Service Order for Asset (Project, value to be capitalise)

Could we make Service Order with Account Assignment Cat "A" (in place of K)
actualy we want to book the service value to 1 asset. But system is giving folliwing  error in case of "A" and even not saving the document:
Asset Profit Centre should be same as plant
after tick this error follwoing error is comming:
System error (PO_POST)
and not saving the docuemnt. there is no issue in given asset no.

Hi,
Create Asset number with Profitceter same as the plant.
Then check the Account asssignment category setting with the PO document type in SPRO.
Then create the PO with Account assignment as A & the asset number assignmet in the PO.
Regards,
Raj

Similar Messages

  • Value contracts Maintenance Orders (service Orders) for particularly period

    Hi Experts,
    My client wants Value contracts Maintenance Orders (service Orders) for particularly periods. How can I maintain this scenario in sap MM.
    Thanks in advance,
    Chandhu

    Thanks for your replay,
    I have tried already standard value contract.
    I have mentioned 1000 service number in value contract. But I am not getting service number at the time of Purchase Order creation with Value contract reference number.
    Thanks
    Chandhu

  • Travel Expenses settlements against Service Order/WBS Element/Project Ord

    Hi Experts,
    I have one req. in Travel Expenses, i.e. need to settle travel expneses against Service Order/WBS Element/Project Order.
    Can you guide me how to do this req.
    Thanks & Regards
    Rajesh

    Hye mate,
    This is possible for sure what you need to do is to go at travel request . In travel Request there is an option of Enhanced Travel cost/ Alternative master cost center. if you click on it . you would find an option of cost assignmnet click on it
    there you would have option , like an excel sheet like fields of  the cost centre, wbs element, profit center, order number what eve is requred and save it.
    now the cot of trip would go that particulat cost center or der numbe or WBS rather then the cost center assigned at master data in ifototype 0027.
    Regards
    Waqas Anwar

  • Mass creation of Service orders for a Field Action

    Hi Experts,
      Is there a way to mass create service orders for a service action. Basically we have a part that we want to update in the
    field that is not part of an IBASE record. We would like to replicate an exact service order, one time, for each of our
    customers. This is something that is done on a fairly regular basis. To avoid errors in manual entry, I was wondering if
    this is a method to deal with this in CRM? I have seen this done with CATT in ECC.
    Thank you,
    Nanda

    Hi All,
       I tried using LSMW to create service orders, but I found out from SAP that batch Input is not a supported channel to load business data into the CRM system anymore! So can anyone suggest me a better way to mass create service orders?
      I have tried using eCATT as well and this didn't work. I have created one service order (template) for each of the customers and whenever I need to edit these service orders (ex. with a new product), I want to be able to do this automatically by using the list of service order templates and the new product. Will a BDC work or can I use a BAPI to do this? Any suggestion/tips will be highly appreciated. I want to be able to copy the template to a new service order and then be able to add a new line item for the product, this should be repeated for all the service order templates.
    Many Thanks,
    Nanda

  • Is ATP check possible in Service Order for Sales Item?

    Hi All,
    My question, is ATP check possible in Service Order for Sales Item? My requirement is that when i create a service order in the web UI with a sales item and drill down to the item level, i see the schedule lines assignment block but w/o any Confirming date, so i want to know whether the ATP check is happening or not. For example wen i create a sales order in web UI with a sales item and drill down into the item level, the schedule line AB shows me the Confirming date checking the ATP. But this is not happening in case of service order. So kindly suggest the reason and clarify my query. Thanks
    Regards
    Sridevi

    Nobody can help me???
    Please.
    Thanks

  • Purch.Order for Assets - Urgent

    Hii all of u
    Can any one plss explain me how to do Purchase orders for Assets and the required configuration if any...
    Plsss help me it is very urgent to me..
    I will assign full points
    Thanks & Regards
    Ramki

    Hai,
    while creating purchase order, you should assian Account assainment category (A).
      In Line item level , in Account assainment category we have to give Asset no and Gl a/c.
    ok
    Regards
    ram

