SD - SA Forecast Schedules  and JIT calls

Hi Experts,
We have a situation here - customer sends Forecast Schedules (for planning) and JIT calls through inbound 830 and 862 respectively. When 830 hits SAP system the schedules on forecast tab are replaced with new schedules in the existing SA from the schedules in 830. The customer then sends 862 - JIT Calls on a need basis.
The situtation here is Customer can only confirm a certain quantity in one JIT call for a given JIT horizon date. So customer ends up sending multiple JIT calls for the same material (most of the times they are in the same transmission). All these JIT calls need to be added as schedules in SAP irrespective of the similar existing schedules within a given JIT horizon.
The issue is SAP can only copy old schedules which are outside of the given JIT horizon when a new JIT schedule is added. Is there a way to handle this situation and add all the JIT schedules which are sent in different JIT calls regardless of JIT horizon.
Any help in this regards is highly appreciated. Points guaranteed for helpful answers.
Regards,
Gajendra
Edited by: Gajendra Bhatt on Apr 2, 2008 5:28 PM

Implemented an enhancement in the ODETTE logic using the new enhancement technique. This enhancement looks for a special rule assignment for the customer in OVA9. If the rule is assigned then it copies the existing delivery schedule lines to the new delivery schedule regardless of the new delivery schedule date.

Similar Messages

  • Forecast delivery schedules and JIT deliveries

    Hi Gurus,
    Got a question on sales scheduling agreements schedule lines. Our customer sends 10 weeks of forecast delivery schedules and 2 weeks of JIT deliveries. which one of these two are passed to MD04?
    Assuming only forecast delivery schedules are seen in MD04:
    Assuming customer sends forecast delivery schedule for week2 as 50. but in JIT deliveries he only sent 40 for that week. if only forecast deliveries are see in md04, then my forecast and planning quantity is 50 , but actually my JIT delivery is only 40.  AM I  producing 10 extra? that  means my planning is wrong?

    925,
    so in system it will show on 3/21 monday
    I guess this means that you are entering using a Day format rather than Week format.
    You have answered you own question already.  If the online SAP help, which you have read and reasonably paraphrased, is not clear enough to make you understand this, I cannot help you.
    JIT horizon is 3/23, Forecast is for 3/21. 
    As I stated before, even though it may in your mind represent a week's demand, it is still for one day.  There is no bucketing, nor time-based disaggregation, nor consumption.  It is just a scheduling agreement.
    You wrote
    am using MRP indicator D. that means within jit horizon, consider my jit quanity for requirements. and after jit horizon consider my forecast delivery schedules as requirements.
    .  This is a reasonable paraphrase of the SAP online help.  Do you believe this?
    Forecast schedule is for 3/21.  NOT for W 12/2011.  This is before the JIT horizon, isn't it?  What do you think will happen to the forecast schedule, looking at the last 'rules' you just wrote? and as stated in the SAP help that you read?
    Now you want to enter JIT schedules. 21/22/23/24/25/26.  JIT horizon is 23.  24/25/26 are after JIT horizon.  What do you think will happen, based on the 'rules' you just wrote? 
    I feel my time is being wasted when you keep asking me these questions, already having the answers explicitly stated in SAP oinline help.  Since you do not have access to a system, this cannot be a support issue, it is a evidently a matter of idle curiosity for you.  I therefore believe I will will move onto other forum questions, where there is a possibility that the questioners will get some business benefit from my answers.
    Best Regards,
    DB49

  • Scheduling agreement Fcst del schedules and JIT question

    We have a requirement of not sending forecast delivery schedules TOR to MRP from SA.
    Instead, we take this forecast delivery schedules and massage the data (add or delete) and then send it to MRP as regular forecast (PIR).
    so when the JIT schedules come, does the forecast get consumed with the JIT's in MD04?
    lets say, I got 100 pc for 2nd week of July 2011 as forecast delivery schedule from customer and I loaded them into MRP as PIR
    and I got JIT for only 90 PC for the 2nd week of july 2011.in MD04 will the 90 get consumed from the PIR??

