Hi all,
Service entry sheet 927080 has acceptance indicator enabled. The revoke
of acceptance is not possible for this entry sheet. Service line item
is not available in this service entry sheet. Refered PO has the status
Services are delivered, waiting for invoice verification. While doing
invoice verification, Error appears No (suitable) item found for
purchase order.
Service entry sheet is having non-editable status since acceptance
indicator is enabled. The same cannot be revoked.
On going thru the header change document, user has deleted the line
item. Item change document is not available. It has change document
no. -
25 with time 16.16 and -
27 with time 16:15.
Kindly advice, how to do rectify the Service entry sheet with service
line item.
Rgds
Suddy
Hi all,
Any advice.
Rgds...Suddy
Similar Messages
-
Service entry sheet reversal document (Status: Error in process) List repor
Hi,
I have a requirement, to have or develop report which gives service entry sheet reversal documents (Status: Error in process),
while investigation i found below options (not exactly meeting my requirement)
1) Display and Process Confirmations Centrally >Document Category>reverse documents
which giving all reversed document list (need only error list) and it is giving only my puchasign group list (need all purchasing group list)
2) I can execute PPB_PD with BUS2203>status>I1019
is there any way/possible option that i can execute a report of reversal service entry sheets which ststus :error in process"
Thanks,
JaiHi Christian,
Thanks for your reply.
But this is what has happened. No the SES was not deleted in ECC before the confirmation was deleted in SRM. Our users don't have access to ECC T-codes.
Also I have checked the time at which the cancellation was created and everything is in sync.
How can i change the status of SES from 'Error in process' to 'posted in backend'?
Please advise
Thanks -
Service entry sheet creation from PO without selecting line item of PO?
Dear SAPIENTS,
While creating service entry sheet for one frame work order (PO) i do not want to select line item of PO. I want all the service of PO line item should come automatically in single service entry sheet number.
At present whenm i enter the PO number its taking line item 10 as default because of this service of that line item is coming and for every line item i have to create different service entry sheet.
Regards,
Kaushal RaiHi,
in ML81N please enter the entry sheet header data, then go to full screen services, push the button for
"service selection" and after that a popup appeares for the service selection (SAPLMLSP
0500). On the bottom of this popup you have the button "complete" = adopt all = F9. If you hit this
button all of your services within the service specification will be copied into the entry sheet
at the same time.
Regards,
Edit -
Service Entry Sheet - Revoked/Accepted
<i>
Actually PO can be accepted or revoked maintained in Service Entry sheet (Tranasction - ML83 ) here .There is an indicater like acceptance it's maintained form as sheet is accepted /rejected. I need which Field and table populating data or flaging this message . but one more thing one structure(RM11R) having this field.Please tell me which table to maintaing data.
thanks
suresh </i>Hi,
The data will be stored in ESSR table. Field for "Acceptance Indicator" is ESSR-KZABN.
thanks,
sksingh -
Service entry sheet creation thru bapi for multiple line items
HI All,
WE are using BAPI_ENTRYSHEET_CREATE bapi for the creation of service entry sheet against service PO.
We are able to create the service entry sheet successfully with single sevice line item using this bapi,but when we are going for multiple service line items in item services tab in aPO, we are able to create the service entry sheet with only one service line item although there are 4 service line items in the item service tab in the po.
We know that this bapi cannot support more than one po line item as it has provision for only one line item at the header leavel in the bapi
will be rewarded for the best solution.
Regards,
veluHi,
Do you know the note 420334?. There you have very useful information.
Best Regards,
Arminda Jack -
Service Entry Sheet Qty Change
Service PO is created with 21 line item of service. And Service entry sheet is created for 18 line item.
Now i want to edit the existing service entry sheet to make it for 21 line item.
Please help....Hi,
if Service entry sheet is fully released/accepted then reverse service Entry sheet release by Revoke option using t-code ML81N/ ML85 .
or
if Service entry sheet is not released,then add the remaining line items by using service selection option using Tcode ML81N and go to change mode. -
Multiple Service Items in One Service entry sheet
Hi All
I have created one PO with 4 line items for multiple PR's and is contain multiple service items.
Is it possible to create only one service entry sheet for all the PO Line items?
at the moment, system allowing me to create one entry sheet for one PO line items.
PO line item number 1, is appearing by default in the top of the service entry sheet.
My user wants to create one entry sheet for all PO line items
Thanks & Regards
PKShi..
SAP treats every line item of PO as separate Entry Sheet...
kindly refer to the link..
Service Entry Sheet-Multiple Line Items
If you want to have create single SES for all services, means while creating PO don't create separate line item for each service.
