Setting client role in non-production systems

In our QA test systems of R/3 and BW, the client role  in SCC4 was set to 'Production'. The reason I was given is that  by setting the client role to 'Production', will enable some settings in FI such as period closing,and customizing settings remain open  without transportable requests. I totally disagree with this. I worked on numerous projects, but this is first time I am hearing this. I always set client role to Test in non-production systems, without any problems. Do any one have  any idea about this?
Thanks
Santosh

SAP have a concept of "current settings".  These include things like exchange rates and other items which really appear to be configuration settings.  In a non-modifiable system these cannot be changed because the transport management system tries to get involved.  If the client is set to productive, this restriction is overridden.
I would always suggest that the QA system should be set to productive and non-modifiable to ensure that the behaviour of the transactions affecting such objects can be tested in a production-like environment.  If you need to have your QA system open for any sort of changes you are exposed to having changes introduced in QA to leading to the impression that new/modified functionality or config works but when the transport takes the unmodified version to production you'll be in trouble.

Similar Messages

  • Technical Monitoring one template used for production and non-production system.

    Dear All,
    Is there a way to have one template in Solman Technical Monitoring for production system and non-production system with different alerts ? For example if it exceeds a threshold for production system it will trigger red alert or set automatically an incident and if it's non prod system it will go to yellow warning alert ?
    Regards
    Lukasz Goral 

    Hi Likasz,
    You first create and customize the template, and then assign to a system.
    If it was selecting a system and then customizing a template, then may be such functionality makes sense.
    So, I don't think that is possible.
    Better would be copy the template used for production to non-production and make the adjustment to it.
    Regards,
    Divyanshu

  • How to make JOB CONTROL setting for delta extraction in Production system .

    Hello All,
    We are in the process to transport our development to PD server in BI . We have transported the data sources to ECC production and now we are filling the setup table for " SD BILLING BW " . After filling Setup table data in full mode through infoPackage we have to load data in delta mode .    
    How we can set our Update mode(LBWE setting) in PD server ?
    Is LBWE  T.Code authorisation required in ECC PD server to make the setting of Update mode   or   We have to set all  Job Control Paramater in Dev System at the time of transport the datasource request to ECC production .  Is our time which is set in job control of  ECC development  will be reflected in ECC production ?
    can any body tell me about how to make setting for delta extraction in Production system .
    Thanks ...

    Hi,
    How do you load the data in the development system?
    - you set up the update mode in the infopackage. There you must customize "Initialization"
    - you have to filled the setup table in the production system without laoding the data in the BW? then this step was for nothing. Filling the setup table and do the INIT in the BW, this must be together - during no changing will be done in your R/3 SD.
    Sven

  • SAP_ALL in non-productive systems

    Hello SAP Security Administrators,
    I have been searching (without success) for documentation or posts for a SAP security best practice for who should or should not have the profile SAP_ALL in a non-productive system.  Is this typically left up to the individual company security policies?  Is it a given that Basis will have SAP_ALL for administrative support?  Are Security Admins allowed to have elevated privs in a non-productive system for research and troubleshooting?
    We are trying to establish a standard for non-productive systems, so any input would be greatly appreciated!
    Regards,
    Janice

    I do not think there are real standards. Personally I consider using SAP_ALL a sign of utter lazyness because there is never a person who needs to access all functionallity in an ERP system.
    The only valid occasions I know to use SAP_ALL is during upgrades but even then it's not a guarantee against surprises.
    You are talking about non productive systems but that does not exclude systems with production data, something to consider.
    Some thoughts:
    Do you want people to influence developments and/or transports if that is not their task?
    Do you want pepole to see sensitive testdata just copied from production?
    Do you really think your system/landscape configuration will be safe if you have to rely on agreements? Transport routes for instance?
    SAP_ALL is something I only allow in sandbox systems and only if they're being backupped at least weekly. That is to avoid heavy discussions when people destroy each others work by curiously hitting buttons and 'trying' transactions.
    I am sure some others will have a few suggestions to add

