We have one scenario that,  one of  cost posted to  wbs  on March 2006,   it was  settled to AUC,  on  April 2009 only. But as per our company policy whatever cost available in wbs,  it has to be settled  in subsequent month based on settlement rule.
My query is why  the system  was made settlement in April 2009 instead of  April 2006. How to  find out which  parameter was not maintained to run settlement. Is there any log available .
Your immediate response in this regards will be highly appreciated.
With regards,
V.k

For collective settlements, you have to define variants n then run a job in background or manaully by selecting variant. You define the group of WBS in variant which you would like to settle each period end. You might also set some Status limitaions for particular WBS to be picked up.
So my question was how were the Variants defined? Someone might have missed that WBS in Variant and hence it was not settled earlier. Pls chk you variants defined in CJ8V for your batch jobs.
Thanks
Sarang

Similar Messages

  • Reverse fo a settlement made in different year - KD283

    Hi folks,
    I need your help.
    Could you please tell me what to do to reverse a settlement made in a different year?
    By current settlement of an SD-Order position the error message KD283 - WIP/cost of sales can only be settled after reversal appears.
    It is because we had to reverse some settlements...we were able to reverse only settlements made this year, but those made in last year were not able to reverse.
    What to do, please?
    I have found the SAP note 140672, but I am not sure if it is the right way, because it might insult in COPA-FI difference. Am I right?

    Hi,
    There are two options:
    Option-1:
    a) You can perform reposting or manual allocation in the current period and thus transfer the costs back from the cost center/dummy order to the sender.
    b) Then, you have transferred the costs from the previous period which must still be settled or reversed into the current period.
    c) Finally, the costs are now selected during the settlement in the current period.
    Option-2:
    a) You can use the full settlement processing type (initial screen of the settlement transaction), the system checks whether or not there are debits not settled yet from prior periods, and if so it issues an error message. You can then immediately correct the relevant orders, possibly by reversing the settlements of the current period and settling the previous period again.
    b) For doing this, need to implement the correction of Note 586673 first.
    Since this (Note 586673) involves program corrections and a reversal of the incorrect settlements, no issues in the change to 'FULL' with the existing 'PER' rule.
    Regards,
    LakshmiPrasanna

  • Locking PDF but only allow further signatures & get the list of of changes made after signing

    Hi,
    I have looked at Adobe Acrobat 9.0 and found the Signing > locking feature which blocks any changes after the document is signed. I need to know whether using Acrobat SDK, one could implement a similar locking option via plugin in a way that it ONLY allows further blank signature fields to be created or sign existing ones and locks all other changes. If possible, any pointers to API functions would be appreciated.
    If the above is not possible using Acrobat SDK 9.0 then can the SDK provides a list of all the set of changes made after the signing is performed (at the time of verification) in the form of some codes which can guide the plugin author about what change after signing was done e.g.
    a blank signature field was signed
    a blank signature field is created
    watermark has been applied
    form is filled
    sticky notes/stamps/other annotations are added
    Regards,
    mwak

    Thanks for your response. I have just performed this:
    I signed a PDF ( having no prior signature or blank signature fields ) using Adobe Acrobat 9.0 and locked it. I am now not able to create more signatures on this PDF. I believe I can't add more signatures even using the Acrobat SDK and Lock means complete lock-down of the document. This is different to what you said " it restricts modifications EXCEPT for other signings" or may be I am not understanding it clearly.
    I created two blank signature fields. When I clicked on the first, there is no Lock settings at the time of signing. I believe because If it is locked then the next signature can't be signed. With only a single signature field present, the lock feature is there.
    So I believe I have to resort to the option of identifying the changes in a revision and then if it the change is related to say adding stamps, sticky notes prompts the user at the time of verification.
    Can some one point me to the API functions set which identify list the objects which have changed after signing.
    Regards,
    mwak

  • I upgraded to the new IOS, but lost data and apps. When I try and restore the only backup I see is the one made AFTER the lost data. How can I access an older backup from the cloud?

    I upgraded to the new IOS, but lost data and apps. When I try and restore the only backup I see is the one it made AFTER the lost data. How can I access an older backup from the cloud?

    Why don't you talk to apple and find out if backup exists? That conversation with apple will stop your guessing.

  • Upgraded to 5.0, then 5.0.1. In the process the various calendar "types" disappeared, but at least all entries showed in Ical, with entries made after the upgrade showing pinkish/red. Yesterday all formerly made entries, disappeared. any tips?

