Dear gurus,
A product is produced at a particular workcenter based on certain chrecteristics.Suppose the same product is to be produced with certain other charecteristics other workcenter has to be selected.
How to map this .kindly suggest

Hi ramesh
Option 1 ( for Different lot size )
Create Two Routing for Material X.  One with first work center and another with other Work cneter. And create Two prod versions  ( T code C 223 ) one with Routing 1 and BOM and another with Routing 2 and BOM. You have to differentiate the PV by lot size ( it is must ).
Then in material master of material X . MRP 4 view give selection of BOM only by PV.
While running MPR the system will automatically explode the required PV with Routing for that LOT.
Option 2
You can choose alternate sequence option with manual selection during conversion of plan order to prod order.
Create alternate sequence in Routing and do setting for manual selection in OPL8 ( order type dependetn parameter).
Option 3 ( If the lot size is same ie., you cannot differentiate the lot size.)
You have to change manually in Prod order in ( CO 02 ) Before release of Prod order.
Hope this will clear
Regards
J .Saravan

Similar Messages

  • Urgent : Automatic Selection of  work center

    Dear All,
    Good Morning,
    please provide me valuable input to accomplish the business scenario,
    the scenario is
    1.There are 16 NC T-Bending Machine with different capacity.
    2. The Client wants to select the workcenter automatically if the 1st workcenter is overloaded i.e 2nd workcenter should be selected by the system
    Again,if 2nd workcenter is overloaded then system should select 3rd workcenter and so on..
    How I can make it possible.
    I am trying the Alternative sequence ,will it works to achive the requirement .
    please give ur valuable inputs.
    Thank in advance,
    Vijay Mankar

    In capacity leveling transaction, enable "date entry when dispatching".  Then, every time you dispatch operations, you will get a pop-up for date entry.  Luckily, this pop-up also has a field for work center - so you can change work center also (with or without date changing).
    We are using this method extensively.  Start transaction with all the work centers that you want to be considered.  Then, just select all the orders and dispatch.  In pop-up, change work center to the next in list.  So, some orders will get dispatched to that work center, and after its capacity is fully booked, the balance orders will fail to dispatch.  Once again, select all orders (left in the order pool) and dispatch, and change work center in pop-up.  You will have to do this as many times as the list of work centers OR till all orders are dispatched (whichever occurs first).  Takes just about a minute per work center and works perfectly.
    - Chetan

  • Select the work center in sales order

    Hello gurus,
    When I create a saler order, the system create automatically a service order with the corresponding data which are reported in transaction OISD for the service material. The key of this table only permits a work center for one material service and plant. And it is impossible to add more work centers for the same service material and plant.
    So I need to be able to choose the work center when I generate the sales order. How can I get it?
    Thanks in advance

    Dear Venkat,
    Try These tabels:
    MARC Plant Data for Material
    /BEV1/RBVBAP                     Sales Document: Item Data        
    COER                             Sales Order Value Revenue        
    VBAP                             Sales Document: Item Data        
    VSVBAP_CN                        Version: Sales document: Item data
    VVBAP                            Sales Document: Item Data        
    GLPPC                            Profit Center Accounting: Plan line items
    GLSPC                            Profit Center Accounting: Line Items    
    Regards,
    Naveen.

  • Selection of Operation on Work center

    Dear all,
    In repair order ,when iam performing Repair Auction i need to activate Operation selection using work center setting.
    Where can i activate this Functinality *so that i can choose from pop-up screen of particular  the Work center and its Operations.
    Thanks in Advance
    Regards
    raj.