  • Client Roles in a Three System Landscape

    I initially post this Question in other forum:
    Hi all,
    We have a three system landscape. In the Development client, we have the Customizing Client, the Sandbox Cliet and a Training client. I have some questions about this configuration:
    Acording to System and Client Settings - System Administration Assistant (BC-RRR) - SAP Library, Training client must be in Quality Assurance System, and it must be created by client copy from client QTST (it gets the transports from Custimizing). In this Training System we must create users for all our key-users to training. We must not create any user for key-users in sandbox client (this client is for the DEV team). is that ok?
    What are the downsides of having out TRAINING client in the Development System?
    Now, a consultant is asking me to open some modifications in the TRAINING client: He needs to load Exchange rates (OB08) in that client, but he is getting "Client is not modifiable". They are asking me to create users for key-users in the sandbox client and the training client.
    I need to know if they are using the system in the right way. I dont want the system to become a mess.
    I been reading this notes: SAP Note 356483. I don´t know what this means: "Now the corresponding Customizing object is no longer subject to the transport connection and is excluded from the changeability check. The change is active in all clients of the system. You can also change the Customizing object in a locked client (independent of the client role). However, now it is also no longer possible to manually transport entries of the view or table."
    Aditional notes:
    SAP Note 78329,  sap kb 356483
    Thanks for your help!
    One person answere me this:
    Hi
    You should create your question in the appropriate area :
    Software Logistics
    The drawback of having training client in dev system is that it could be negatively impacted by ongoing changes performed in that system (custom program that are changed, not working...)
    Some specific customizing changes can be set as current setting and thus can be modified without needing to open customizing but only if the client is set as productive.
    There is also a way do deactivate modification recording of objects (aka deactivating the transport connection) but, if you apply this change for this activity/object, you won't be able any more to record change into transport orders
    Regards
    356483 - Customizing: Current settings in the test system
    77430 - Customizing: Current settings

    Hi Andres
    I do not really now the exact impact, it might prevent some business data from being mass processed or overwritten...
    I did had to deactivate the transport connection on specific objects/activities for some customers.
    It depends on the frequency of that activity. I don't like to open the client to modification as you can sometime forget to close it back, and sometime also it gave the opportunity to other consultants to make changes that would create inconsistency among envt in the whole landscape.
    At least activating the recording of changes could help in tracking the source of modifications
    RZ10 => rec/client=ALL
    STMS => RECCLIENT=ALL
    Regards

  • Regarding Client Role change in DEV system.

    Hi All,
    I had some requirement from SapHR they want to do some Holiday calender changes in Sap Level.
    and we have only Test Role client in our Dev System. They want me to change the Client Role from Test to Customizing Client.
    Kindly let me know if Client Role is changes from TEST to CUSTOMIZING. is there any inconsistany in TMS.
    Thanks,
    Abdul

    Hi,
    Run BDLS to change the source system assn. Then check to see if all your transfer structures are active and also your source system is now the correct one. Easiest way is to goto RSA7 on the src system and see where the system is pointing to.
    Cheers,
    Kedar

  • EWA for non-productive Systems

    Hi all,
    is there a possibility to get Early Watch Alerts for Systems in a Solution, which are not marked as productive.
    I don't want to create many solutions.
    The same problem i have with the monitoring, I only see the productive in the monitoring overview.
    Regards
    Tobias

    >
    Schlosser Tobias wrote:
    > I have added Systems to the Solution XY. The Leading Role of this solution is "productive Systems"
    >
    > I have add System PR1 (Productive) and System DE1 (Development).  But I can only see the EWA for the Productive.
    > If I want to see the EWA for the Development I have to delete the log. components and switch the leading role to "Development Systems".
    >
    > That's very inconvenient.
    >
    > I wan't one Solution with all my Systems, and EWAs for every System in it. Is this possible?
    Yes, it's possible to have all systems (Prod, Dev, QA, ...) within one solution and to have EWA activated.
    You need to choose "Put in Solution" from the context menu. See screen shots attached.
    Regards,
    Ruediger

  • Source system deletion before copy or refresh of Non productive system

    Hi
    regarding the refresh of non prod BI system. . As part of refresh, we were asked to follow note 886102.
    In this Scenario B3 matches to us. While doing the scond step. I have to delete source systems from RSA1 except my self system.
    It is taking long time to delete source systems as each object of source system is prompting for request and consuming long time to complete thsi activity.
    Please help me with a smarter method to delete the sourcesystems.
    Thanks,
    Haaris
    Edited by: Hari Prasad Bolla on Jul 14, 2010 8:50 PM

    Hi:
    The primary source of information is the how to paper on this topic:
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/bff13df2-0c01-0010-6ba7-bc50346a6fd8
    YOu are correct, you can refreh the BI system without deleting the source system.
    Thanks for any points you assign (after all, I wrote the paper!).
    Best Regards -
    Ron Silberstein
    SAP

  • Setting Quality Assurance System Client role to Production

    Good evening all.
    I have had my customer ask if it would be possible to set the client role for our QA system to "Production".  The reason for this is that a number of transactions that they perform within production require that the QA system be opened when they wish to try them first in QA.
    Examples of the transactions are:  KSC1, KSC2, KSU1, KSU2, OB52, OB08.
    I know that changing the setting is possible, but what are the issues with doing this to the QA system?  Is this something that shouldn't be done except when necessary, and if so why?
    Thanks for your help!
    Joe Johnson

    Thanks for the answer, but I understand the process.  I am looking to see what the implications for setting a QA environment to a production role would be, and what are the negatives of doing so.
    The processes mentioned don't require that the production environment be opened, and the users would like to see the same for QA....
    Thanks!