    925,
    so in system it will show on 3/21 monday
    I guess this means that you are entering using a Day format rather than Week format.
    You have answered you own question already.  If the online SAP help, which you have read and reasonably paraphrased, is not clear enough to make you understand this, I cannot help you.
    JIT horizon is 3/23, Forecast is for 3/21. 
    As I stated before, even though it may in your mind represent a week's demand, it is still for one day.  There is no bucketing, nor time-based disaggregation, nor consumption.  It is just a scheduling agreement.
    You wrote
    am using MRP indicator D. that means within jit horizon, consider my jit quanity for requirements. and after jit horizon consider my forecast delivery schedules as requirements.
    .  This is a reasonable paraphrase of the SAP online help.  Do you believe this?
    Forecast schedule is for 3/21.  NOT for W 12/2011.  This is before the JIT horizon, isn't it?  What do you think will happen to the forecast schedule, looking at the last 'rules' you just wrote? and as stated in the SAP help that you read?
    Now you want to enter JIT schedules. 21/22/23/24/25/26.  JIT horizon is 23.  24/25/26 are after JIT horizon.  What do you think will happen, based on the 'rules' you just wrote? 
    I feel my time is being wasted when you keep asking me these questions, already having the answers explicitly stated in SAP oinline help.  Since you do not have access to a system, this cannot be a support issue, it is a evidently a matter of idle curiosity for you.  I therefore believe I will will move onto other forum questions, where there is a possibility that the questioners will get some business benefit from my answers.
    Best Regards,
    DB49

  • Delivery split through VLSP along with JIT Calls with AW Partner profiles

    Hi SAP SD/LE Guru's,
    I have one critical issue to resolve immediately in my implementation of SAP 4.6C system in multinational automotive industry. It's in the area of Delivery split along with AW - Duns number partner profile and JIT calls.
    Here is the scenario:
    1. JIT(Just In time) calls will be created through EDI based on the ship-to, PO Nos, Duns number.
    2. The requirements will be updated in Scheduling Agreements JIT Delivery schedule.
    3. Picking is done based on the requirements.
    4. Packing, Deliveries and Handling units are created: Note: Each handling unit is linked to one JIT Call.
    5. Based on the Shipments, Deliveries needs to be split into further sub-deliveries.
        Ex. One Delivery has two HU's. This needs to be split into another delivery so that one HU need to be detached from original and attach to new delivery. At the same time corresponding JIT call also need to be detached from original delivery and attach to new delivery. This can be done through VLSP : Subsequent split(Outbound delivery). Split profile: 003 - split based on Quantities.
    The issue: When executing delivery split using VLSP and split profile: 003, the system is terminating and giving short dump.
    The error analysis says that AW - Duns number is creating the problem. The short dump occurs in SAPLV05I in Function module: SD_PARTNER_UPDATE.
    There is an SAP note: 154766 related to this problem says that Partner header should be used only once in copy control.
    But in customization of copy control from Sales order to Delivery, there is no VBPA Partner header.
    I appreciate if you can provide solution for delivery split and resolve this short dump issue.
    Thanks,
    Murali Chintakunta

    In reference to this change in the Custom Reports... Better experience when exporting data - to prevent customer confusion when exporting data from Mac computers, we have removed the export to excel option and exporting in CSV format by default.
    What is the customer confusion we are trying to stop here? I've got even more confused customers at the moment because all of a sudden they can't find the export to excel option but know it exists if they log in on a PC?
    Mark

  • Forecast delivery schdule and JIT delivery schedule difference

    Hi All,
    What isthe difference between Forecast delivery schdule and JIT delivery schedule in JIT scheduling agreement (LZJ)?? 
    I am doing JIT Inbound process now. Is it necesary to update both the schedule lines(Forecast delivery schedule&JIT delivery schedule)??
    Thanks,
    Anbazhagan E

    Hello,
    Forecast Schedule updates your planning , i.e. in MD04 you could see system is planning for quantities updated in forecast schedule.
    regards,
    amol

