Service entry sheet restriction for vendor

hi guys,
Can any one explain how to restrict the service entry sheet for a specific vendor?
thanks.

If that is only the vendor v can block but that specific vendor changes continuosly.
For this i have set up the relaese procedure in service entry sheet by taking strucure CESSR and field LIFNR.
the problem is, i have given the characterstic value as vendor a/c no.. for whom v r trying to restrisct,but release is triggering to all vendors.
v want only for specific vendor.
thanks.

Similar Messages

  • Service Entry sheet Creation for Shipment cost Document

    Dear All,
    While creating a shipment cost document .A service PO is getting generated in the back ground based on which a service entry sheet is created and LIV is made.But in the configuration we are mapping the Transportation planning point to Purchase organisation alone.
    Can some one let me know whether the generation of PO in the back ground for a shipment cost document in the back ground is a standard SAP feature if so can you tell me the configuration steps.
    Regards,
    K.Vivek

    Hi,
    Creation of Service PO in shipment cost document is based on the following SPRO setting or T-code.
    T code : T_56.
    SPRO > LE > Transportation > shipment cost Document > Shipment cost types and item categoires.
    Get into the details of item categoires, you can see the indicator Generate PO.
    hope this helps.
    Harish

  • Mvt. 101 with ML81N for service entry sheet split for every service line

    Dear guru.
    I have one purchase order position for service (item category D)  with three different service line.
    I run ML81N and i create the service entry sheet for every service line.
    If I see the goods receipts movement generate , the system show 1 movement line with qty 1 and the total of amount in LC of the 3 service line.
    Does exist a chance in order that system create 3 different movement lines for every service line with quantity and amount specific.
    Thanks

    Hi,
    I think you have create Service PO with description & UOM .
    then that you have mention activity for services ( Service line) . But if you mention n number of service line  that all values acumulate to service line of line item.
    so, you can't get different entery in accounting document & material document. this always w r t line item of the service PO.
    You have to note one think  all the service line tiem is unter the line item 10 only.
    just check your PO in ME23N.
    SAM

  • Service entry sheet creation for planned services

    Hi,
    I have created a service purchase order with planned services. After this I am trying to create a service entry. During ML81N, I give the P.O number and then click on create service entry.
    However, to adopt the services from the purchases, there is a service selection tab which takes the user to the services tab of the purchase order and then the user must select the relevant service and click on the adopt button to bring the  service into service entry sheet screen.
    However, in my  case, the service selection tab is not appearing on the service entry screen. Hence I am not able to call the services from the purchase order. I am on ECC 6.0 version.
    Am I missing some step in config or in procedure ?
    Kindly advice.
    Regards,
    Rajeev

    Hi,
    This doesn't sound like a config problem.
    If the services are on the PO then you should be able to select the option to choose them from the PO services.
    A remote (very remote) possibility is that you may have an authorisation problem, stopping you from being able to use the PO details? Is this possible? do you have authorisation to change this PO via ME22N etc:?
    Steve B

  • Service entry sheet create for contracts with unplanned services

    Hi,
    I am creating SES using BAPI_ENTRYSHEET_CREATE. I have a scenario in which i need to create SES based on the PO no, PO Item , Quantity, Headertext, Contract No, Contract Item, Contract_Item_Line. While creating manual SES using ML81N we use Contract button to provide contract no, item and service(service with master, without master). When i am creating SES it is creating SES but the service is getting posted as unplanned not contract checkbox. In ML81N screen there are four checkboxes for any service line. 1)Plannes 2) Unplanned 3)Contract 4) Dele. Indicator
    In my case it should flag the contract button but when there is an unplanned service for any contract no, it is flagging the Unplanned checkbox not contract checkbox.
    Please suggest
    Thanks
    Randhir

    you can get the PackNo details of entry sheet from ESSR and of PO from EKPO. from the packno find the subpack no in ESLL. put the subpack no again in ESLL as pack number and you get the services for entry sheet and PO. you may try a logic to link both

