Serial nos entry during production order confirmation in CO15 - User Exits

Hi all,
Is there any user exit existing for a serial nos screen pop-up during production order confirmation.
Regards,
Sravan Kumar V

Hi,
For serial numbers at the time of goods receipt, u have to activate sr. no. mgt for that particular finished product. This can be done by assigning sr. no. profile in the material master record of that material in work scheduling view. once this is done , system will automatically prompt for sr. nos at the time of goods receipt. I am not aware about any user exit.
Thanks & Regards,
Vijay Patil

Similar Messages

  • Recording shift during Production order confirmation

    Hi All,
    Is there a way I can record the shift during production order confirmations using CO15, CO11 or CO11N? I do not see the shift field in the confirmation screen.
    Thanks & Regards
    Subbu SP

    Dear,
    If you don't want to use the standard functionality of SAP or you are on lower version then you can go ahead with  enhancement.
    CONFPP07   Single Screen Entry: Inclusion of User-Defined Subscreens  by using this you can define shift in confirmation.
    For more details refer this link,
    Re: Shift usage in confimation.
    << Moderator message - Point begging removed
    Points unassigned >>
    Regards,
    R.Brahmankar
    Edited by: Rob Burbank on Oct 20, 2010 4:28 PM

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • Error during Production Order Confirmation

    I get a real wierd error during production Order confirmation.  The error message is
    "Additional items are not allowed
    Message no. ZOAL010"
    Can anyone throw some light on this?
    Regards
    Raj

    it is not std SAP message.
    you can check the user exit for confirmation.
    check in transaction code CMOD/SMOD for CONF*

  • Equipment as PRT's during Production Order Confirmation

    Hi Gurus,
    During Production Order confirmation I cannot see whether I have consumed equipments as PRT which are attached to operation.
    The operation is showing CNF status as well the Order.
    How can I see whether which Equipment was used for each operation since there can be more than one equipment as a PRT's for a single operation.
    Regards
    Nilesh

    I use Production Order confirmation hence saw it in CO14 and checked that PRT's are in PRT REL status..I guess this is what you mean to say right??
    Thank you so much for your response.
    Regards
    Nilesh

  • User Exit for Production Order confirmation with CO15

    Hi All,
    what User Exit I should use when validating batch when we do Production Order confirmation with CO15.
    Not when we create or release a Production Order.
    Will reward,
    mindaugas
    Edited by: Mindaugas Kazlauskas on Jan 30, 2008 5:03 PM

    Hi
    The Follwing Userexits available:
        Transaction Code - CO15                     Enter Production order Confirmation
    Enhancement/ Business Add-in            Description
    Enhancement
    CONFPP01                             
      PP order conf.: Determine customer specific default values
    CONFPP02                               
      PP order conf.: Customer specific input checks 1
    CONFPP03                              
       PP order conf.: Cust. specific check after op. selection
    CONFPP04                             
        PP order conf.: Customer specific input checks 2
    CONFPP05                               
       PP order conf.: Customer specific enhancements when saving
    CONFPP06                               
       PP Order Confirmations: Actual Data Transfer
    CONFPP07                               
       Single Screen Entry: Inclusion of User-Defined Subscreens
    CONFPS01                              
       PS confirmation: Determine customer specific default values
    CONFPS02                               
      PS confirmation: Customer specific input checks 1
    CONFPS03                             
        PS confirmation: Customer specific check after op. selection
    CONFPS04                              
       PS confirmation: Customer specific input checks 2
    CONFPS05                              
       PS confirmation: Customer specific enhancements when saving
    CONF0001                               
      Enhancements in order confirmation
    CONFPI01                              
       Process order conf.: Calculate cust.specific default values
    CONFPI02                               
       Process order confirmation: Customer spec. input checks 1
    CONFPI03                              
       Process order conf.: Cust. spec. check after op. selection
    CONFPI04                               
       Process order conf.: Customer specific input checks 2
    CONFPI05                              
       Process order conf.: Cust. spec. enhancements when saving
    CONFPI06                              
      Process order confirmation: Actual data transfer
    CONFPM01                             
        PM/SM order conf.: Determine cust. specific default values
    CONFPM02                             
        PM/SM order confirmation: Customer specific input checks 1
    CONFPM03                               
    PM/SM order conf.: Cust. spec. check after op. selection
    CONFPM04                              
       PM/SM order conf.: Customer specific input check 2
    CONFPM05                              
       PM/SM order conf.: Cust. specific enhancements when saving
    If it is helpful rewards points.
    Regards
    Pratp.M