  • JIT and Forecast Schedules

    Hello Experts,
    We are using Scheduling Agreement with Release documentation. The creation profile is having the following details
                             Aggregation horizon
    JIT Shcudule        Dialy Aggregation - 60days
    Forecaset Sch    Monthly Aggregation - 365 days
    Now we maintained demand on monthly basis in MD61 Say
    Oct '09: 100     Feb: 140
    Nov'09  : 110   Mar '10: 150
    Dec '09: 120  Apr'10: 160
    Jan '10: 130  May '10:170 till Sep'10: 210
    Created Scheduling aggreement with creation profile, Maintained the SA details in Source List. Now on MRP execution(on 28th Oct '09), the following are observations
    1  For the month of Oct'09 system created PR (not schedule line)
    2 For the month of Nov, Dec, Jan : JIT Schedule is created with delivery dates spanning monthly once
    3 In the Forecast release also, it is observed that for each month starting from Nonv '09 to Oct'09, schedule lines are created
    Can you please tell me
    1 How come PR is created for first month. If we need to create schedule line for the first month also,is any setting needed
    2 Eventhough dialy aggregation is 60 days for JIT, the scheule lines for Nov, Dec & Jan also created. Any views on this
    3 In Forecast Schedule Release, it is showing the schedule lines right from Nov'09. How come it is covering the schedule line period covered in JIT also.
    Request you to provide your inputs please
    Thank you,
    Best Regards,
    Ramakrishna Mangena

    Hi
    1 How come PR is created for first month. If we need to create schedule line for the first month also,is any setting needed
    Check the MRP control parameters and make it as 3- Planned order in Create Purch req.
    2 Eventhough dialy aggregation is 60 days for JIT, the scheule lines for Nov, Dec & Jan also created. Any views on this.
    Schedule line will be created based on the demand you have maintained it will not follow the aggregation. Aggregation of scheduled quantities determines the periods for which the schedule line quantities of a schedule line agreement item are to be consolidated
    3 In Forecast Schedule Release, it is showing the schedule lines right from Nov'09. How come it is covering the schedule line period covered in JIT also.
    Check whether you have maintained no aggregation till Novembed for the JIT scedule. Suppose if you maintained no aggreagation till 15th of November then Forecast will start from Nov 15th onwards.
    Since you are using both Forecast / JIT , Forecast schedule also will start aggregating the sceduled qty along with JIT. You can control this via tolerance check.
    Hope it helps
    Thanks/Karthik

  • JIT calls and JIT Schedule release

    Dear All,
    How to create JIT calls and also let me know how to release JIT schedules for delivery.
    Regards,
    Mullairaja

    Check this
    [Scheduling Agreement with Summarized JIT Calls |http://help.sap.com/bp_autov1600/Auto_JP/html/A67_EN_JP.htm]
    thanks
    G. Lakshmipathi

  • Using a JIT call with stock transport scheduling agreement

    Hi,
    I have a requirement to send forecast schedules for a stock transport scheduling agreement from procuring plant to producing plant. Production would be done in producing plant against these forecast schedules. Producing plant would only ship against a JIT call (pull trigger) from procuring plant and not against a forecast schedule line. Is there a way in standard SAP to achieve this?
    Thanks,
    Krishna

    I don't think so.
    You need to transfer the production forecast as demand plan in the production plant. Have a MTS planning strategy (like 10), then manufacturing is triggered by this demand plan, and goods are stocked in the production plant, waiting for the pull call from the sales plant.
    Don't forget to take care of the consumption of demand with STO (I think there's a note on this).

  • Jit Scheduling Agreement  and JIT customer

    Hi All,
    while I am creating new Scheduling agreement system asking to assign first JIT customer assignment before saving.
    Where we set this condition.
    Chidambaram

    As you have probably already discovered, the Partner Description stored on the Ship to line of the Sold to customer master links to the Partner Description in the JIT Customer on JITV and links to the Partner Description in OVAI (This last, so that you get the Forecast Idocs and the JIT Calls posting to the same SA)
    And in my experience, once you set up a LZJ type SA for a particular Ship to, you cannot change the Ship to, like you can do on LZ type SA's.
    If you need to abandon a SA that already has JIT calls posted, 1) create the new SA, 2) flag the old with "reason for rejection" and 3) use JITR to move the JIT Calls from the old one to the new one.