    Hi,
    Have you selected the Operation selection at the given node,
    Plant Maintenance and Customer Service -> Maintenance and Service Processing -> Maintenance and Service Orders -> Functions and Settings for Order Types -> Default Values for Task List Data and Profile Assignments
    Then try processing. Hope it will solve your issue.
    Regards,
    N.Nagaraju

  • Function Module to get a work center's capacity requirements (load) within a given period

    Hi all experts,
    Currently I’m doing a capacity summary report similar to CM01, but with a summarized capacity availability and loading for a period.
    Selection Parameters: Work center range from and to, Period from and to
    List Format: Work Center, Avail Capacity, Loaded Capacity, Free Capacity, Load %
    I have found a standard function module (FM) to get work center's available capacity for a period, but still facing the challenge to find a FM to get a work center’s capacity requirements (load) in a period.
    I have read through all the related threads from the web, and tested the recommended FMs, but still cannot get a right result.
    Please help to provide some leads for a FM or the logic.
    Best Regards
    Philip

    Hello Philip
    The following function modules should be useful:
       - CY_PRIMARY_SELECTION            - Function module for selection of orders for the work center
       - CY_SECONDARY_SELECTION          - Check for additional criteria
       - CR_CAPACITY_AVAILABLE_PERIODS   - Reads the available capacity from work center
       - HR_PERSON_READ_TIME_INFO        - Reads the available capacity from person (modification)
       - CY_GET_PART_CAPACITY            - used only for the first period to read backlog
       - CY_LOAD_DISTRIBUTION            - Distribution key
    Please observe that these are simple function modules, not BAPIs, That means, they were developed to be used on the SAP internal programs and they are not supported by SAP when used in custom programs.
    BR
    Caetano

  • Standard Values in Production Order for Alternate Work Center

    Hi SAP Expert,
    I would like to find out whether there is possible solution for the requirements as below:
    e.g.
    >>> Routing for Product A only has one Operation 0010.
    >>> 4 Work Centers/Resources (A,B, C, D) can be assigned to run this operation where all these 4 Work centers/resources are having different capacities (Setup, Labour, Machine hour & Electricity are different).
    >>> Out of these 4 work centers, only one work center will be selected (Selection criteria will be based on the capacities & availability).
    >>> In my current setting, only one preferred work center (A) is maintained in the routing for operation 0010.
    Issue:
    >>> If I select the work center B manually in APO during the planned order creation, the Production Order created will be tied to work center B but the standard values captured in the Production Order are still referred to the standard value of A.
    Question:
    1. Is there any way I can maintained in the routing so that it will captured all the different standard values for each work centers?
    2. If the answer is yes for Q1, then can the SAP auto populate the correct standard value into the Production Order according to the work center I selected before the planned order is converted into Production Order?
    Thanks.
    Regards,
    Hooi Chia

    Hi,
    You can use alternative sequence in routing and mainain three different sequence for all 4 workcenter.
    At APO side you can maintain priority for alternative sequence in PPM/PDS.
    Now when you execute the scheduling Heuristic depending on priority and capacity workcenter will be assigned.
    Regards,
    Vishal

  • Work Center in Maintenance Order.

    Hi ,
    Due to Process Change some maintenance work centers become obsolete.
    Can it possible to hide or work center do not see in F4  help in Maintenance order.

    Dear Ashu
    Jogeswara Rao Kavala input is the most suitable in your case however another work around would be :
    If you are using the "Person Responsible" for your work center, then remove the entry from the person responsible for such obselete work center as they will not be used any more and no person will be responsible for their maintenance and co-ordination. This will help in all other reports selection and analysis also.
    While searching for work center(F4 Screen), default the tab "Person Responsible".Now when you select any work center based on person responsible, automatically that work center will be excluded from your selection screen.
    Pre-requisite: You use Person responsible assignment in ALL work centers....
    Other way would be to set deletion flag to this work center so that even if they are included by user without looking into F4 help, system will prevent those work center from including in the work order for further processing.
    Hope this helps
    Regards
    Murad..

