Secondary resources

Hi!
I'm trying to find a table with information of a process order's secondary resources.
This is for a report which is to show values and quantitys of the components and sec.resources of
the process order, planned quantitys and actual used quantitys.
BoR
Fredrik

Hi
You can find it from any one of the following tables:
CRCA      Work Center Capacity Allocation
CRCO      Assignment of Work Center to Cost Center
CRHD      Work Center Header
CRID      CIM Resource - Entities
KSSK      Allocation Table: Object to Class
T705R     Assignment of work center to subsystem link group
Thanks
Saravana
Reward if useful

Similar Messages

  • Secondary Resource in the operation "SETUP" of a PPM

    Hi experts,
    I need to record directly in APO (SCC03) a PPDS PPM with a secondary resource which should be considered in the setup activity
    I recorded the following:
    Operation          Activity          Activity Type          Mode           Resource
    0010                    0010                    S                         1          WLINE_1
    0010                    0010                    S                         1          SECONDARY_RESOURCE
    0020                    0010                    P                         1          WLINE_1
    In the activity 0010 (operation 0010) I placed a flag in the field "setup activity"
    When I tried to actívate the PPM,  the system sent me the message:
         OPERATION 0010 ONLY CONTAINS A SETUP ACTIVITY
    How I can to solve this issue?
    How I can include a Secondary Resource in the setup operation of the PPM?
    Regards, 

    How are you logging into the system? Are you using the Fingerprint to login or the password in Client Security Solution (CSS)? Remember that Client Security Solution controls your settings for the Password Manager (Security settings for Fingerprint reader data are controlled by CSS also)
    You can go to Start -> All Programs -> ThinkVantage (or Lenovo Care) -> Client Security Solution
    If you have CSS version 8, you should see a Menu Bar at the top.. You can click on Advanced , then Reset - this will allow you to clear all password data from the Password Manager.
    In addition to the "Reset" option, you also have the ability to "Manage" your settings. Use this to make changes to way you log into Windows at boot. You should have 5 options listed under "Manage". This also allows you to decide whether or not to use the Fingerprint when signing on.
    If you are trying to clear you fingerprint data, that can be done from BIOS
    F1 -> Security -> Fingerprint -> Erase Internal Fingerprint Data -> "Yes" to confirm.
    You should also take the time to read this Guide on Fingerprint Reader Tips below:
    http://www-307.ibm.com/pc/support/site.wss/document.do?lndocid=MIGR-59650
    Also read over "Client Security Solution 8.0- Considerations"
    http://www-307.ibm.com/pc/support/site.wss/document.do?lndocid=MIGR-66965
    I hope this will provide some help.
    Regards,
    Mark
     Do NOT PM me with technical issues. Post in the forum for assistance. Thanks

  • Wrong secondary resource Transferred to iDOC

    Hi,
    For a Master recipe we have a mainatained a secondary resource for the operation and the resective Prcoess order  contents ( operations, sub operations, qtys..etc ) will be moverd to the RTCIS ( ware house management ) system through an iDOC via a customized report. when we checked the iDOC it has picked  a wrong sub-operation where as the Process Order still have the correct one.
    We are already looking into the code of the custom report. but want to know if we have maintained anything wrong for the sub-operation asseignment as this happens only for few Process Orders .
    Thanks,
    Nagesh.

    There is a Z Program which we have corrected.

  • Table name for secondary resources

    Hi!!
    I would like to know the table for Secondary resources which we assign in Master recipe.
    Best Regards,
    Ajit Dubal.

    Dubal,
    MAPL - routing master
    PLKO - routing header table
    PLPO - routing dtl
    CRHD - work center table
    AUFK - Prod order header
    AUFC - Prod order detail
    Regards,
    Sankaran

  • FM for Creating secondary resource(CRC1)

    Hi,
    Any one knows the function module for creating secondary resouce and the tcode is CRC1.
    Regards,
    Raghu

    Hi,
    Check these FM's
    RPM_CREATE_RESOURCE             Create a new resource
    RPM_CREATE_RESOURCE_DATA        Create a new resource
    Regards,
    Jyothi CH.

