Service PR qty reduced than the PO qty

Hi,
For material PR, if the qty is reduced than the PO qty we can activate
06 648-Requisition quantity already ordered in full (see follow-on docs.)
but what is the message no for service PR line item control.(if the service PR qty is reduced than the Service PO qty)- for service line item.
we are not using the service master for for creation of service PR/PO

dear indranil,
thank you.
06 076 is applicable for material PO, it is not working for service PO.
as header line qty and not the service line qty
we have already checked the same.

Similar Messages

  • GR qty less than the SL qty.

    Hi Experts,
    I have 2 schedule lines scheduled for earlier dates.
    say, SL-1 -> 100, SL-2 -> 200
    If i do a GR (MIGO) against the SA today then it should prompt me the qty as 300.
    But the system is prompting a lesser qty (say 50). Why??
    What all do i need to check to resolve this...
    This is very urgent.. please advise...
    Thanks,
    Manju

    Hi,
    Since the SL dates are in the past, if i do a GR at the present date then it must allow me to receive the entire qty (i.e. 300 in this case).
    But, it is not allowing me to receive qty more than what it has proposed.
    I need to receive the entire qty that is due.
    Please advise.
    Thanks,
    Manju

  • Invoice qty greater than the PO qty

    Hi All,
    I have created material  PO with 100 qty Value 5000 and freight cost 1000 rs for the same Qty.
    Issue: at the time Freight Invoicing with PO/bill of landing
    Material: GR & IR Done for 100 qty -- No issue
    Freight: when am doing invoice (MIRO) i have given Purchase Order no and paid the freight rs 1000 for whole 100 qty
    Issue: If i do invoice (MIRO) by for the same PO and given bill of landing, system still proposing some qty 40 Qty and proposing some cost.. and able to save .
    but it should not propose the Qty... Plz let me know how to restrict it... In case freight Invoice
    Thanks

    Hi,
    not some qty... if i select the Bill of loading in MIRO, then system is proposing the whole qty for the particular item of PO.
    PO:123  100 qty  Fright cost 10  value 10000  Bill of Loafing:XYZ
    MIRO-Delivery plan: Done With PO whole Qty 100  freight cost 10rs value=1000 rs
    If i select :Bill of loading XYZ (Same PO and same item).. system is proposing same Qty 100 and value 10000..
    Thanks

  • Issud  qty is  greter  than  the   Reservation  qty

    Dears,
    I   Have  creted the   Resevation  100 qty  for  cost center 1.
    While  i  am    issuing  the   qty    to   cost  center system  is  allowing  more qty  than  the  reserved   qty100.
    Even  if  i  given  the  200  qty  system  is  posting the  Document .
    How  Avoid  this  Posting  and  where  i  ahve   to    cofigure  the    System   setting  please  Guide   Me.
    If  i  am   issuing the   More  qty  than  the   Reserved  qty  systemm  should  give  the   Error  message.
    Like issued qty  is  more  than  the   Reserved    qty .

    This can be controlled by setting the messages to Error in the Relevant application area.
    Go to SPRO-MM-Inv Mgmt & Phy Inv-Define attributes for System messages / use trxn code OMCQ and find the Relevant message number and set to Error and Save.
    Also Check in SPRO-MM-Purchasing-Environment-Define attributes for System messages / use trxn code OMC0 (trxn code may not work) and find the Relevant message number and set to Error and Save.
    Eg : 06 078 Target quantity exceeded by  & & etc

  • Header qty is less than the operation qty.

    To certain production order header qty is less than the operation qty. Please advise me.

    Dear,
    Base Quantity - Quantity of the material to be produced to which the standard values of the operation refer.
    Operation Quantity - Quantity planned for this operation.
    Base quantity and operation quantity may not always be the same, if we have partial lots delivered during the sequence of operations, the operation quantity will be equal to the lot delivered during the operation.
    Base quantity is dependent on the BOM, where it signifies the total quantity of output after using the components of certain quantity.
    In routing, you neeed maintained there operation quantity, and unit of measure of operation quantity accordingly with base quantity unit of measure.
    Check up the Processing formula used in the Scheduling tab of Work center (Use SAP002 = Machine * Oprn qty / Base qty / No. of splits)
    Hope clear to you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Oct 7, 2008 11:37 AM