  • Work center in material determination of DIP profile

    Hello,
    the source of our DIP-Profile is 0001 Acutal costs - line items.
    We have the requirement to use the work center in material determination as criteria.
    But in DP90 we get material determination error.
    The issue is that in the failed combination no work center is available.
    Why can´t the DIP find the workcenter we used in the service confirmation?
    Thank you
    Kind regards
    Manfred

    Hello,
    after above setting have tried this in ODP1
    select The Work Center in Chr.then >select Source on left hand side  ->Select the Actual cost Line Item>select Material determination-->Select Material for which Transfer Cost and Quantity -->Marked the Check Box Material determination and Individual
    Also please let me know Which Control Key you are using in service order??????
    Regards,
    Rakesh
    Edited by: RAKESH ASHOK MANE on Sep 9, 2010 3:16 PM

  • Dyanmic work center selection in production order based on material

    Hi ALL,
    We’ve a business requirement to support the following functionality.
    There are four similar type of milling machines say MILL1 MILL2, MILL3, MILL4, we create a single work center called MILLMC by specifying total capacity of four milling machines in the capacity header screen of work center with 4 individual capacities. And we mention work center MILLMC in the operation of routings for respective materials.
    However, during production order creation, there needs to be provision for detailed planning of work centers as per the following requirements
    In production order, some operations can be performed on any one of the machines MILL1 MILL2, MILL3, MILL4, so provision needs to be there to enter exact machine on which it is performed in the production order operation after the details are copied from respective routing during production order creation.
    In production order, some operations can be performed on only MILL3, so system should select only MILL3 in the respective operation of the production order
    In production order, some operations can be performed on either MILL1 or MILL2 or MILL4 and not on MILL3, so system should not select MILL3 in the respective operation of the production order.
    Please provide your valuable feedback to support the above requirements.
    Regards,
    Satya.

    Hi Satyanarayan,
      Please do refer to the below document. I think the same concept can be used for work centers as it is used for resources in PI industry.
    Resource Classification in Master Recipe for Planning
    Regards
    Kalyan

  • Work center selection during UD

    harhe e Hi,
    We have the following scenario,
    Production guys confirmed order confirmation or make backflushing confirmation to update the WIP/FG stock,
    then quality cleared such stock through posting to unrestricted or blocked stock or rejection store location,
    Quality person requires during UD posting ,work center/Machine selection should be there in QA32 transaction,
    so that the analysis could be made for the work center,
    Best Regards,
    Devendra

    Using Inspection Point assignment, you can record the Work Center / Machine.
    But with Inspection Point, you can't have F4 selection option in standard. You have to type the Work Center code manually which may prone to error.
    You can check for some user exits to define Sub screens to pop up.
    QEEM0029  User-Exit for Characteristic Overview Subscreen
    QEEM0030  User-Exit for Subscreen: Characteristic Single Screen
    QEVA0004  Exit for changing information line in usage decision header
    QEVA0005  User subscreen for displaying add. data for usage decision
    QEVA0006  Entry to usage decision transactions

  • The dynamic selection for profit center in FBL1N isn't working

    Dear all,
    I have one one issue regarding FBL1N.
    The dynamic selection for profit center in FBL1N isn't working.
    If we enter profit center, we don't get any value.
    As per developer after debugging, table BSIK is not getting updated, hence values are not updating in the report.
    Please let me know, any configuration is missing.
    BR,
    Shailendra

    Try BSEG and see if its there for the particular doc. If its not there its a functional issue, you have to capture profit center at the time of entry. You can either make the profit center field mandatory or substitute it at the time of document generation. Consult your FI consultant. If u have activated New GL features the profit center may me in table FAGLFLEXA. but i don't think u can get the profit center from this table for your purpose, you may need to develop a zreport.
    And its not BISK its BSIK
    Edited by: Harisankar S on May 4, 2010 3:05 PM

  • Work Center Required on Selection Screen

    Dear All,
    My client has required work center as selection criteria on usage decision screen.
    Thanks to all.