    Upgraded to 5.0, then 5.0.1. In the process the various calendar "types" disappeared, but at least all entries showed in Ical, with entries made after the upgrade showing pinkish/red. Yesterday all formerly made entries, both old and in the future, disappeared, only recently made ones in pink/red are shown. any tips?
    I did switch off and on, did a sync with itunes, etc, but no luck.

    RIM doesn't push the upgrades -- your service provider does so, once they have certified and approved the operating system upgrade for their devices.
    But, .973 does work on the 9520 in the manner you wish it would, I've used it myself on that model.
    1. If any post helps you please click the below the post(s) that helped you.
    2. Please resolve your thread by marking the post "Solution?" which solved it for you!
    3. Install free BlackBerry Protect today for backups of contacts and data.
    4. Guide to Unlocking your BlackBerry & Unlock Codes
    Join our BBM Channels (Beta)
    BlackBerry Support Forums Channel
    PIN: C0001B7B4   Display/Scan Bar Code
    Knowledge Base Updates
    PIN: C0005A9AA   Display/Scan Bar Code

  • Report logic to get net payment made after creditmemo posting

    i have to create a report for vendor payments made against a project i.e wbs.I am able to get the details of invoice from BSEG and payment clearing from BSAK.If i have posted credit memos to these vendors how could i get them included in the report to ensure i could derive at the net payment made to vendor including the credit memo posted.How do i get the net payment after considering the creditmemo posted.

    Hi, you can use the posting key logic, normally the posting keys used for invoice, credit memo and clearing document will be different. You can take help from debit or credit indicator also.

  • CBO madness after bulk loading

    This is an extension of my other recent posts, but I felt it deserved it's own space.
    I have a table of telephone call records, one row for each telephone call made or received by a customer. Our production table has a 10-field PK that I want to destroy. In my development version, the PK for this table is a compound key on LOC, CUST_NO, YEAR, MONTH, and SEQ_NO. LOC is a char(3), the rest are numbers.
    After a bulk load into a new partition of this table, a query with these 5 fields in the where clause chooses a second index. That second index includes LOC, YEAR, MONTH, and two other fields not in the PK nor in the query. The production instance does the same thing, and I was certain that having the 5-field PK would be the magic bullet.
    Oracle SQL Developer's autotrace shows a "Filter Predicates" on CUST_NO and SEQ_NO, and then the indexed range scan on the other 3 fields in the second index. Still noteworthy is that query on just LOC, CUST_NO, YEAR and MONTH does use the PK.
    Here are the steps I've taken to test this:
    1. Truncate the partition in question
    2. Drop old PK constraint/index
    3. Create new PK constraint/index
    4. Gather table stats with cascade=>TRUE
    5. Bulk load data (in this case, 1.96 million rows) into empty partition
    6. autotrace select query
    7. Write to dizwell in tears
    This table also has two other partitions for past two cycles, each with around 30 million row.
    Yes, gathering table stats again makes things behave as expected, but that takes a fair bit of time. For the meantime we've put an index hint in the application query that was suffering the most.

    First, the CBO doesn't actually choose a full table
    scan, it chooses to use a second index.Depending on the query, of course. If the CBO thinks a partition is empty, I would suspect that it would find it most efficient to scan the smallest index, and the second index, with fewer columns, would be expected to be smaller. If it thinks they are equally costly, I believe it will use the one that was created first, though I wouldn't want to depend on that sort of failure.
    I've lowered the sample percentage to 10% and set
    CASCADE to FALSE and it still take 45 minutes in
    production. The staging table was something I was
    considering.
    Are statistics included in partition exchange? I've
    asked that question before but never saw an answer.Yes, partition-level statistics will be included. Table-level statistics will be automatically adjusted. From the SQL Reference
    http://download-east.oracle.com/docs/cd/B19306_01/server.102/b14200/statements_3001.htm#i2131250
    "All statistics of the table and partition are exchanged, including table, column, index statistics, and histograms. Oracle Database recalculates the aggregate statistics of the table receiving the new partition."
    You could also just explicitly set table-level statistics, assuming you don't need too many histograms, possibly gathering statistics for real later on.
    Justin

  • HT4437 what date does my iMac have to be made after to do airplay

    After what date does  your apple need to be made to have air play?