  • Increased Qty in sales order than the Billed qty..  urgent

    Hi folks,
    When I am creating a return sales doc. with reference to a Billing doc,
    everything is getting copied on to the return sales doc.
    The Qty of the item is also getting copied on to the sales doc.
    But when i increase the qty of the item , it is giving me a warning message  saying " Qty is more than the billed qty." and thus allowing me to take it.
    The client want that this should be an error message and hence shouldnot allowed to take the increased qty.
    Can anyone tell how to make it an error message.
    thanx
    sourav

    Hi Sourav,
                  Check copy control settings in the transaction VTAF.
    In that you go to item level copy control check the field Pos./neg.quantity whether this field set as '-' or not.
    If not set enter - (Minus) then try
    If already enter you need to go for the User exits to cahnge the warning message to error message.
    I hope it will help you
    Regards,
    Murali.

  • Scheduling Line qty greater than the Scheduling agreement qty

    Hi Experts,
    1. I have a scheduling Agreement (SA), and the qty mentioned against this SA is 1000 (say).
    2. Now when i generate schedule lines for this SA (ME38), I am allowed to schedule more than the quantity that's mentioned in the SA.
    3. Please advise, is it possible to restrict this behaviour. i.e. I want to give an error message if the Schedule Line qty exceeds the SA qty.
    Please advise. Very urgent.
    Regards,
    Manju.

    Hi Manju,
    Yes its possible to restrict the case as u mentioned.
    Check the below settings:
    IMG-MM-Purchasing-Environment data- Define Attributes for system messages
    go to meassage no : 00-06-067 set it as Error message.
    U'll achieve ur result.
    Award points if its helpful
    Sangram

  • Returns qty accepting more than the invoice qty

    Hi Experts
    When i am creating a sales order with reference to invoice the system is allowing to enter the quantity more than the invoiced quantity.
    suppose the invoice quantity is 100 when i create a sales returns system is accepting to do returns for 150 also whichshould not be and also it is allowing to do so many times with the same reference document
    i am getting just q warning message that for this invoice reference already returns exists if i bypass the warning message system is allowing to do next time also
    how to do
    any user exits to control which checks the VBRK number and VBRK billed quantity and it should less or equal to VBAK quantity
    regards

    Hi,
    Yes, unfortunately SAP does allow it.
    We are using FORM USEREXIT_MOVE_FIELD_TO_VBKD of MV45AFZZ to have our own validation for the same.
    I hope this helps,
    Regards
    Raju Chitale.

  • Goods Issue Qty More than Purchase Order Qty ( Intercompany Stock trans. PO

    Hi All,
    I have following Issue,
    I can do Goods Issue more than qty which is in Intercompany stock transport
    purchase Order.
    I want to restrict this Process, It should not allow more than PO Qty.
    In the STPO Setting, Checking rule field is blank.Is this the reason for
    the Issue.
    Thanx in Advance.
    Key.

    Hi -
    This is controlled by setting at item level in purchase order / sto creation transaction i.e, ME21N.
    Go to item --> Delivery tab.
    You will see under delivery tolerance and over delivery tolerance.
    Please reward points if youfind this information useful.
    Thanks,
    Ramesh

  • Excess Qty confirmation than Production order qty

    Hi
    SAP Experts
    Is it possible to confirm excess qty of yield in co11n against Production order qty.
    pl. guide me the steps required.
    with Best Regards
    Yogesh

    Yes,
    If you do not waht to conform excess qty than the production order qty, then the following are the options
    - as our friend told in Work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
    - In production order the under/over delivery tolerance should be zero and unlimited delivery tick should not be active.
    - In OPK4 fior the combintaion of plant and order type the following confirmation parameters are to be maintained
    Under delivery - X error if qty below under delivery tolarance
    Over delivery - X error if qty above over delivery tolarance.
    With this settings you can avoid what you wanted.