Instead put all services under one line item in PO.
hope it works...
thnkas..
Edited by: ashish2210 on Jul 19, 2011 4:18 PM -
Service entry sheet error.with new material group for services
Dear Experts
We need to create material group for roll shop spare parts service,we created a new material group.
when we are creating PR/PO with item category as D and a/c assignment K( entered cost center here).its giving error message
as RC= 3M8 47 Account determination for entry JSL KBS J001 not possible(while making service entry sheet)
after that i changed PR/PO and gave cost center and G/l account.now the service entry sheet is accepted.
is it necessary give G/L account manually,if user chose wrong G/L account how to avoid this problem.
please clarify me,
do we need to assign valuation class for material group for services?(where to assign)
or
should assign G/L account manually to cost center while creating PR/PO
Please clarify me
Regards,
Varun
Edited by: madhu varun tirupati on Sep 8, 2010 2:48 PMHi,
Option-1:-- >
Without creating material group and you can use your other service material group(existing service material group) and create a service master in AC03 as spareservice. Create a Service PO with text as roll shop spare parts service with other details as required like quantity of service, cost center & G/L account etc. After service being completed you can do SES in t.code: ML81N
Option-2:-- >
If you want report at the end based on different material/service group level, you can create a material/service group in OMSF for roll shop spare parts service and then you can assign to valuation class to material group in OMQW t.code. Then carry out regular process service order, SES etc.
Based on requirement, you can enter G/L account manually or can set default G/L account in purchasing document with help of t.codes: OMSK, OMQW, OME9, OMGO & OBYC
For error u201CAccount determination for entry JSL KBS J001 not possibleu201D, you cannot assign KBS transaction/event key to an account in OBYC t.code. Only you can assign G/L account to cost center with your CompanyCode in OKB9 t.code. Check the SAP note: 364570 & 106981
Regards,
Biju K -
How to find Goods Receipt Number particular to Service Entry Sheet Number.
Hi Experts,
In one of my reports i need to bring purchase order ,service entry sheet, goods receipt number .
In ekbe i am getting the purchase order and its service entry sheet while keeping BEWTP = 'D'.
so i am getting purchase orders and their service entry sheet numbers in belnr.
Now i want to get the corresponding goods receipt number .
But i am getting goods receipt number against the purchase order but not against service entry sheet , in same EKBE
while keeping BEWTP = 'E' movement type = '101'.
My doubt here is how to get the corresponding goods reciept number for a service entry sheet.
if i have three service entry sheet numbers for a purchse order i have three goods receipt numbers
but how to get the relation between them which GRN to which service entry sheet
. is there any table which stores the service entry and its grn.
If i am any thing functionally wrong which i wrote above please correct me and give ur inputs.
Thanks
vamsi
Edited by: vamsi talluri on Aug 20, 2009 7:21 PMHi Sarath,
If the Purchase order Item category is 'D' then it is a service order then it can have N service entry sheet numbers and once each service entry sheet is accepted it will be available for Goods reciept .. so that information will be avaiable..
U can obtain the GRN against the Service entry sheet in EKBE itself.
BELNR refers to GRN
LFBNR refers to Service entry sheet number.
And hence i am closing the thread.
Thanks
vamsi -
Print output of service entry sheet
Dear users,
I have configured message output determination for service entry sheet,partner function for vendor and printer configuration from MN13. However when I am running T Code ML83, and putting a service entry sheet no. the message ' no purchasing document found' is coming. When i am checking the message tab in the service entry sheet, I see status green for message type NEU. Can you please suggest why this problem is arising and how can I get output from ML83
Thanks in advance
adsHi,
Sine the output message 'NEU' is displayed green which means the message has been successfully processed. Select the processing status as '1' in ML83 and try taking the output of Entry sheet or go to messages in Entry sheet - select the output type NEU and click on repeat output - Save the entry sheet - Take print in ML83. -
Account Assigment Transfer to Service entry sheet
Hello;
I wanted to transfer time sheet from cat2 to service entry sheet (SES) using catm without having to enter the GL and the cost center in the SES I tried to put the accnt assgmnt info thru the PO still I'm getting error in CATM saying GL not entered.
Any help would be appricaited
IbouHi,
I think maintaining suitable Data Entry Profile will solve your problem. Take help from HR consultant.
SPRO->Cross Application Component->Timesheet->Specific Settings for CATS Classic->Setup Data Entry Profiles.
Regards -
Confirmation of Service activity Thru Service Entry sheet.
Hi!
We are releasing Purchase Requsitions thru service activity in our projects.Subsequently these PRs are converted to POs & finally we are maintaining service entry sheet for acceptance of service in service entry sheet.