    Welcome to the Apple Community.
    AirPlay Mirroring requires a second-generation Apple TV or later, OS X 10.8 or better and is supported on the following Mac models: iMac (Mid 2011 or newer), Mac mini (Mid 2011 or newer), MacBook Air (Mid 2011 or newer), and MacBook Pro (Early 2011 or newer). It also requires the computer to be using wi-fi.

  • Activity of settlement rule after closing of IO

    Hello,
    i have that case: I closed one IO, after that i run the transaction KOSRLIST_OR and the status of the settlement is ACT. Please advise hot to deactivate that IO.Is it normal after closing of IO to have that kind of status?
    Thank you in advance!

    Hi Sri Ram,
    I had done same thing as you mentioned, I had assigned settlement rule in project definition. I had selected copy from superior WBS element system is showing same error " Superior WBS element not found and nor automatic settlement rule is created after saving project.
    Regards,
    Varun Maheshwari

  • Iphone 5 batt draining like mad after ios 6.1.2

    Hi Guys,
    I am experiencing seriously bad batt life after upgrading to ios 6.1.2. I really regretted upgrading. Batt life was fine with ios 6.0. After this stupid update, my phone is losing like 10% batt every 1 hr of use. I am seriously very disappointed with Apple. If this is the kind of crap they give to their customers, i am seriously considering a switch to an android phone. For those who have not upgraded their os, please DONT upgrade. I have give up believing in Apple and their claims of upgrades being able to fix problems... because with each upgrade, things will only get worse.
    Adwordh

    Any way to prove this problem guys? This battery problem is driving me crazy...

  • Issue coming when a call is made AFTER pr1.3 updat...

    hi
    I upgraded to PR 1.3 and am facing a issue regarding call whenever there is a incoming call or out going call the screen gets locked and i mannually have to unlock the screen and thn operate.
    I cnt even see the proximity sensor working.
    Please help me with this issue.
    what step shuld i take?
    thaknx

    There can be problems after the update due to the apps installed before the update.
    I had 'custom ringtones per contact' installed previously and after updating, there was no ringtone for any incoming calls. A reinstall of the app fixed it.
    Just to be clear I removed some apps such as this one and did a reinstall of the 1.3 update through NSU and restored the apps (some through the auto reinstall and some manually)

  • Automatic Settlement just after confirmation

    Dear Experts,
    Please advice how the Process Order got automatically settle once the Process Order confirmation happened, if possible.
    Because in variant of settlement CNF status of Process Order not exist.
    Please advice
    Regards
    Sumit Kalyan

    Sumit,
    Why you want to do this? In standard condition system should settle all orders for which cost has Incurred during the period , so that the Settlement period and Posting period will be matching.
    Please explain why you want to prevent PCNF orders from settling.
    Regards,
    Prasobh

  • Investment measure settlement doubles after investment profile change

    We changed the indicator "Summary Settlement/Line Item Settlement" in Investment Profile (which was already used for Investment Measures) and "Amount and Percentage" indicator to allow the amount wise capitalization of AuC/Investment Measure on various fixed assets.
    Now, while we try to settle the amount through CJ88, the system is settling the values that were already settled in previous periods. As a result the expenses become understated and Asset are over stated. How can we resolve this issue while we have already changed the Investment Profile as mentioned above.?

    We are trying to settle March 2014 period therefore we can't carry out any new postings other than settlement.
    For your reference, here is the Case:
    EAC003 is an expense account and primary cost element
    ABA001 is CWIP Account with Statistical Cost Element
    The amount posted in March 2014 on account EAC003 is 323,813 which has value type 4 (Actual). When we run the settlement, the system settles the amount 3,053,065 (including 2,729,252 of value type 11: Statistical Actual)

  • Business Script to be made after Splitvaluation configuration

    hi,
    after configured Splitvaluation my boss asked to prepare Business Script for that.
    what is business script and how to make.?
    Regards
    rk

