Scrap qty in planned order in COOISPI
Hi
When using COOISPI for planned orders the result does not show the field SCRAP.
The field SCRAP can be choosen in the result screen, but for planned orders it is alway zero (0).
When running COOISPI for process orders the scrap field is filled correctly.
Field in Planned order: PLAF-AVMNG
thanks
Vijay
Hi vijay.anukonti,
to see the quantity SCRAP in the COOIPI for planned order you need to set this value in the planned order (view Hdr - field Scrap Quantity). Otherwise it will came with no value.
Make sure you check the type of planned order and if it allows to have this info (for example type LA Stock Order).
Regards,
Felipe Tavares
Similar Messages
-
How can I set a fixed scrap qty on planned orders created by MRP?
During production of some specific subassemblies, destructive testing is done that requires us to scrap two pieces per production order. I know I can set an assembly scrap percent, but what I need instead is a way to set a fixed assembly scrap quantity that will get loaded onto every planned order created by MRP for these subassemblies. If we can't do this, we can't plan the correct order quantity and eventually end up being short of parts. I know we can set a safety stock or safety time, but I'd rather just plan the right quantities if possible.
Is there a user exit, configuration option, or master data setting that will allow me to do this?
Thanks,
RandyHi Randy
This can be solved by one solution. _You can try this._
You define the same item in BOM again with qty 2 nos. Double click on the item no. Then it will take you to item detail. There in Basic data tab page at quantity data ( Tick the fixed quantity. ).
When ever BOM explodes for the header material automatically The item will be exploded 2 nos extra.
Ex
The header is Mat X and items is Mat Y. While creating BOM for X give item Mat Y in item no 10. give the quantity as per the requirement.
And again give item Mat Y in items no 20. give quantity 2 nos and activate the fixed quantity tick as instructed above.
When ever requirement for Mat X is 100 nos. The plan order for Y will be 102 nos .
Hope this will clear.
Regards
J .Saravan -
Hi all,
When i confirm an order there is a field of scrap quantity. Suppose there is an order for 10 qty. Now while confirming the order i give in the yield field as 6 qty & 4 qty in scrap quantity.
Then i want to both Qty 10 qty (Yield + Scrap) should show delivered Qty(10 qty) in production order.
after that if i will do conformation then system should not take yield as well as scrap qty.
because, Order qty = delivered qty
Please guide me
Regards
JainashuHi Jainshu,
What your cleint is expecting is not correct. You should be able to convince him based on facts explained to you above. Scrap qty can never be a delivered qty.
In case you still wnat it, then i would suggest you not to book scrap at first place itself. Confirm all the qty as Yield only. Finally total production order qty is in stock, scrap it from unrestricted stock with 551 mvt type.
I am afraid but user exit wont help as your business process itself needs review.
Regards,
santosh sarda -
Bapi for sfg dependent dem,snp planned order qty, and ppds planned orde qty
Hi Gurus,
I am not much familiar with APO, so please help me,
Input details:
Field Value
Planning Version 000
Source Location * 1001 Single/Multi Value
Product * 1000061 Single/Multi Value
Production Planner * PRC Single/Multi Value
Start Date *
End Date *
o/p:
Source Location Date Semi-Finished Material Material Description SFG Dependent Demand SNP Planned Orders qty PPDS Planned order Qty Total SFG Variance due to Lot size Total SFG Variance reference to dependent demand
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT 340 412 420 8 80
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT
Is there any bapi to fetch the data as shown in o/p.
ThanksHi Phani,
Tryout the below BAPIs
IF10503 (object)
BUS10503
Regards
R. Senthil Mareeswaran. -
Not able to find the source requirement of MRP RUN-(planned order)
Dear All,
Actullay In MRP run system is generating 10000 qty in planned order but in MD61 there is only 3000 qty and no sales order requirement also exists for the same. And when i rerun the MRP by choosing option 3 in planning mode, then also it is generating the planned order for 10000 qty only but Iam not able find out the base requirement for that. Kindly suggest me the solutions.