  • Service entry sheet (Confirmation for service) creation by supplier

    Service procurement MM-SUS.
    For processing service orders(no hirarcies, only one service line)
    I Have transfered the service Purchase order from ECC
    to SUS(SRM7.0).i am able to see the purchase order
    and POR created and transfered to ECC. Further confirmations
    for Creating SES in ECC,how?
    i have tried with create confirmations in start page of SUS.
    but service POs are not available.what are the settings  required in SUS (for service confirmation) to create SES in ECC.
    with screen shots is more helpful.
    regds
    Rami

    Hi Nikhil,
    thanks for your Feedback.
    we are not using EHP4. our ERP system is ECC6.0 only. I know EHP4 is required at ECC side. But  in this stage
    we are going with ECC6.0.with Custom developments. I think modifications are required in the Interfaces and at ECC side.
    as SRM is already upgraded to  SRM7.0.I think no custom developments needed at SRM side.only the service orders requests
    from ECC to PI and PI to SRM needs to be modified?
    scenario name  : ECC triggers Idoc to PI and PI generarate XML to SUS (Orders02 to Purchase order request).
    i have checked the Idoc and all  fields required for creating service order in SUS is available.is any other fields/check box required in Purchase order Idoc. so that we can map.
    in service purchase order Item detail screen(service lines) is not displaying in SUS side and also confirmation(SES creation).
    regds
    Rami

  • SRM-SUS for Service Entry Sheets - Classic Scenario

    Hi SRM Gurus,
    Our client wants to use SRM-SUS for the Service Entry Sheets (to being with and then later expand more in other SRM areas). The lead system will be R/3 system.
    We will be going with ECC 6.0 and SRM 5.0.
    Service Order will be created in R/3 and replicated into SRM (SAP have said this is new functionality in SRM 2007 and SAP will provide us with this functionality in SRM 5.0 as well)
    SAP are also recommending using MDM for hosting the catalogs for service entry sheets to enable vendors to selete their items during the confirmation / filling the service entry sheets. - they say this is mandatory
    SAP are also asking for XI for the data to be transferred from R/3 to SRM (and may be vice versa) - they say this is mandatory.
    Few questions:
    1) What kind of hardware size are we talking about to have SRM-SUS, MDM, XI and Portal (PI)
    2) Are MDM and XI mandatory as said by SAP and if yes, in what scenarios. What is they way around
    3) How good is the functionality provided by SRM-SUS for Services? Is it as good as in R/3 (or even better)? We will be having complex Services in our scnearios.
    4) What can be a typical time to install SRM-SUS, MDM, XI and Portal in the Dev environment to get moving onto the project?
    An early response shall be highly appreciated.
    Thanks in advance
    Regards
    Rahul

    few answers to your questions
    1) what is the release of SRM  you want to work with?
    2) services in SUS is not available as standard , and will be provided by SAP as consulting up on request.
    3) for hardware requirements , please refer to the master guide for the srm release you will be working on -->
    and also you can refer to the software component matrix in master guide --> to see if any component is mandatory..
    4) XI and MDM as far as i know is mandatory for SRM 6.0 and above , But in SRM 5.0 , XI is compulsory.
    5) so xi is mandatory in anyway in SUS as different systems are involved and therefore is required for routing the documents correctly.
    6) time for installation again depends on your supplier base , and your level of expertise.
    7) it is not always recommended to compare between two different systems , R/3 and SUS are different and so functionality will not be the same
    8) but as far as i know R/3 is stronger functioanlly..

  • Vendor evaluation tab in service entry sheet

    Hi All,
    Can any one please help me out to configure the vendor evaluation tab in service entry sheet T code ML81N.  Already done the field setting for service entry sheet and maintained the Purchasing Organization Data in vendor evaluation.
    Regards
    MG

    Hi Guys,
    Thanks for your update. i have refered the above mentioned note, but is it possible to show more than two subcriteria in the vendor evaluation tab in service entry sheet.
    For example i have a criteria like below
    Criteria                               Sub criteria                 Scoring mentod
    Manpower Skill                  Deployment                        C
                                              Competence                       D
                                              Training                              C
    So now my doubt is how can i get all the above three sub criteria in the vendor evalution tab in ML81n. I am getting the first two sub criteria.
    Is there any other way to do it like user exit any enhancement etc.
    A urgent reply shall be highly appriciated.
    Thanks
    MG

  • To make service entry sheet for multiple line items of the service PO.