  • UCCX 8x. - Agent Personal Queue Question - Dequeue to Overflow verses add secondary resource

    All, 
    I am writing a script for Agent Queue on UCCX 8x, and I want a secondary agent to be able to answer calls for this Queue when the primary Agent is on Break or Logged out .
    I am thinking two options:
    A. Dequeue to Overflow Queue
    B. Adding a secondary agent assign skill  level 10 to the Queue instead.........but the issue here is that this secondary agent belongs to another queue and would need to have a choice whether to answer calls from the other Queue.
    What do you think is the best option?

    What if you set queue priority better so the backup agent always answer this queue first and if it is empty he will answer the second queue till the other agent is available? 

  • Secondry Resource confirmation

    Dear All.
    We are using Process Order, for some phases we have assigned secondry resources. If my yield quantity is 100 Kg then i require 10 Hr in phase & also in secondry resources while confirmation of phase if i do partial confirmation for 50 Kg system automatically calculate activity of 5 Hr like same if i confirm secodry resource there is no option of yield quantity so that it always consider as 10 Hr so please suggest is it possibel to active yield field in confirmation of secondry resources for calculating activity???
    Regards..

    Dear Dev123,
    If my understanding is correct, then this secondary resources are the additonal resources that are required for processing an
    activity when an operation /phase is carried.The system only helps in capturing the cost for performing additonal activities and
    not any yield against the secondary resources.
    If my understanding is correct then the system does not considers the secondary resources even during order scheduling.You
    can check the same in the time calculations during order scheduling.
    You can check the same behaviour in the T.code COR6N/COR6.
    Regards
    Mangalraj.S

  • Difference between Resource and Workcenter

    Hello guys,
      i know this question is addresed before, but i am not satisfied with their answers, and even i looked in SAP HELP but i didn' get the answer.
       I know some of the differences that they use different category, and in resource we use phases instead of suboperation,and in resource we can use secondary resource.
        So guys could u help in finding the differences between them.

    WorKCenter is the terminology used in Production (ex. Automotive, High-Tech) Industries.
    Resource is analogous to WorkCenter, but the terminology is used more in Process Industries (Ex. Chemical, Pharma etc.)
    To Clarify futher,  at SAP functionality perspective Sub-Operations & Phases are the functionalities that come with Routings &  Recipes which are used in PP & PI Industries repectively.  
    Hope this helps.
    Regards,
    Bharat.

  • Resource

    Dear SAP Guru's,
    in a process industry production takes place in different stages.
    For a particular stage let us say Blending there will be 5 phases where we use different resources.
    Instead of creating 5 resources in recipe i wish to go with one resource called blend.
    At the same time i need to capture reporting data of resources of individual phases also.
    How can this be achieved.
    Should i go for secondary resources.
    System by default will pick the resource assigned to operation for all the phases under it.
    Kindly Give ur inputs
    Thanks & Regards,
    Karad D D

    for each operation in your routings you can set a "Control key".
    check it out.
    if you need to customize those keys goto tranz. OP00

  • Resource report

    Dear All,
    in a process industry production takes place in different stages.
    For a particular stage let us say Blending there will be 5 phases where we use different resources.
    Instead of cretaing  5 resources in recipe i wish to go with one resource called blend.
    At the same time i need to capture reporting data of resources of individual phases also.
    How can this be achieved.
    Should i go for secondary resources.
    System by default will pick the resourceassigned to operation for all the phases under it.
    Kindly Give ur inputs
    Regards
    Jeevan

    closed

  • PP Issue - Resources VS WorK Center

    Dear PP Guru,
    As i know for resources , there's secondary resource could allocated for costing purpose.
    Thru resource network, you can define the network as the work center and the assign an specific resource (work center) at order release.
    Can anyone tell the similarity & different in term of resource vs Work center ?
    TQ

    Dear,
    Resource & Workcenter are approximately same. Resource are assigned to work center category 008 (Processing unit). This is inturn assigned to the Task list type 2 (Master Receipe). Work center (CR01) is deifned for work center ct 001 or 002 and assign it to the routing. And in simple language work Centers  use in routing of PP (discreet manufacturing), and resources use in master recepies of PP-PI (proces manufacturing).
    Hope clear to you. There is no other difference.
    Regards,
    R.Brahmankar