  • Allowing Multiple Login of users in Production system

    Hello,
    In my office there are total 4 employes which all use SAP but they all use one username and password so it isn't possible for them to work at same time. Only one employe can work, then after he completes his task he must log-off, and then other employe logs-in and so on... So Multiple Logon option is disabled. I would like to enable Multiple Logon option but as I read it somewhere Mult.logons in productions system of users musbe set to off?
    I am not sure what do do because I need to have option for employes to lgoin at the same time with one username/password.
    If this is not possible is there any other way to achieve this? Also is there any way that one employe can enter/view data and other three employes can login at same time only to view data?
    Any help is appreciated and <removed_by_moderator> !
    Greetings,
    Adi
    Edited by: Julius Bussche on May 30, 2011 4:28 PM

    P1071191 wrote:
    Hi,
    >
    > In the default parameter, set the paramater login/multi_login_users,
    >
    > Set the value of this paramater login/multi_login_users UID1, UID2, UID3, UID4.
    >
    > May this solve your problem.
    >
    > Regards,
    > Vinod.
    >
    > Edited by: gvk1305 on May 31, 2011 8:36 AM
    gvk1305 wrote:
    Hi,
    >
    > In the default parameter, set the paramater login/multi_login_users,
    >
    > Set the value of this paramater login/multi_login_users UID1, UID2, UID3, UID4.
    >
    > May this solve your problem.
    >
    > Regards,
    > Vinod.
    >
    > Edited by: gvk1305 on May 31, 2011 8:36 AM
    @Jurjen Heeck
    Hello Jurjen,
    I have no intention to voilate any of license agreement, I had to do it once in emergency.
    @David Berry
    Hi David,
    There are four users in my office but I am not sure of exact total number of SAP users in my company.
    @R. Voerman
    Thank you very much for this information. I will try this definetly. Could you tell when I enter this parameter, then
    multi_login_users option is ON, right?
    @Julius Bussche
    You can also assign it selectively to more users than the length of the system parameter field allows...
    Hello Julious,
    how do I this in transaction SU01, what do I need to change?
    It's no problem form me to change this parameter but I am not sure if this is good because of security issues?
    http://sap-basis-security.blogspot.com/2009/01/how-to-restrict-multiple-logons-of.html
    Note:
    "Multiple logons of users must be set to 1 in sap production systems. This can be allowed in DEV systems. But in production it must be restricted."
    Edited by: samnovice on May 31, 2011 10:27 AM

  • Chart of account conversion SLO tool,method for a Production system

    Hi All
    We have a requirement like we want to use Chart of account conversion tool for a production system where transactional data are present.
    We have used this COA conversion tool for best practice solution not in a production system.
    we want to know the difference between these two methods like production and non production system.
    Provide me some process document on the SLO service tool for the same
    Mrinal dey
    9836265158

    Hi Mrinal
    I'm wondering the same? How to go on in productive system after to use the conversion toll?
    How did you manage?
    Regards
    Angels

  • Monitoring availability  - Different action for Production/Non-production

    Hi there,
    We've configured availability monitoring on our central monitoring system using CCMSPING agent. Everything is configured correctly and working nicely. However, I have a problem how to take a different action depending on whether alert was raised for production or non-production system.
    I've configured an autoreaction method for MTE class Availability_SysPercent_ABAP. This class is not dependent on the remote system. It is the same for all monitored systems, which is the reason for my problems.
    If I assign an autoreaction method to the MTE class, the same method will be called if there is an alert for any of the monitored systems. The autoreaction method automatically logs a new ticket in our call handling system. Unfortunately the call handling system can't parse the email to find out which system was the alert generated for. It can only raise a ticket based on some keywords in the content of the email.
    The way we configure CCMS for everything (apart from availability) is that we assign different autoreaction methods to different MTE classes. It can't be done in this case as there is only one MTE class. We can't assign different autoreaction method to individual MT elements as this is lost (see note 660126). One of the options could be to change CCMSPING to generate a different MTE class for production and non-production systems, but I haven't found a way of doing it. Another option was to have 2 CCMSPINGs, but they both use the same MTE class.
    Has anyone got any experience with this or can suggest anything we can try?
    Thanks,
    Rob

    Hi,
    Its still available.
    You can still assign different method to nodes.
    Its working fine , we are using.
    You can assign different method to different systems in RZ20  itself.
    Regards,