Regards,
KrishnaDear balu
Check assembly scrap in MRP 1 view
and also check which lot size u r using
is it HB - replanishment up to maximum stock level
or FX - fixed order size
Kindly check
Regards
Sachin -
Not able to find the source requirement of MRP RUN-(for planned order)
Dear All,
Actullay In MRP run system is generating 10000 qty in planned order but in MD61 there is only 3000 qty and no sales order requirement also exists for the same. And when i rerun the MRP by choosing option 3 in planning mode, then also it is generating the planned order for 10000 qty only but Iam not able find out the base requirement for that. Kindly suggest me the solutions.
Regards,
KrishnaHi
In MD04 at bottom, you can see a button for pegged requirement, click there you will come to know the list of requirement. It is not only because of Planned independent requirement you maintain in Md61, it could be due to lot size in Material master, or if you have fixed vendor in sourcelist then it could be because of Minimum order quantity with the vendor, or it could be safty stock or reorder point maintained in Material master
Regards
Antony -
Where we enter raw material reservation qnty for planned order in monthwise
sir,
as per client requirement in every month raw material reservation quantity fixed for planned order in monthwise.
in sap Where we entere raw material reservation for planned order in month wise nov, dec, jan and whre its show.
is it possible after mrp run.can we check that raw material reserve stock in mmbe for planned order.
pl guide me step by stepDear Prakash,
1) in MMBE, you cannot see Reserved qty against plan order ( it is not a confirmed receipt )
2) the reserved qty which is shown in MMBE is against production order
3) only after converting plan order to production order ( Header material )
4) dependent requirements will convert into reservations
Regards
kumar -
Production order and planned order qty should not consider in MRP
Dear All,
i do not want to consider the previous month production order qty and plenned order qty (Nothing but WIP qty) in the current momth MRP, but the stock has to consider in MRP.
Example,
Before MRP,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
After MRP, the requirement should be as below said,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
Pld OrdQty : 1000 for 02.05.2008
For the above requirement ,i have done settings in the availabilty check like , for include planned order and include production order are "DO NOT TAKE IN ACCOUNT".
Even then also the planned order qty is generating for the "500" only.
please give the solution for the above said requirement.
thanx in advance
Regards
Srinivashi
MRP will always consider the prod order qty while doing nert req calculation.One thing u can do is TECo the prod orders and un MRP then it wont consider prod order qty.
The Availability check will check whether the components r avalaible or not based on ur scope of check
Reward points if useful
Amit -
Create Planned order based on qty in APO or SCM
Hi All,
I am working product view in APO or SCM system .
Requirement is create new planned order with sales order individual length and planned order pegged to sales order in APO system.
Example
Sales order has factor 4 and individual length 1000( 4 x 1000 ). Total quantity is 4000M.
We need to create 4 planned orders. Each Planned order has a quantity of 1000M.
Please help me and let me if any function module is there.
Thank you,
Durga VintaHi All,
Thank you so much for your response.
I have placed a X pushbutton in product view- > Element tab.
If the user presses X then screen will display with sales order information based on Factor
Example Sales order has 4 x 1000 = 4000M
Factor individual length
1 1000
1 1000
1 1000
1 1000
If the user selects the 1st and 2nd and presses save button. We need to create two planned order for sales order. Each planned order has 1000 qty.
Please let me know if any function module or BAPI in APO system.
Thank you,
Durga Vinta
Edited by: Durga Vinta on Jul 16, 2010 11:38 AM -
Planned order qty. based on usage probability in quotation
Hi ,
I created a quotation with 5 qty. and kept usage probability as 60%. I did the requirement transfer in MRP.In MD04 it generated a planned order of 5 qty. and quotation with 3 qty.
Is there any setting so that system should generate planned order also with 3 qty. i.e. same qty that of quotation.
RegdsHi,
After the req. transfer from quotation to MRP, go to MD04 & check the qty which has been transferred, is it 5 or 3 ?
If it is 3, then check in material master / info-rec if any min order qty / min. lot size is maintained. Also check the lot sizing procedure & safety stock if specified.