    Hello MM Gurus,
    Please help me for the following
    I create a service PO with say 10 line items. Then while doing the service entry sheet the system automatically picks the line item 10 by default. When I try to enter the other items it throws an error" unplanned services cannot be entered"
    So how to make a service entry sheet which shall include all the line items of the service PO at the same time.
    So if I have 100 items in the PO do we make the service entry sheet 100 times against each item? Is there any seeting/solution on this?
    Please help.
    Regards,
    Prasanna.

    Dear,
    I have two solution for u.
    1) Create different service entry sheet -ML81N for each line item and create single invoice verification for all service entry sheet - MIRO
    2) Create service purchase order - ME21N for only one line item.
    And include all services in service tab available at item detail level of service purchase order. Enter it's quantity and rate.
    Than create one service entry sheet for purchase order.
    So you can create one service entry sheet for all line item of services.
    Note: - Use option 2 for easy process.
    Regards,
    Mahesh Wagh.

  • Invoice booking with respetc to Service Entry Sheet

    Hello Friends
    I created one PO (Related to services u2013 Item Category u2018Du2019 and Account Assignment Category u2018Ku2019)
    for a Net price of 54,296.35 INR and service entry sheet made for same 54,296.35 INR.
    At the time of bill booking through transaction MIRO, I have to book only 52127 INR (After service entry sheet made, vendor offered a special prcie 52127 INR) But in item data (in MIRO) system is not allowing to change Amount to 52127 from 54296.35 INR and throwing following error message.
    Condition processing not possible for items with account assignment
    Message no. M8575
    Diagnosis
    This item is subject to account assignment. The system does not allow you to branch to the conditions.
    Procedure
    To enter or change the amount, branch to the account assignment screen.
    P.O. NO.396950 & S/E 1000095526
    Could u please explain what would be the problem in this case?
    Thanks
    Vijayakumar TVN

    Hi,
    I tried in my system and its working fine allowing to change the amount in MIRO. My doubt is whether it was client requirement during implementation to set such an error message..
    It might has something to do with the Partial Inv. field in the Account assignment category in PO item level..
    Are u using Derive from account assignment category???
    Please check this answered thread
    Error Message M8575 - Partial Invoice not possible
    Please check
    sBk
    Edited by: Sujithbk on Dec 14, 2011 5:56 AM
    Edited by: Sujithbk on Dec 14, 2011 5:58 AM

  • How to find Goods Receipt Number particular to Service Entry Sheet Number.

    Hi Experts,
      In one of my reports  i need to bring purchase order ,service entry sheet, goods receipt number .
    In ekbe i am getting the purchase order and its service entry sheet while keeping BEWTP = 'D'.
    so i am getting purchase orders and their service entry sheet numbers in belnr.
    Now i want to get the corresponding goods receipt number .
    But i am getting goods receipt number against the purchase order but not against service entry sheet , in same EKBE 
    while keeping BEWTP = 'E' movement type = '101'.
    My doubt here is how to get the corresponding goods reciept number for a service entry sheet.
    if i have three service entry sheet numbers for a purchse order i have three goods receipt numbers
    but how to get the relation between them  which GRN to which service entry sheet
    . is there any table which stores the service entry and its grn.
    If i am any thing functionally wrong  which i wrote above please correct me and give ur inputs.
    Thanks
    vamsi
    Edited by: vamsi talluri on Aug 20, 2009 7:21 PM

    Hi Sarath,
         If the Purchase order Item category is 'D' then it is a service order then it can have N service entry sheet numbers and once each service entry sheet is accepted it will be available for Goods reciept .. so that information will be avaiable..
    U can obtain the GRN against the Service entry sheet in EKBE itself.
    BELNR refers to GRN
    LFBNR refers to Service entry sheet number.
    And hence i am closing the thread.
    Thanks
    vamsi