Our issue is that we want the service activity to get automatically confirmed once we accept the service in service entry sheet.Presently we are doin it manually.
Please suggest nescessary configuration or process to achieve the above.
Regards,
SeemantHi,
In CATS network activity will be confirmed as soon as time is entered.CATS module there is integration between HR & PS module. Time will be entered by employee against network activity / WBSE etc. This time entered can be approved & the same will be transferred to CO / PS for posting actual cost / time etc. Please refer below URL to know more details on CATS.
http://help.sap.com/saphelp_erp60_sp/helpdata/en/64/400b2b470211d189720000e8322d00/frameset.htm
Hope this will help you.
Regards,
Rakesh Pradhan -
Creating Service entry sheet using bapi BAPI_ENTRYSHEET_CREATE
Hello Guys,
I am trying to create a service entry sheet for single line item only using bapi BAPI_ENTRYSHEET_CREATE.
its is creating Service entry document but not populating the line item for me (here only one line item for me).
If you guys have sample code (how the poupulate the internal tables) could you please send it across?.
Thanks in Advance..
SteevanHi,
Creating Service entry sheet using bapi BAPI_ENTRYSHEET_CREATE
For creating service entry sheet follow below link and it helps to you.
http://wiki.sdn.sap.com/wiki/display/ABAP/CreatingServiceEntrySheetusing+BAPI
Regards,
Sekhar -
Commitment item error at the time of Service entry Sheet
Hi experts,
I have created a service PO, in which I have given the GL. Now when I am going to post the service entry sheet, I am changing the GL account. But system is picking the commitment item with reference to the GL earlier provided in PO.
I want to pick the commitment item with reference to the GL I am providing in service entry sheet.
Pl suggest how can I achieve this.
Regards,
Ankit AgarwalHi Eli,
Thanx for your response.
But derivation rule is same for all GL. Whether we put GL in PO or in Service entry sheet, system will derive the commitment item from the same single rule.
Regards,
Ankit Agarwal -
Creating Service Entry Sheet without using Service Master/Service lines
We are invoking the BAPI_EntrySheet_Create to create the service entry sheet. We are currently facing this issue...
1) For assigned PO's, we are getting the PO item and Account assignment information from BAPI_PO_GetDetail. We are using these values to populate the parameters/tables to invoke BAPI_EntrySheet_Create. For population the Entrysheetservices table, we are not using information from Service Master/Service lines but use the information we get from an external system to populate the Service lines(ESLL). We do not provide a Package No/Service information when invoking the BAPI but populate the service lines with short text, quantity, Gross price etc without service information like package no, outline indicator etc. The BAPI creates a service enty sheet successfully(this is without the SES Acceptance indicator not being set) but when we lookup the SES# from ML81n transaction the ESLL details lines are not displayed.
When displaying the SES using transaction ML81N, the header information is displayed correctly but the lines are not displayed. The Header information is correctly populated in ESSR table and detail is also populated in ESLL table. I think the cross reference information is correctly set in ESLH table to pull up the detail when ML81N as it is missing the package/sub pack information.
Your expert advise in resolving this issue is very much appreciate. Please advise.Hi,
Creating Service entry sheet using bapi BAPI_ENTRYSHEET_CREATE
For creating service entry sheet follow below link and it helps to you.
http://wiki.sdn.sap.com/wiki/display/ABAP/CreatingServiceEntrySheetusing+BAPI
Regards,
Sekhar
Maybe you are looking for
-
All 11g pre-requisites check failed on solaris 10
During 11g R2 (64 bit) installation on Solaris 10 64 bit, all pre-requisites checks were failed. Like the first one given below: ======================= Physical Memory - This is a prerequisite condition to test whether the system has at least 1GB (1
-
Hi All, I'm trying to send a custom ebMS document from Acme to Global Chips over Email. It is throwing me the below error message. From the below error I found out that the port number was wrong. I think it is taking the port number by default, but t
-
How to fill the reference key in BAPI_ACC_DOCUMENT_POST
Hi, Currently iam uploading data for FB01 transaction using BAPI_ACC_DOCUMENT_POST. I want to fill the Reference key of header as input. Please let me know the data which we have to fill the input fields. Thanks in advance, Regards, Krishna..
-
Hi, I am wanting to save some space with the oracle logs which are created. I have zipped up the files and want to delete the logs until I actually have to use them. Does Oracle access these logs during normal operation or am I safe to delete them an
-
WM how to determine storage bins manually for a multi row transfer order?
Hi to everyone. in our WM configuration, SAP system is posting transfer requirements automatically according to goods receipt. After that, we want to post transfer orders with reference to recently created transfer requirement. We prefer to use Logis