I am having issue during period end closing. Settlement say no accrued amount found for settlement. But when I see report project has the following values,
(rev)-2000
(cost)1500
Total=  -500
Should these costs/ rev need to be settled some where as a period end closing? If yes then where? CJB2 generates profitability segment rule.
Do I need to run WIP before settlement? Project is already billed. (When I go there WIP shows this error 'KJ217 revenue are not planned')
When I do not bill customer only charge employee hours in project. WIP shows value and allow executing. And so the Settlement of project. So can settle expanses to PA and see report.
Addition Info:
We are creating projects from contract. There are services provided to customer in this particular scenario.
We are assigning employee hours from CATS and activity planning from CJR2 on WBS.
Billing customer using RRB and creating billing doc and invoice from there.
WBS has RA key assigned for RRB
Settlement rule automatically generate rule to settle in PA segment.

Thanks you for the quick response. When I run KKA2 it gives me the following message:
"Planned revenue for valuation is zero". I already have revenue planned in the project from cj42.
Please explain
Thanks

Similar Messages

  • Service Charge Settlement

    Hy,
    please can somebody explain me the process of service charge settlement?I don't understand how is using the settlement units and how the postings are made.
    Thank you very much.

    Hi,
    I've added an excerpt of the online documentation of RE-FX which gives an overview over service charge settlement.
    I know that are only basics but maybe it helps you to get a better understanding. If not please tell me where you need more detailed explanation.
    Regards, Franz
    Purpose
    You use service charge settlement to distribute apportionable costs that arise during a particular settlement period to the tenants.
    Process Flow
    Below is a description of the processes involved in service charge settlement.
    I.    Master Data for Settlement Unit, Rental Object, and Contract
           1.      Enter measurements in each participating usage object.
           2.      Assign the usage objects to a participation group for each business entity.
           3.      Create a settlement unit for each service charge key, and assign the rental objects participating in the settlement to this settlement unit using the participation group.
    If costs for more than one settlement unit were jointly invoiced, you must create a master settlement unit.
           4.      The settlement participation is automatically generated for each contract. However you can define exceptions in each contract.
    II.   Incoming Invoice Posting
    Account assignment of service charges is made to the respective settlement units or master settlement units in the Financial Accounting (FI) component. The settlement amount is transferred automatically to the correct settlement period by means of the settlement reference date.
    For postings with extended withholding tax, only advance payments posted as revenue are considered for the conditions relevant for service charges. The system does not support special general ledger processes with withholding tax. The standard withholding tax term is often used during service charge settlement. You can determine the term from the conditions only in the Transfer Posting Advance Payments Debit Balance settlement mode.
    III.  Execute Service Charge Settlement
    Execute the service charge settlement run at the end of the settlement period:
    ·        Advance payments are transferred in a batch input session.
    ·        There are several steps involved in the settlement. You can save each step (except posting) and call it again.
    ·        The results of settlement can be posted directly to Financial Accounting.
    For more information on performing service charge settlement, refer to Simulating and Executing Service Charge Settlement.
    Result
    Depending on how you set it up, the service charge settlement performs the following activities:
           1.      Calculation of total costs for the settlement period for each service charge key
           2.      Cost apportionment to the relevant contracts or rental objects
           3.      Posting of cost shares to tenant accounts
           4.      Determination of the advance payments (actual payments) made by the tenant for which credit transfer postings are made

  • Problem with project settlement

    Hi,
      I want to settle cost in project system by exclude some cost element for example
    Cost was posted against WBS Y.001 with 2 lines item. cost element 10001 -  100 usd
    20001 - 200 usd
      Our requirement is only cost element in range 10000-19999 can settle to cost center, for other cost element cost remain in WBS.
      But when i excecute project settlement system generate error message as u2018Cost element 20001cannot be assigned to a settlement cost assignment in allocation structure ZGu2019. For allocation sturture ZG i was maintain cost element in source form 10000 - 19999
    So, Is it possible to settled by exclude some cost element even cost have posted to?
    Thanks so much,
    june.

    Hi Pornat,
    Please check Allocation Structure before cheking the Settlement Profile.  In allocation structure the sender cost object and receiver cost object is there, pl check it.  if u need any inputs then let me know.
    raj

  • Project Settlement Issue

    Hi All,
    We had an invoice that was entered with a wbs that had the following currencies:  CO Currency = USD, Transaction Currency = USD and Object Currency = GBP within a company with a currency of GBP.  However, when settling through CJ88, the settlement produces CO Currency = USD (zeros out), Transaction Currency = GBP (balance) and Object Currency = GBP (zeros out).  So, when you try to settle for the next month, CJ88 states that there is an error states "Execute amount settlement up to and including settlement period 003 2009 first"
    Message no. KD262. 
    As a bit of background, the project is in USD by some of the wbs elements within the project are based in GBP from the company code which is in GBP.  I'm not sure how to have the settlement work out so that there is no balance.
    Any assistance would be greatly appreciated!
    Pete

    Hi Sarang,
    We settle on an individual wbs element so I tried reversing the settlement and then re-settling the wbs once again.  The same issue is occurring where the CO Currency = USD, Transaction Currency = USD and Object Currency = GBP within a company with a currency of GBP. However, when settling through CJ88, the settlement produces CO Currency = USD (zeros out), Transaction Currency = GBP (balance) and Object Currency = GBP (zeros out).  In order to properly settle, all 3 currencies need to zero out but it is still not working.
    Any other thoughts?
    Pete

  • Customer service Order settlement

    Resource related billing.
    I created a Service Order. I finished all the steps from Create Order to Billing VF01.
    Next Service Order Settlement. I did not activate Profitability. I freezed the settlement profiles and allocation structure.
    I configured the settlement to Sales document item.
    I cannot settle the order. if I give Sales document also in settlement rule order is not accepting.
    Suggest.