  • Grn creation at the time of service entry sheet

    Hi,
        when created sevice entry sheet,Grn document also created automatically in sevice process for this any settings avilable?
    regards
    murali

    Hello,
    Material document created at the time of accepting service entry sheet is standard SAP setting.
    When you order a services thru service entry sheet, say for example you create a service order for calibration of measuring euipments. So after service completed that comes in your company you fill service entry sheet in ML81N, there you entrs services and accepting the same. and After accepting systems generates material document.
    Regards
    Kedar Kulkarni
    Edited by: Kedar Kulkarni on Jan 18, 2008 1:38 PM

  • Reminder to perform Service Entry Sheet

    Hi All,
    May I know is there any existing reports that I can utilise to send reminder to user to perform Service Entry Sheet after services have performed?
    Thanks.

    Dear,
    I have two solution for u.
    1) Create different service entry sheet -ML81N for each line item and create single invoice verification for all service entry sheet - MIRO
    2) Create service purchase order - ME21N for only one line item.
    And include all services in service tab available at item detail level of service purchase order. Enter it's quantity and rate.
    Than create one service entry sheet for purchase order.
    So you can create one service entry sheet for all line item of services.
    Note: - Use option 2 for easy process.
    Regards,
    Mahesh Wagh.

  • Multiple Line Items in One Service Entry Sheet

    Dear All,
    Can we capture multiple line Items of same PO in one Service Entry Sheet
    If yes,Please can you give some steps to do the same.
    Regards
    Murali raju

    Hello,
    We need to create a service entry sheet seperately for every line items of the PO.But you can create Service entry sheets for multiple lines with in that Line item.
    Ex. if u have 2 line item in the PO,
    Every line item of the PO will have Multiple services in the Item details..So these Multiple service number Entries shall be treated in the same Service Entry sheet. But not the 2 nd Line itme ot the Purchase order as it will have another set of Service entries.
    Please cme back if u hv queries..
    Mug

  • Multiple account assignment in automatic Service entry sheet

    In TRX VI01 I created a Shipping Cost document (SCD); this document automatically created a Service PO with account assignment category (AAC) "U" and also created a service entry sheet (SES) for this PO. The AAC in the SES is K.
    Since the PO and the SES are created automatically, I want to use a user exit, Bapi or similar to change the AAC to X and to enter multiple account assignment in the SES.
    Any user exit o Bapi that I can use to do this?
    Regards,
    CD

    B.K.
    I need the user exit in the SES no in the PO.
    Thanks,
    CD

Maybe you are looking for

  • Bangla character not displayed correctly

    Hi, All   I am work in a multilingual project where some bangla character not displayed properly like "block" in Bangla. The exact apperence of block is ব্লক but in my application it appere as breking character  I am using the latest build of flex sd

  • IPod Classic Issues

    I have the 160GB iPod classic, when listening to music it freezes or will skip songs.. Or play only a limited amount of the song before changing to another.. What can I do?

  • Start multiple services on a list of computers

    I'm trying to write a PowerShell script to start multiple services for a computer list in a txt file.  I know there has to be a way, but I'm running in circles trying to figure it out.  My latest test is Get-ContentD:\Scripts\test.txt|Foreach-Object{

  • Jstl function tags question

    I'm trying to output the size of a Vector in jstl 1.1 like <%@page contentType="text/html"%> <%@page pageEncoding="UTF-8"%> <%@ taglib uri="/tags/struts-html" prefix="html" %> <%@ taglib uri="http://java.sun.com/jstl/core" prefix="c" %> <%@ taglib ur

  • Capacitive sensors are backwards

    Not sure if I am dyslexic or what. The capacitive buttons on my display seem to be backwards. If I touch the right button, the brightness bar moves to the left. If I touch the left button the brightness moves to the right. It's very confusing. Un-App