  • Mapping labour resource in ppds

    Hi
    I want to map labour resource with labour time fetching in order at the time of scheduling in ppds. Please help me how to achieve this..
    my schenario is as....
    normally i have 50 labour resources,but due to some problem only 30 labour resource came....how i can utilise these 30 resources so that my machine utilisation will be maximum and i will be able to meet my requirement...
    please let me know for further clarification...
    Regards
    pradeepta

    Hi Santosh,
    You have to maintain one more capacity with category 002 in ECC with available capacity & formula to calculate the capacity. When you transfer this resource to APO apart from the machine resource, labor resource will also be transferred to APO.
    When you use this resource (machine) in recipe and transfer this recipe into APO, it will reflect as secondary resource in APO PPM.
    When orders are scheduled for machine you also get the requirement of labor.
    Scheduling formula does not contain the parameter for labor; hence the primary resource & secondary resource consumption are same.
    If the labor houru2019s requirements are different than the processing time of operation, you can try to change capacity consumption data manually for secondary resource in PPM.
    If worker are not required in to give their full attention to one machine only but a pool of worker operate a couple of machine which required more attention at certain movements i.e. loading/unloading or set-up. you can create a pooled capacity in ECC system, which can be assigned to may work centers. The capacity is transferred as resource to APO and modeled as multi-mixed resource (no-dimension).
    Regards,
    VD

  • Process order operation

    Hi
    In Process order we are using Operation & Phases in master recipe.
    Standard values are giving to phases only.
    Individual Confirmation (COR6) are performing using Phases only..
    Process instructions are also giving to phases only.
    For  creating phases operation is required( superior operation)
    Just i want to know  where these operations will be used in a process order  other than this.
    I want  to know the difference between Primary & Secondary resource and their application in Process order..as these terms are not there in REM/Discrete Mfg..
    Regards,
    srihari.

    Hello Shrihari,
    What you have observed is right.
    In process order processing we need to use the phases instead of operations in production order eg. when you want to do the partial confirmation, you need to do it for the phases and not the operations.the GI of components( if attached to the Phase )will then take place at that time.
    About primary and secondary resources I can give you a practical example.
    If you consider a washing machine as a resource then it has two parts the Wash tub and the drying tub. You can consider the washing machine as the primary resource and the washing tubs and drying tubs as secondary resources of the washing machine.
    Hope this helps you.
    Award points if benefitted.
    Hemant

  • Process order activity confirmations

    I have a requirement to write a program which automatically confirms the secondary resources in an opeation, for a specific AUFNR. The manual confirmation is done using COR6N.
    I am fetching all the relevant fields from gt_phase parameter of the bapi bapi_procord_getdetail. Now I have to do the calculations of each standard values for activity types mentioned in the secondary resources. If the total quantity to be produced is 100 kg, and if the yield is 5 kg, then I am calculating 5% time for each activities mentioned there.
    For viewing all the operations and secondary resources, the tcode is COR3.
    Now my confusion is, how should I confirm these activitis. THere are two function modules, BAPI_PROCORDCONF_CREATE_TT and BAPI_PRODORDCONF_CREATE_TT. Which one is the right one? Also, how will I pass my calculated values for activities. If we are specifying the yield parameter there, do we need to do the calculation really? Please help me...

    Function module documentation BAPI_PROCORDCONF_CREATE_TT is for Process Order.

  • Work Center  takes only 6  activity types

    Hi
    I    have   6  types of labor  activity type  ( L1 to  L6 )  ,  1  machine and  1 set up.  Total  8  activity  types.
    Now   if   the  planned  labor  is  eg  L1,  the  actual  may  be  L6.  But    I  cannot  assign     all   6  labor  type in the  work center.    Work center  allows  only  upto  6  activity types.
    I   checked  in  HR  module,  where  in   CAT2  we  can   record  ACTUAL  activity type  /  order  / employee data.  This can be moved to  controlling.      But  when  it  is  planning,  then  I  dont  know.
    How  can  I   accomodate  all  6  labor  type in the  work center.
    Thanks
    kamala

    Hi Kamala
    If you are in a production order scenario -
    You will have to create 2 work centers... One for Labor and another for Machine/Set up... there by you will have 2 operations in routnig
    If you are in a process order scenario -
    You can do with one single work center... This will accomodate 6 act types..
    Apart from work center, there is a concept of "Secondary Resource" in Process order scenario, which can accomodate your other 2 act types...
    Regards
    Ajay M