  • Delivery Qty Greater than Sales order Qty

    Dear All,
    I want to do delivery against a Sales order,but system is allowing me to do PGI more than the Sales order qty,please advice where i can restict my PGI agisnt the Sales order qty.
    Regards,
    Muzamil

    Dear Prashanth,
    Thanks for your quick reply and resolution
    We have a problem when there is a delivery from projects(CNS0).When we are running the transaction CNS0 and entering  Qty 7, and creates delivery, system generates a Delivery Number and takes us to VL02N where we enter batch,picked qty and storage location.Here we find delivery quantity 7 by default and if we change the quantity from 7 to 10 even then system accepts more quantity as it checks the project stock.
    We want system should not allow the delivery quantity more than the quantity specified in the CNS0.
    We are not creating sales order as we directly delivering from projects.
    In the previous case,as you suggested we made the changes in delivery item category,but the same logic is not working here as it is without sales order.
    We are using item category DLP and Delivery type is LP.
    Request you to provide your valuable inputs
    Thanks in advance
    Regards
    Muzamil

  • Delv qty greater than sales order qty

    Hi ,
        We are on ECC 6 . In one of the del, delivery qty is greater than sales order qty.
        which resulted in overpicking. ( Sales order qty 560 , delivery qty 587 & Pick qty 587).
        This is over delivery & overpicking issue.
        Is there any way to stop this for ECC 6 version.
        Let me know.
    Thanks  & Regards

    Hi Tushar
    You need not maintain the over-delivery limit.
    If you set set "B" in the "Over Delivery" field in the Delivery Item category (0VLP), then system will not allow you create a Delivery with delivery quantity greater than Order quantity.
    I mean, if the order quantity is 10 pc, then with reference to that Order ,you can not create a Delivery for more than 10 pc.

  • Gross price of Service entry Sheet more than the value ordered in PO

    Hi all!!
    I have a PO that were created and changed by the following way:
    The user created the PO of service with the quantity = 1 and the price = 50.000,00
    Than he made the service entry sheet of this PO and MIRO normally.
    As the fields on service tab wasn't blocked, the user changed the quantity to 105.000,00 and the price to 1.
    After that, he made 3 services entry sheet to complete 105.000,00 quantities.
    With this, the value delivered became bigger than the value ordered in the PO.
    if I make a service entry sheet with a quantity of 200.000,00 for example, the message SE363 will be shown to me with a message that the "quantity entered exceeds quantity in purchase order".
    I'd like to know if there's a way by customizing of control the price on Service entry sheet based on the value ordered in PO instead of quantity.
    Can anybody help me?
    Thanks in advance,
    Cris

    Hi Ajit and Rajesh
    Thanks for the response.
    The user made a PO with one line with quantity 1 and net price 50.000,00.
    In the services tab, he put a sevice with quantitiy 1 and gross price 50.000,00, and than made the service sheet entry, and MIRO.
    After this he changed in the services tab the quantity to 105.000,00 and the gross price to 1 (with the objective of making more than one service entry sheet by quantity).
    With this, the system let the user make many entries of service allowing the user to make entries os sheet more than the net price that is in the line of PO.
    I'd like to know if there's a way configure the system to make a compare between the gross price and the net price when i'm doing the service entry sheet, because now when I change a line of service tab, the system is not considering that other service entry sheet were made.
    So that, i'm having the value of ordered bigger than the value delivered.
    Nowadays, the block is made by quantity as I said, but i'd like to block by price too.
    Sorry about the bad explanation before, I hope that now i explained better.
    Thanks
    Cris

  • A/R Invoice Qty Greater than Delivery Qty

    Hi All,
    Can I post A/R Invoice with the qty greater than the Delivery Qty????
    I came across a case where I have a delivery Document of 10Kgs But Qty changes to 10.5Kgs at the time of A/R Invoice posting.
    Is there any std feature available of we need to do any work around. Pls suggest.
    Cheers,
    Sree.

    Great.......
    Then the way is clear.
    You can manully edit the Qty at AR invoice row level.
    try this in Test DB first whether your effect goes right or not.
    But as per my knowledge it goes perfectly  even if you edit.
    It will increase your stock by 0.5 kg from GRPO stock.......
    Regards,
    Rahul

  • Delivery Qty should not cross order Qty

    Hi friends,
    When I am doing delivery for the qty more than the order qty, it is accepting. My scenario is delivery should not allow the qty more than the ordered qty. Delivery should be done only for the ordered qty.         I think it is possible. So can anyone tell me the settings for this?
    Rama rao

    Dear Arul,
    In your sales order, check which is the item category that is getting triggered.
    Can find it in in the item level , near to Customer Material Numb field.
    or double click on the item.
    you can see the item category in the TOP near to your material and sales document item.
    Now go to vov7 and select this item category and change the Completion Rule to B as advised.
    Check and revert back.
    Thanks & Regards,
    Hegal K Charles

Maybe you are looking for