  • Scheduling Agreement JIT / Forecast calculating wrong

    Hello experts,
    I´m with a problem with JIT / Forecast.
    The forecast are calculating wrong values. For example:
    Cumulative quantity calculated: 584
    JIT schedule:
    DATE             TIME         Order Quantity       Cml. released quantity        Open Quantity
    06.01.2012     00:00     32          32                      
    10.01.2012     00:00     352          384                      
    13.01.2012     00:00     128          512                      
    17.01.2012     00:00     88          600              16
    Forecast schedule
    DATE             TIME         Order Quantity       Cml. released quantity        Open Quantity
    20.01.2012     00:00     112          112                      
    24.01.2012     00:00     224          336                      
    27.01.2012     00:00     128          464                      
    31.01.2012     00:00     200          664          
    The values of forecast are calculating by Cumulative quantity calculated that is 584 and I dont have any Open Quantity and in this case I need to have Open Quantity in Forecast.
    The forecast must not be calculated by the amount in transit
    Help me.
    Tks
    LFC

    Hi ashish
    Check the  planning delivery schedule tab and go to item data -> delivery schedule header and check wheather any proper information has been filled or not
    Regards
    Srinath

  • ME84 Outputs both Forecast and JIT when only Forecast is requested.

    We are using ME84 to generate Forecasts and JITs for MM type LPA Scheduling Agreements.
    When we generate only Forecasts (LPH1) a JIT (LPJ1) is also created, but with the same data as the Forecast.
    When we generate only JITs the output is a JIT (LPJ1) with the correct data.
    When we generate both, one LPH1 and two LPJ1's are created and one of them has the Forecast data instead of the JIT.
    I just got here, and when I asked the Purchasing people about it they said it always does that and they just throw the erroneous JIT away.  Now we want to implement Vendor EDI and we don't want the weird "JIT with Forecast data" to go to the vendor, but we do want the correct JIT to go to the vendor.
    I have gone through every Purchasing Output Control process I know of and can not figure out where this extra "JIT" is coming from.
    Does anyone have any ideas?
    We are on ECC 5.0.
    Thanks in advance.

    For anyone who seeks answers to this topic in the future:
    I turned the problem over to SAP and they found the cause.
    SAP Note 337750 says "In LV61BNNN ('Output requirements'), Include LV61B111 has been deleted inadvertently.".  LV61B111 is the code for "Requirement 111" which limits JIT output to be only for JIT schedules.  That code was not in LV61BNNN in the Production system  (It WAS in both the Q and D systems,  and JIT behavior did work properly in Q but not in Production).
    The simple solution was to run SAP program RV80HGEN in the Production SAP System, after which the Include was there and the problem is solved.

  • Schedule agreement-JIT and creation profile (are necessary to maintain)

    Hi Friends ,
    I am doing schedule line agreement in this way.
    1) Create SA agrement -ME31L
    2) Maintain schedule lines -ME38
    3) MIGO-
    4)MIRO
    That is working.
    A ) But then why it is necessary to maintain in material master under purchasing tab- JIT
    and
    B) in vendor master -Creation profile
    Please can u explain me A and B
    Regards,
    Mahesh.

    Hi Mahesh,
    Maintaining JIT in material master is necessary only if you wish to Use JIT scheduling agreement schedule lines, if you are fine with only FRC schedule line, then you don't need to update this field. This is a control on the material level, like you know if a certain material can't be managed on a JIT level then you will not use it, so JIT agreements can't be created for it.
    I don't feel Creation Profile is mandatory for vendor master, because you can opt to enter the creation profile in the Scheduling agreement additional data. Creation profile basically has a lot of control function, here isthe abstract from SAP Help
    The creation profile determines:
        Which event triggers the creation of a scheduling agreement release (changes involving the lines of the overall schedule and/or the reaching of the next transmission date)
        How the delivery dates are shown (aggregation and release horizon)
        Whether Backlogs and Immediate Requirements are determined and shown in the scheduling agreement (SA) release
        Whether a tolerance check is carried out for SA releases that are created due to changes to the overall delivery schedule in the system
    Regards
    Chandra Shekhar

  • How to create inbound JIT Call Manually?