  • Serial Nos entry for FG during Production order confirmation in CO11N

    Hi all,
    Can anybody explain me how can we confirm the assemblies serial no wise for FG in CO11N.  this is a stringent requirement for my client.
    Withthis  they can track which assembly n upto which operation was that confirmed.
    Thank you

    Hi,
    In OIS2 define a profile and assign procedure PPAU and configure PPAU as
    usage = 03,
    EQ re = 01.
    Assign this profile to assembly as well as product, that profile u have to assign it in material master work scheduling screen.
    Now when you go for confirmation in co11n system will ask you the serial no.
    Now you do the confirmation...you can get what you described.
    This is a standard Sap functionality.First do confirmation and then do goods receipt in MB31 where you assign serial numbers.
    OR.
    An other way is go to COIB here u have to enter the the serial number and material then it will display the this serial number generated against which production order.and if ur generating number of serial number against single production order then it will dispaly all serial number.
    COIB -
    > enter material number and serial number -
    > click on list<>tree--
    >again enter the serial number and material -
    >click on explode it will display the production order and if number of serial numbers are their then it will display at the bottom
    Please check it and refer to below link
    http://help.sap.com/saphelp_470/helpdata/en/dd/f8c817b3f911d1896e0000e8284931/frameset.htm
    Hope will work for you.
    Regards,
    R.Brahmankar

  • Error during Production Order Confirmation mfbf ( backflush)

    in my company in sap when i using mfbf for production Order confirmation of tractor then during backflush using mfbf tcode order confirm but in my store dept no metiral cunsume  so please regards this problem
    with warm regards
    pritpal singh

    Dear Pritpal,
    sorry dear,today i cant check  my inbox immediately. Anyway my mail id is [email protected]
    have checked as per my previous post.
    regards
    pradeep

  • User Exit For Production Order Confirmation Using CO15 or COGI

    Hi all,
    I need user exit for the production order confirmation so that i can set
    AFPO-ELIKZ and AUFM-ELIKZ (delivery completedu2019 status flag) to Blank......
    Thanks

    hi,
    check these exits.
    CONFPP01                                PP order conf.: Determine customer specific default values
    CONFPP02                                PP order conf.: Customer specific input checks 1
    CONFPP03                                PP order conf.: Cust. specific check after op. selection
    CONFPP04                                PP order conf.: Customer specific input checks 2
    CONFPP05                                PP order conf.: Customer specific enhancements when saving
    CONFPP06                                PP Order Confirmations: Actual Data Transfer
    CONFPP07                                Single Screen Entry: Inclusion of User-Defined Subscreens
    CONFPS01                                PS confirmation: Determine customer specific default values
    CONFPS02                                PS confirmation: Customer specific input checks 1
    CONFPS03                                PS confirmation: Customer specific check after op. selection
    CONFPS04                                PS confirmation: Customer specific input checks 2
    CONFPS05                                PS confirmation: Customer specific enhancements when saving
    CONF0001                                Enhancements in order confirmation
    CONFPI01                                Process order conf.: Calculate cust.specific default values
    CONFPI02                                Process order confirmation: Customer spec. input checks 1
    CONFPI03                                Process order conf.: Cust. spec. check after op. selection
    CONFPI04                                Process order conf.: Customer specific input checks 2
    CONFPI05                                Process order conf.: Cust. spec. enhancements when saving
    CONFPI06                                Process order confirmation: Actual data transfer
    CONFPM01                                PM/SM order conf.: Determine cust. specific default values
    CONFPM02                                PM/SM order confirmation: Customer specific input checks 1
    CONFPM03                                PM/SM order conf.: Cust. spec. check after op. selection
    CONFPM04                                PM/SM order conf.: Customer specific input check 2
    CONFPM05                                PM/SM order conf.: Cust. specific enhancements when saving
    use the exit which contains both structures AFPO,AUFM.