  • MD04 Does not show Service orders for owned equipment

    Hi,
    Is there a way to make MD04 - Material Stock Requirements List, to show a particular type service order? Our loaner equipment is owned by us and goes through Repair after it comes back from a customer. We create service orders for those materials and when running MD04 we would like to see those service orders as supplies.
    Thank you very much,
    Sergiy

    Unfortunately, third party purchase orders have nothing to do with my issue. My case is service orders, repair orders for the materials we own. MD04 shows requirements as these loaners are going out to customers on customer repair orders. When they get back they get repaired and put back into our own stock and then shipped to another customer on a loaner program. If the service order is scheduled to be completed we would like to know how many are coming back into stock and make decisions based on requirements in MD04. Therefore, I would like to have MD04 show those service orders as supplies.

  • SERVICE ORDER for SALES ORDER quantity

    Hi gurus,
    i have the next problem.
    I have a sales order item that trigger a service order (CS). The problem is when i enter quantity 10 in sales order.
    It appear this message:
    "Due to technical reasons, you can only create one service order for a sales order item at the moment in service processing."
    Can I do a sales order with quantity 10 pieces and the service order with 10.????
    It's possible to customize that funtionality??
    Only one ???
    Thanks very much

    Nobody can help me???
    Please.
    Thanks

  • Service order/confitimation - plannedvalues/actual values  or not flowing

    Hi All,
    When I am creating a Service contract in SAP CRM an internal order is created with planned values but when I am creating a service order/service confirmations and assigning it to a contract t the planned values/actual values are not flowing on to the internal order
    Can you please let me if any specific configuration is missed or required for the above scenario?
    Thanks
    SK

    closed

  • Restriction of user status in service order for billing due list

    Dear CRM Experts,
    I have configured status profile for service order as OPEN,INPROCESS and Completed and have assigned this to the service order transaction type.
    Now once i save a service order without errors ,the system is automatically generating abilling document in  billing due list TX:BEA_DL_01 even though the user status assigned to it is OPEN ,INPROCESS AND COMPLETED.
    According to our client requirement ,a billing document has to be created in Billing due list if the User status assigned to it is COMPLETED only.
    Please suggest the solution.
    Bye,
    Madhav

    Hi Nanda,
    As per your last reply, for some Service Orders you are unable to change the Status. Can you have check whether those service Orders are error free?
    Sometimes, when there are errors in service orders or in 1Orders you cannot change the status from In Process or Open even when you have released certain Items.
    Hope this helps.
    Thanks,
    Samantak.

  • Sales order for a project

    Dear all
    Requirement : To get the list of  total sale orders (of a particular order type) for a specific project .
    e.g. : I would like to extract the list of all sale orders (only sale order type: OR) for a project.
    Plz guide.
    regards
    Sapshed

    Yes, this is the std tcode but it might be patch level or version level dependant.
    In that case you can go to tcode VA05 and after putting the selection in the first screen, click on the Further Selection Criteria tab on top of the selection screen.
    After clicking the tab, you get one pop up screen where you have Sales doc type option, so you can select the same and give the input in next input screen.
    After putting the selection criteria you can view the sales order of particular document type.
    Else you can get the list of all sales orders within a date range and then filter the list wrt sales document type column.
    Rgds,
    Antima

  • Contract determination in service order for PPR items

    Hi Experts,
    Contract data is not being determined for some items in service order. All these items are assigned to product list in service contract using product range or PPR.
    1) PPR is created with the type "sales contract"
    2) In the categories section assigned the relevant category ID's
    3) PPR is assigned to the service contract under product list.
    4) Service order is maintained for contract determination 'D'  - determination both at header and item level
    5) When a service order is created I see that expected items are not showing the contract data.
    Any suggestions - any specific setting I am missing
    I found a SAP note for same problem in previous versions of CRM. (5.0 to 5.1)
    but we are on BBPCRM 6.0
    Thank you
    Ram