    Dear,
    Try to use the QE01, QE505, here maintain the required operation and work center and give the USage decision.
    Please check and revert.
    Thanks,
    Hrishi

  • Selection of technical objects by work center and plant

    Hi there,
    I want to select functional locations and equipments that are diretly linked to a workcenter which you can see in the location tab in the standard-transactions.
    How can I select this data the way from work center (and plant) to the technical objects? Which tables I have to use??
    Kind regards
    Jens

    Try using Function Module ITOB_FUNCLOC_READ_SINGLE.

  • Maintaining work center list in Capacity Planning: Selection List in CM01

    Hi,
    Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
    Thanks a lot!
    Min

    Mandy,
    Couple of combinations you should check,
    1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
    2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
    3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
    Hope this helps....Reward your points and close the thread if so,
    Regards,
    Prasobh

  • Work center wise production order infomation report

    Hi all,
    i have a requirement that workcenter wise (with date) production order information with quantity details (plan and actual).
    Eg: My production order quantity - 40 nos. (it takes 4 days to finish).
          i have three operation in production order.
          my order scheduled start date - todays date.
    In standard, when enter my first operation work center, system showing production order and its quantity (40 nos) . but i need to split that order quantity in report.. means on todays date for particular production order - order quantity = 10 nos.
    Clent want like that (with quantity break) report..
    Any standard report ???
    If customization.... How it can be mapped in SAP.??
    Thanks in advance

    Hi,
    You can use the FM COIS_SELECT_ORDER_DATA_READ.
    CALL FUNCTION 'COIS_SELECT_ORDER_DATA_READ'
          EXPORTING
            iv_prod_order_sel       = lv_prod_order_sel
            iv_proc_order_sel       = lv_proc_order_sel
            iv_planned_order_sel    = lv_planned_order_sel
            iv_rem_objects_only_sel = lv_rem_objects_only_sel
            is_objects_to_read      = ls_objects_to_read
            it_parameter            = lt_parameter  "General Structure for PARAMETERS and SELECT-OPTIONS
            it_status_hdr           = lt_status_hdr
            it_status_opr           = lt_status_opr
            it_status_cmp           = lt_status_cmp
          TABLES
            ct_ioheader             = lt_ioheader
            ct_ioitem               = lt_ioitem
            ct_iodocl               = lt_iodocl
            ct_ioopdocl             = lt_ioopdocl
            ct_iomamo               = lt_iomamo
            ct_ioconf               = lt_ioconf
            ct_ioopconf             = lt_ioopconf
            ct_iosoconf             = lt_iosoconf
            ct_iogomo               = lt_iogomo
            ct_ioopgomo             = lt_ioopgomo
            ct_iosogomo             = lt_iosogomo
            ct_iogmer               = lt_iogmer
            ct_ioopgmer             = lt_ioopgmer
            ct_iosogmer             = lt_iosogmer
            ct_iosequen             = lt_iosequen
            ct_iooper               = lt_iooper
            ct_iosoper              = lt_iosoper
            ct_ioopcomp             = lt_ioopcomp
            ct_iooppreq             = lt_iooppreq
            ct_iosopreq             = lt_iosopreq
            ct_iooppord             = lt_iooppord
            ct_iosopord             = lt_iosopord
            ct_ioopmst              = lt_ioopmst
            ct_ioopprt              = lt_ioopprt
            ct_ioopcap              = lt_ioopcap
            ct_ioopscap             = lt_ioopscap
            ct_iosocap              = lt_iosocap
            ct_iososcap             = lt_iososcap
            ct_ioopsccf             = lt_ioopsccf
            ct_iososccf             = lt_iososccf
            ct_ioprodlist           = lt_ioprodlist
            ct_iomatver             = lt_iomatver.
    This FM get data from the report used by transaction COOIS. If you needed the header data then you can use lt_ioheader table and seperate the data with the date. If you need at operation basis the you can use lt_iosoper table. You can use this FM to create custom report even with the checks like material availability, PRT availability, capacity requirement etc.
    Thanks and regards,
    Pradip
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:27 AM

Maybe you are looking for