  • Serial number assignment to components during production order confirmation

    Dear all,
    When confirming a production order (Tcodes CO11, CO11N, CO15) the user should have the possibility to add serial numbers for components directly in the goods movements overview.
    A modification for that is describe in the SAP Training documents SCM 310, p. 485-487.
    Do you have any details on the described modification and/or any experience with similar modifications?
    Thank you in advance.
    Best regards,
    Klaudia

    Hi friend,
    Use t-code OIEN... Thr u can see the external number range given for various groups of equiments..
    hope this will help.
    Regards,
    Ravi Thakkar
    INCAT

  • Batch split  during  production order confirmation

    Hi All,
    This is the process which  is followed  at our  customer  end, they want  to  split the batches  during  confirmation,
    1.Production order created
    2.While  going through each operation, some components are failing in the in-process inspection and  they need to be quarantained  for  further  process,(it may be rework, scrap, etc)
    3.Now  the  question is  we  want  to create  individual  batches, say  for  example out  of  100qty  which went  operation number 10,   50  were found  to be o.k.  and  the  remaining  50 are  having  defects, we want  to  create  two  different  batches  for this  scenario at  the  time  of  confirmation.
    Is there anyway  in SAP todo  this , like userexit
    Has anybody  has  gone through  similar  scenario's
    Thanks in advance
    Regards
    Venkat.

    Dear Vanket,
    In the operation you can confirm Yield, Scrap and rework quantity.
    In your case in each operation you need to create a batch for each qty what you enter.
    As I told you before batch can be created either production order release or during GR.
    In each operation you are not going to perform GR, hence batch creation is not possible.
    You have 2 options as I see.
    1. Create different intermediate materials and have production orders for each operation so that you can do the GR for each production order.
    You can have the same batch for each stage material so that issuing material and production materials are different but batch is same.
    If there is any defective quantity you need to decide you want to scrap it or you want to go for rework. If you want to go for rework then, using trigger point function you can create a auto rework order for the qty of rework entered during confirmation.
    2. Second option is you can create a production order as you are doing now, but you need to create batch manually in MSC1n transaction for rework as well as yield qty.
    You can confirm the yield qty and rework qty, but you cannot assign the batch as you are not performing GR. You can enter the batch number in the confirmation text field for information purpose. During the final operation when you do the GR, assign the batch to yield qty and post. About the rework qty you are not going to post qty to store, you need to create rework order and confirm the qty, during GR you can assign the batch and do GR.
    If you ask me if you need to strict process to represent your case you need to go for first case.
    Please go through the above carefully and test the cycle and come back if you need any clarification.

  • Error during production order confirmation - costing related

    Dear All,
    When i am confirming a production order through CO15 following error is coming and system is not allowing to proceed further
    Enter rate EUR / SAR rate type M for 01.01.1998 in the system settings
    Kindly guide me how to avoid this error

    Dear,
    Please go to OB08
    Then enter the details Currency Type M
    Then put the valid date from date
    Then put the currency from
    Then put the currency to
    in last columan put the rate
    as
    Exc rate   Valid From              Ratio(From)            From                                Dir.Quot                   Ratio               To
    M              01.01.2011    X        1                           AED (Currency)      =                         x             1                    EUR (Currency)
    Thanks,
    MS

  • Scrap During Production order confirmation.

    When I Put scrap qty in Co11 screen or co15 Screen, Is movement type 551 gets automatically activated??What are the accounting effects and by what transcation can I see these accounting effects.

    Hi,
    Please check production order header screen Go to --> documented goods movements.
    Regards
    Ranga

  • Production order confirmation using CO15

    Hi ,
    When i am confirming production order with reference to sales order using CO15 , material document is being posted only for assembly material , but not for components.
    Please let me know how i can correct this.
    Thanks in advance.
    Regards,
    sudheer

    Sudheer,
    You can display confirmation using transaction CO14, here you click the goods movement tab, and if you find GI items highlighted in Blue then these goods movement error needs to be reprocessed. Execute transaction CO1P and save the records there, then execute transaction COGI and clear the error records.
    Regards,
    Prasobh

  • Batch Classification for Auto GR during Production Order Confirmation

    Dear All,
    I have a scenario,where Auto GR has been activated in last operation of an order.Material is batch managed with certain characteristics.When I use CO11n, and go to goods movement tab,batch for 101 movement type is entered but Batch classification pop up doesn't come.For that we need to select the line item,goto extras and create batch,then Pop up for batch classification comes.But,if we do GR with MIGO & MB31, This classification screen automatically in Co11n. i have tried certain exits also, but nothing works.

    Hi Stuti<
    Refer the below links it will solve the issue.
    [Batch Determination - help|http://help.sap.com/saphelp_45b/helpdata/en/25/283cb44f7811d18a150000e816ae6e/frameset.htm]
    [SDN Thread-1|Re: Batch Determination issue -reg]
    [SDN Thread-2|Batch Determination;
    Regards,
    Shyamal

Maybe you are looking for