Regards,
Vivek -
Rounding of qty from sale order to planned order
Hi ,
There is sale order for 'X' material with qty 94,861meters, but when a planned order is generated the qty is rounding to 94,870 meters.
can any one give the reason, what are the things should be changed.
Regards,
somiraghuHi,
In IMG under
Production -> Master Requirements Planning -> Planning -> Lot-Size Calculation -> Maintain Rounding Profile
Regards,
Srilatha. -
Planned order qty. shodnt change after copying quotation and creating SO
Hi Guys,
In my scenario i am creating a quotation of qty. 100. Sytem generates planned order of 100 qty.After i copy the quotation and creates a sale order changing qty. to 50, the system is changing the planned order qty. to 50 whereas the requirement is planned order qty. must not change i.e. it must be 100.
Is there any setting for this.
Regards
Laxmikanthanswered
-
Restricting production order qty while the converting planned order
Dear all Hi,
I have a planned order for 10 qty. While converting it to production order the system is allowing me to increase the qty to more than 10 (eg 11 qty) & it is saving the production order.
But the clients requirement is that system should not allow the user to create the production order for qty more than palnned order qty.
Please help/suggest how to get this restriction from the system.
Thanks in advance.Hi,
If that is the case, then eliminate the Process of manual conversion of Planned Order to production order.
You can use the Program PPBICO40.
Schedule this Program as a background job, after the MRP Run.
Authorization management with strict monitoring will eliminate this type of process.
Regards,
Siva -
Check in Production order qty with ref to Planned order
Dear all,
Please suggest me, when i am creating a productin order with ref to planned order , so the order qty should not exceed the planned order qty.
How can i control this , please give ur valuable inputs on the same.
regards
Ravi AroraDear
If you are not particualr to conver the planned order to production order through CO40 , then you can control with the help of
Enhancement : PPCO0007 (Exit when saving production order)
Functional Module : EXIT_SAPLCOZV_001
Include : ZXCO1U06
Compare the Order header Qty with the sales order Qty If the production order header qty is more do not allow the system to save the production order..
Otherwise please check those out for your requirement :
Planned Ord. to Production Order User Exit (PPCO0005)
EXIT / BADI for Tcode CO40
Regards
JH -
Adding Total plan order qty to 2lis_04_p_matnr
Dear BW Gurus,.
I am appending a standard field (GAMNG - Total plan order qty) to the extract structure MC04P_0MAT.When i activated the structure,got it done but with warning that the Field GAMNG is not within the customer namespace...Now when i check the DS,the appended field is present with "HIDE" AND "FIELD ONLY" Options checked.When i try to uncheck them fields and check "select" field and save,it throws an error" THE OLTP SOURCE STILL CONTAIN ERRORS"..Would appreciate any help on this..
manythanks
arunHi,
Check by deleting the setup table for the DS 2LIS_04_P_MATNR.
If there is delta already running, then you need to do initialization once again for field GAMNG.
Vis
Maybe you are looking for
-
How do I update Album artwork onto my ipod.....
How do I update Album artwork onto my ipod after i have found the artwork and added it to my itunes? i tried to just plug in my ipod and sync. it but that didnt work.
-
How to connect the iPad to a VGAG cable
HHow do you cconnect an iPad or iPhone 6 to a VGA
-
Debugging of a subroutine pool.
Hi there, Does anyone knows if is posible to debug a subroutine pool? I'm trying to print a smartform of a RFQ using the function ME_READ_PO_FOR_PRINTING, but the program prints a different requisition a not the one selected. I want to capture the RF
-
Where can I find the Hyperion System 9 Downloads?
I'm specifically looking for System 9 Essbase and Financial Reporting components. Thanks! Randy Schmitz
-
Update SharePoint list with project finish date on Project.Updated event
Hello, I want to update a column in a SharePoint list with the project finish date when a project is updated on Project Server. My OnUpdated event handler is being called ok, but if I change the project start date Project Server runs an asynchronous