    Hi All,
    Currently I am doing SAP JIT configuration. I have created the JIT Customer.
    Now I need to get a JIT call to determine the schedule lines in the scheduling agreements. In real scenario, JIT call comes through Idoc from the customer side.
    But I need to create JIT Call manually to do the configuration. So , How to create it? Is it Possible?
    Thanks,
    Anbazhagan E

    Use transaction JIT1
    Put in the Sold to customer number and the Ship to Partner description, just like in the first section of JITV, and put a unique value for this JIT Customer is the "Ext. JIT Call No." field.
    When you hit enter you will get the Call Components grid or both the Component Groups and the Call Components Grids (depending on what Maintenance Mode you selected on JITV).
    Let's assume your Mtce Mode = 3 - Discrete Material / Summ JC. Therefore you only get the Call Components grid on transaction JIT1.
    You need to fill in certain fields at a minimum, more depending on the JIT Call Configuration.
    Bare minimum, you need:
    1) Customer material or Material (if you fill in one, when the program finds the matching LZJ SA, it wil default the other)
    2) External Status (ex. ECRE or CR or whatever External status you have defined and linked to the CREA action in configuration)
    3) Planned Ship date or Planned Requirement date
    4) Quantity
    If when entering the Customer material or Material, the Sales Document and Sales Item is not populated, that means you do not have a matching LZJ type SD scheduling agreement in the system. Or the data you are entering on JIT1 does not exactly match.
    The SA must be there before you can do JIT1.
    The JITV entry must be there before you can set up the SA.
    Hope this helps at a basic level.
    You may need to enter additional data at the header of the Inbound JIT Call, or at the Call Components level, depending on a particular scenario or to correctly find the SA.
    If you have EDI that has come in and you want to create a similar JIT Call. Use the [Propose JIT Call button]
    On the 1st screen, enter the Sold to, Partner Desc and new JIT Call number.
    When you get to the 2nd screen, click the Propose JIT Call button, and enter the JIT Call you want to copy from. You just need to enter the External Status and new Planned Date. The materials and quantities and other fields get copied from the source JIT Call.

  • Function Module to create Delivery with JIT Calls

    Hi SAP Guru's,
    We are working on SAP 4.6C version.
    I am looking for a function module to create delivery with JIT Calls.
    We are currently using the SAP standard function module "SHP_VL10_DELIVERY_CREATE" to create Delivery with JIT Calls. Each JIT Calls has apx 60-80 materials in it and each material refers to a unique Scheduling Agreement. This function module is taking very long time in production server to create delivery, it does not take much time in dev or quality server.
    We have JITV setting profile (For Sold To Party and Partner Description Profile) set as RELACE (to summarize the line items in JIT Call).
    Is there another function module that we can use to create delivery with JIT Calls?
    Thanks in Advance,
    Amit

    Hi there,
    There is no such function module.
    Regards
    Sanju

  • 830 Function Code in IDOC posting only in Forecast Schedule of Agreement

    Hi All,
    I am trying to post an 830 IDOC against a Scheduling agreement. Each time i post it is updating the forecast schedules of the agreement. In our case we have IS auto version and i want the IDOC to update the JIT schedules. Can anyone tell me what i need to check or rectify in order to achieve this.
    Priyanka

    Hi Priyanka
    When you are posting DELINS or DELJIT against your scheduling agreement; check for the following to ensure what schedules it will update.
    In the IDOC; segment: E1EDP10 and field: SCREL. this will have values like 02 or 03.
    If the value in this field is = 03; then your IDOC will update the forecast schedules (as it is happening currently).
    If the value in this field is = 02, then your IDOC will update the JIT schedules of the agreement. This is the key for posting the schedules. So please check this value.
    Hope this helps
    Regards,
    Syed Nasir

Maybe you are looking for