...wht abt the 5kg of material..on whom it will be lying...excluding the delivery tolerence entry in master data..
    How the accounting entries will be...??

    hi,
    You can do the following way:
    1. Make the GR for the real qty 95 obtained and make the IR as per same qty ie. for 95
    or
    2. If you are done with the GR doc,, then make the IR invoice reduction for 5 quantities
    or
    3. Do IR for full qty and later create the credit memo for the remaining qty of 5...
    Hope it helps..
    Regards
    Priyanka.P

  • Adding Pre. account no. field from vendor master to PO header screen

    Hi,
    I want to add the field lfb1-altkn (Pre.acct.no.) to the purchase order header screen under org structure tab. This field has to contain the value from the Vendor Master Accounting Information View Prev.acct no. field.
    Please let me know how to proceed.
    Thanks and regards
    Durai

    you can not add to the Org tab but if you use this user exit MM06E005
    then you can add the field to the customer tab on PO header and add the logic in the user eixt to read the value from vendor master

  • Payment method not defaulting from Vendor master data

    Hi All
    I am running F110 payment run. In the Payment proposal SAP  is not pulling payment method from vendor master data for some invoice. we have like two payment methods , Sap is defaulting payment method for one type of payment method and not defaulting for the other...What could be the possible reasons?( for both the invoices We are not maintaining any payment method)

    Hi
    In F110 if payment methods are different from vendor master data and payment methods mentioned in parameters tab it will take payment methods from parameters tab, so that you have to give both payment methods in parameters tab so that it will consider both.

  • PO texts from vendor master

    Hi,
    when I create a PO using a vendor, after filling field Purchasing Org., Purch. Group and Company code, system copies a text but I don't know from where.
    In PO down the header texts I can read "Text adopted from Vendor Master (Purch.org.-spec.test text )", I cannot find it in vendor master....
    Could You help me ?
    Regards

    Hi,
    In MK03 please open your vendor go to purchasing data and  click on extras on the menu bar, and select text, here you will find purchase order texts, hope this is what you were looking for.
    Also check the PIR.
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jun 28, 2011 3:07 PM

  • Header Text copy to PO from vendor master

    Dear all,
    I am trying to pull data storeed in vendor master to PO for header text so that we don't need to repeat to each PO for the vendor.
    I tried to link this in "Texts for Purchase Orders" in SPRO ,But not able to link it
    B'coz it's not allowing me to add the object of vendor master
    so pl guide me how i link vendor master text to PO
    Regards,
    Vimlesh

    Hi,
    In customizing ->material management -> purchasing -> purchase order -> texts for purchase orders -> define copying rules for header texts, choose "header text" and click on text linkages. Here you can enter for source object "vendor master", and for source text choose vendor master header text.
    And in the FIX INDICATOR for text you have to maintain blank. then it will copy text
    This will copy text from vendor master to PO header text.
    Please check this and revert back if you need further details
    thanks,
    santosh

  • Header Text PO from Vendor master automatically

    Dear Friends
    This is regarding automatically adoption of header text in PO from vendor master. I am following these steps
    - Maintained customizing as MM>purchasing > PO>texts for PO >define copying rules for header texts .
    in this , select the text type ( this is the PO header text ) and click on text linkage and maintain source obj as vendor master and maintain the fixing as blank ( ie text automatically adopt in the target obj)
    -Then I wrote text (needed in FR lanugage) to respective vendor in purchasing view
    Now When I create a PO, system does not propose any thing under header text
    Did I miss anything.
    Please respond
    Regards
    SG

    Hi,
    1. First I assume the configuration settings are correct
    MM- Purchasing -- PO --Texts for PO --Define Copying rules for header text
    Here the target text type (in this case the PO text type ) i.e. sequence no. is assigned to the correct source object and text (in this case the vendor text type)
    2.If you logon to the system using the language option. i.e. logon id, password and language you get the SAP screens in that language. Now if you try to maintain vendor text in FR and create a PO, the FR Text would get copied to the PO. Now if you go back to the EN logon you ll still find the vendor text in FR. So it is definitely linked to the logon language.
    There should be another way for this too.
    This is an observation and may help you resolve your issue.

Maybe you are looking for

  • HP Laserjet 1536dnf MFP not in list of ePrint

    According to the ePrint-website, my My HP Laserjet 1536dnf MFP supports ePrint Supported LaserJet printers include:  HP Color LaserJet Pro CM1415 Series Worldwide X X HP Color LaserJet Pro CP1525 Series Worldwide X -- HP Color LaserJet Pro M1536 Seri

  • Sending email to user using the notification template in OIM 11g

    Hi all I have created a Notification Template using web console in OIM 11g. Iam able to access the contents from notification template in my java code. But iam not able to find the correct api's to send email to user using the notification template (

  • How do i recover a lost project that i didnt save correctly

    how do i search auto save files to find my project? where does final cut pro save projects?

  • Set an undefined Loaded variable's alpha to 0

    Hi, I'm trying creating a flash navigation bar that can be edited via a simple text file. I'm able to load my different variables properly but i also want to give the user the ability to remove links. I can simply leave the variable from the text fil

  • How to recovery the database from a complete backup

    I have a 10.2.0.3 database with archive log enabled. I do a cold backup of database every Sunday night. I shutdown the database, copy all the database files, control files and redo logs to a backup disk. Then the database started and running again. I