    Dear,
    Business Script:
    Integrated Business Scenarios are events, transactions, and information, including reports, that are required to run the business. They are an ordered sequence of Business Process Scripts that represent a typical situation that occurs within the business. Integrated Business Scenarios cut across subsystems and business processes to form an integrated view of the functionality.
    An Integrated Business Scenario can be functionally-based or time-based. For example, Customer Order Processing is a functionally-based Integrated Business Scenario and Month-End Processing is a time-based Integrated Business Scenario.
    For each Integrated Business Scenario, prepare a brief one or two sentence description of the scenario.
    The Integrated Business Scenarios will be used to:
    · determine what functionality the selected package should provide,
    · determine how the package provides the functionality,
    · determine what functionality will need to be addressed in another manner, such as a manual procedure,
    · serve as the requirements for the new system,
    · serve as input into the creation of system test scenarios.
    The Integrated Business Scenarios are the features to be supported by the system; they normally do not include edits, calculations, or detailed processing logic.
    Identify Preliminary Business Process Scripts
    Start identifying the Preliminary Business Process Scripts.
    The Business Process Scripts are the steps required to perform a specific function within a business process. For example, the business process Purchase Order Processing may include scripts for Creating a PO, Approving a PO, Releasing a PO, etc.
    Use Process Flowcharts, Use Cases, or Integration Definition Model 0 (IDEF0) to graphically represent the steps in the scripts and to graphically show which Business Process Scripts are used within each Integrated Business Scenario.
    For each Business Process Script, prepare a brief one or two sentence description stating what is to be accomplished by the specific script (i.e., the "what") and the business rationale for doing it (i.e., the "why").
    The Preliminary Business Process Scripts will later be refined to:
    · map to which package module satisfies the steps in the Integrated Business Scenario (i.e., the "how"),
    · map to which organizational structure (i.e., the "where") performs each step,
    · describe which package role (i.e., the "who") executes each step,
    · describe the time needed (i.e., the "when") to execute each step,
    · describe which data is used or exchanged in each step,
    · serve as input into the creation of system test scripts.
    Tips and Hints
    Most organizations have about 20 major business processes.
    Start with business model diagrams developed during Strategic Systems Planning or Enterprise Wide Architecture Strategy activities.
    Create a list of questions to help determine the specific requirements during customer interviews.
    Defining the Business Process Scripts and the Integrated Business Scenarios are often done in parallel with each other. It is usually an iterative procedure to identify all of the necessary Business Process Scripts and Integrated Business Scenarios.
    If a package has already been selected, this task should still be done in its entirety so that the requirements are well defined. Don't be influenced by the capabilities of the package; critical requirements not met by the package may exist.
    Use a tool such as a spreadsheet or a database to help track and maintain the business process scenarios and scripts. CASE tools and workflow tools are useful to maintain and graphically depict the business processes, scenarios and scripts. If a package has already been selected, a tool may be available that works in conjunction with the selected package.
    Regards,
    Syed Hussain.
    Edited by: Syed Hussain on Aug 21, 2009 1:51 AM

  • Purchases are still being made after i deleted app

    i deleted this app a long time ago but every now and then its still making in app purchases. I would like to know how to stop that.

    If you subscribed to something in the app, you will need to re-download the app and un-subscribe. It is highly dependent on the app you did it in. Deleting the app will not stop it from charging you.

Maybe you are looking for

  • Wired Network conputer cannot find host printer

    I cannot print to host printer on a home wired network. Printer is HP Photosmart 7520 e all in one. Host Compter is a Dell Dimension 8100 Pentium 4 1.3 GHz  2.0 GB RAM Windows XP SP3 host computer. Netgear N600 Dual Band Router Model WNDR3400 Network

  • Connecting to an LG BD370

    Here's what I have: an Airport Express and the BD370 Blu-Ray player, which I'd like to connect to the internet for Netflix streaming, but is not wireless. What are my options here? Do I have to purchase a new router with available ports? Any help wou

  • Problem with pdf as email attachment

    Hi All, when i am opening the pdf file(email attachment), getting the error  "file type not support or content conversion....." the peice of code is as followed... IF p_email = 'X'.     CALL FUNCTION 'RSPO_RETURN_SPOOLJOB'       EXPORTING         rqi

  • Examples of "change of address"

    has any one seen some good examples of "change of address" cards or flyers? its for a job for a local telephone franchise. any tips greatfully accepted.  Im thinking that a map is a good idea.

  • How can I get the special keys on my external Cherry keyboard to work?

    Hi, so I'd like to get my external Cherry Evolution Stream XT keyboard fully supported. How would I go on about that? I know there [is a guide on that issue](https://wiki.archlinux.org/index.php/Ex - ys_in_Xorg), but how do I know which keycode/numbe