    Hi Shalini
                    i am trying to create a service ticket from WEB IC by confirming Account and Ibase and then creating service request and able to save without error. 
                if i end session and open the service request again in change mode and if delete the ibase, then appeas the message
    "You should run a new contract selection for item 0000000010",  going through OSS notes, but found nothing.
               Contract Determination is set to 'E' : Assign at Item leve : Assign immediately if unique for transaction type ZXXX.
    if i open the service ticket in CRMD_ORDER and go in change mode if i click process action button next to error, this will disappear. but it comes when i assing a ibase to the request, so its working only when i create.
    any sort of help will be appreciated.
    Thanks
    Gopi

  • How to read the status of Installation and service order for a BP

    Hi Experts,
    1. I have a business partner and i would like to know  the staus of the installation(Disconnected or connected etc.,)  existed for this business partner. For this Please provide me the tables which i can use to get the above information.
    2. I have a business partner and i would like to know the status of the service orders(open, completed etc.,) existed for this business partner. For this please provide me the tables which i can use.
    Contributions will be highly appriciated. Thanks
    Regards,
    Lakshmana.P

    Hi,
    I propose to check this thread
    List of ISU Tables
    Best regards
    Vlado

  • Inter Company Purchase Orders for Asset Acquistion

    Hi Everyone,
    I need your expert help on the following business situation.
    My client has 2 company codes. Now the fixed assets have to be transferred from one company code to another by means of purchase orders being created by acquiring company. Can someone help me with the SAP process (like creation of inter company purchase order etc.) for asset transfer in this scenario.
    Thanks,
    Rohit

    Hi
    I think ur createing intercompany Stock transport order with SD involvement
    If yes then vendors are nothing to do with it
    If NO pls. elaborate ur prob.
    Pls check have u done following configutarion for STO
    SPRO --> MM --> Purchasing --> PO --> Set up Stock transport Order --> Define Shipping data for plants.
    Here  maintain, the cusomer, Sales Organization , Distirbution channel and the division combination.
    Also in the Assign delivery type and checking rule node,  maintain the follwing relation.
    Document type --- Supplying Plant --- Delivery type and Checking rule need to be assigned together so that you will be able to see the shipping tab in the Stock transprot purchase Order
    Vishal...

  • Services order for fusion

    Hi,
    What is the order for the services for fusion 11? Any suggested timings inbetween would also be useful.
    Thanks,
    Nathan

    Hi,
    Have a look at :- http://download.oracle.com/docs/cd/E12825_01/epm.111/epm_install/ch04s01.html
    It also has a link to Summary List of Services and Processes which describes the order of starting the services.
    Cheers
    John
    http://john-goodwin.blogspot.com/

Maybe you are looking for

  • Why does "Check for Updates..." show that there are no updates available while I'm using Firefox 3.6.18 and latest version is 5.0.1?

    First and foremost, I'd like to clarify that I hardly have any technical knowledge. So pardon me if this comes across as a silly question to the professionals. Here are the details pertaining to this problem as per the best of my limited knowledge: I

  • Problem in Search Help[F4] - Values Not being Dsplayed

    Hi, Search help values are not being displayed. F4 help pop up is being displayed with the text on top: ' xxxx number of entries found". But no values are visible in that popup where it normaly displayes all values for selection. This is happening wi

  • Links in Apple Mail not opening in Firefox 15

    Links in messages in Apple Mail have recently stopped opening Firefox tabs and windows. The Mail window fades, as if a new window or application were being accessed, but nothing happens. I have reset my default browser (according to Mozilla instructi

  • Agent Connection  failure

    I got a Database Instance and agent down. Agent Connection to Instance Status Failed Details ORA-12505: TNS:listener does not currently know of SID given in connect descriptor (DBD ERROR: OCIServerAttach) But Listener is UP I check tnsping and ping .

  • How can i Use the symbols from the main html page?

    Hello! Im trying to find a solution for days!! i need to use my symbols from the html page, for example to hide the symbol i want to use: sym.$( "sym1" ).hide(); or to make it draggable (with jquery UI) i wanna use: sym.$( "sym1" ).draggable(); but i