  • Difference between client Export/Import and a system refresh

    Hi Experts,
    I would like to know the diffrence between client Export/Import and System refresh.
    Actually i have done client export from our production system and imported it into our quality system, I have asked our functional consultants whether the production data is now available in Quality. They replied me saying whole data of production system is available in Quality system as off date i have copied the export.
    The size of the export was around 8GB, How can this have all the data of Production system which is around 600 GB.
    In this way what is the use of System refresh which is done by database level ( changing the cntrl file etc... ), As i am getting all the data by doing Client Export/Import.
    Thanks & Regards,
    Injamuri

    Hi,
    What is system refresh when and why it is done?
    The system refersh is nothing but the deletion of the client and replacing the data from other client. For example : you have clients 100, 200 and 300. Suppose when you want to refresh the client 100 you remove the client 100 and replace it with 200 0r 300 as per your reqiurement.
    Mostly the refresh of clients will be happen at the time of development stage.
    System Refresh is a simplified term to Client Copy. Client Copy means copying the production client on to the quality to test the real data. As recommend by SAP this need to carried out every 3 months.
    The process to carry out the same is as follows:
    1. Create a client on quality system using txn scc4
    2. Create a RFC between Production system and Quality System (need to create on quality system)
    3. Login to the newly created client using sap* and pass as a password
    4. Txn sccl to start the client copy.
    You can test the client copy by selecting the test run option. (test run will estimate the time taken for the activity).
    Anil

  • Procedure to make a system Non-Productive

    Hello All,
    I want to execute the program ZZ_DELETE_CRMPRLS in the R/3 system to delete the entry in the table CRMPRLS since the LOGSYS and LSGUID are wrong in this table and my material replication is failing. Making the system non-productive is pre-requisite for executing this program.
    Can you let me know what the procedure to make a system non-productive? I want to execute this program in my quality system. Tried locking out all the dialog users but it is not working.
    With Regards
    Sathya

    I think you have the setting in Scc4 to make client role as production or non production like test,development.
    Run Scc4 select the perticular client and then goto change mode and then change the client role.
    Thanks
    Rishi Abrol

  • SCC4- Client Role ? in Client Setting

    Hell Friends,
    I need some information on Client's Role Setting in SAP system  in SCC4.
    Which role need to be assigned to each client based on the requirement/purpose in a SAP System ?
    Here, i am giving brief information on the Clients created in our SAP System Landscape.
    SAP ECC DEV System
              100 - Golden Master Client
              110 - Unit Testing Client
              120 - ABAP Development Client
              190 - Sand Box Client
    SAP ECC QAS System
              200 - Integration Testing Client
              220 - Training Client
    SAP ECC PRD System
              300 - Production Client
              310 - Pre- Production Client
    Now, my question is which role is assigned to which Client in "Client Role" setting under SCC4, based on the Purpose of the respected client. ?
    I am waiting for your valuable response.
    Regards
    Bhavik G. Shroff

    Hi Presu,
    Thank you very much for your valuable response. This inforamtion is useful for the Client Setting in SAP System.
    But, I also want specific information for this setting in SCC4.
    Client Role:
                       C Customizing
                       D Demo
                       E Traning/Education
                       P Production
                       S SAP Reference
                       T Test
    Based on my client List, which Client Role need to be assigned to Which Client ,according to their Purpose ?
    Regads
    Bhavik G. Shroff
    Edited by: Bhavik G. Shroff on Jul 11, 2009 12:44 PM

Maybe you are looking for

  • My ipod isn't being recognized in itunes and not in my computer

    when i plug my 2nd generation ipod up it won't go to itunes and it wont even register in the computer. But when i plug up the 30 gig ipod it goes directly to itunes and it shows up in the address bar. I ran the diagnostic and it showed that the 2nd g

  • Site Recovery Manager (SRM) v6.0 fails to pair sites - certificate chain not verified

    I have used the default self-signed certificates throughout the vCenter and SRM setup.  When going to pair the vCenters, I get "Server certificate chain not verified".  These are 2 new VCSA 6.0 VMs (embedded PSCs for each) and 2 new Windows 2012 R2 s

  • Calling function by clicking a button in JSP?

    Can I call specific function (present in my JSP page) by clicking a button? Regards, sumit

  • Interface o8 on linux to aolserver

    I'm trying to set up AOL SErver to maintain pools to an oracle database with the ACS toolkit but i'm running into problems. The AOLSERVER log keeps reporting that the connection is null. I think the problem lies in the ODBC datasource option of the A

  • Array as Shared Memory - performance bottleneck

    Array as shared memory - performance bottleneck Hello, currently I work on a multi-threaded application, where many threads work on shared memory. I wondering why the application doesn't become faster by using many threads (I have i7 machine). Here i