    Error message.
    Maintain the settlement rule of the sender.
    I have maintained the settlement rule. I have assigned a settlement cost element  to receiver category as SDI.
    I got the error message when i do settlement.

  • Error message KI089: Substitution of settlement senders is not allowed

    Hi ALL,
    To meet the demand of the company, was created a substitution (OKC9) to replace the field value COBL-AUFNR through a user-exit. However, when performing the process that calls the exit in question (transaction KO88) is shows the error message KI089 (Substitution of settlement is not allowed senders).
    Searching the SAP Support Portal could see that there is a note to resolve this problem (SAP Note 317894), but this note would not be valid for SAP ECC 6.0.
    Does anyone know whether it applies to SAP ECC 6.0? I think it's the only solution to solve the reported problem.
    Regards
    Kelson Marcos

    Hi
    I believe the sender should never be substituted. If you posted values to an Order, the same should receive a credit upon settlement. Else, it negates the whole concept of settlement
    I referred to the note you mentioned. What I perceived is you cant substitute a sender during settlement and thats right as per my knowledge
    Ajay M

  • Automatic Asset creation through Project settlement

    Dear All,
    We have one issues where in AS02 AUC Asset quantity is in display mode still we can find the quantity there.
    Can any body help me about the Process of Auto Asset creation through Project settlement.
    I need to know how system calculate the Quantity from the Project settlement. if such type of Process exist in SAP
    Thanks
    Abhijeet
    Edited by: Abhijeet  Patil on Oct 5, 2011 3:05 PM
    Edited by: Abhijeet  Patil on Oct 5, 2011 3:05 PM

    Hi,
    There is process in SAP where we can create AuC from Projects. We need to have an investement profile set up and the same needs to be used in the project. You will have the details in SAP Help documnetation for this.
    Regards
    Sreekanth

  • Assiging wbs element as settlment receiver in service order settlement

    Hi PM CS Experts.
    We are using scenarios of creation of service order from sales order. So whatever cost we incurred for service order settling to sales order via settlement rule - settlment receiver is Sales order i.e. SDI. We are using settlement profie XX which have default object type for settling SDI.   While releasing the service order the settlement rule created with settlement receiver is SDI.
    Now for different business scenarios, we are settling service order cost to WBS. Now we want to create a settlemetn rule for WBS, settlement receiver will be WBS element,  while saving the service order.  What configuration, master data or processes we have to follow for this.
    please reply on this.
    regards
    abhay

    Sales Order line item have account assignment WBS element. From this sales order line, a service order will be created.   So our idea is whatever cost booked to service order should be settled to wbs element instead of sales order.  
    also in location tab of service order, the wbs element from sales order is not inherrited in account assignment section.  Why this we are not knowing. Have you have any idea for this.
    regards
    abhay

  • Project Settlement @ Project Systems

    Hi Experts
    I am working on how to settle a Project in Project Systems.  Could you please provide me guidelines how to do it.
    I am also looking for the connection/relation between Project Systems and Result Analysis of Product Costing.
    Thank you
    regards,
    S. Habib Pasha.

    HI
    The moment you say that the settlement to GL account, it is an external settlement i.e CO to FI ( WBS element being a cost object ) . In the allocation you need to have settlement element as an external settlement element with category "22" . When you are settling to a GL account and if it is a cost element then it will ask for a co object still as the system simultaneously needs to post to controlling as well. Yo make this setting for the GL account through automatic account assignment in transaction OKB9.
    I this will solve your problem
    Anand

  • Final settlement in Service Charge settlement

    Hi Experts
    My client wants their customers to pay their bills when they have recivecd their bills. How should thisa be represented in the SAP system . The flow types available in the system are those for advance payments and flat rates. Which flow type should i adopt for this scenario?
    How should this also appear in the application side?
    Regards
    David

    Hi,
    You should acticate the service charge settlement functionality.
    1. one posts the incoming invoices on settlement units
    2. one runs the service charge settlement which distribute the costs to the rental units and invoices the tennat if he participates in the service charge settlement (which generates open items in FI)
    3. one runs the invoice processing (which is based on the open items in FI
    regards
    stefaan

  • Settlement of Revenue Bearing Project

    Hi,
    Please tell me where can we settle a Revenue Bearing Project to ? I don't want to settle it to a PSG segment . Is it possible settle to the sales order line item (SDI) . Revenues or customer down payments can only be settled to G/L accounts, profitability segments, sales documents (SDI). so please anyone explain how to settle against sales document (SDI) what is prerequisite for this. Please explain step by step if possible.
    Regards

    Hi Nivrutti ,
    You are repeating your question so many times.
    Please study about settlement and check why you want to settle your projects.
    Muzamil

  • Service Order Settlement - assigned to PSG

    Hi,
    I need a help regarding Service Order Settlement assigned to Profitability Segment.
    Currently, in our system every item of SD Invoice posts revenues and COGS to profitability segment (PSG).
    Main characteristic of PSG are: Customer, Product, Division, Profit Center.
    We have implemented CS module using in Car maintenance service.
    And now in CS module it is not possible to get PA document automatically after an invoice posting so we have to settle Service Order to PSG.
    But Settlement rule for Service Order is not on item level (per every material-product separately).
    We wants to have the same rules (per Product char.) for Service Order as we had so far in SD.
    Is it possible to customize Settlement rule of Service Order on item level?
    For instance according to an Invoice items from document flow:
    Thanks,
    Zoran

    Resolved

  • Service charge settlement to 2 Business Partners assigned to a contract

    Please can someone explain how to settle service charge costs to 2Business partners'accounts. For example if we have a rental unit with a tenant and also a landlord of that rental unit and both are picking up costs for different service charge costs or the same service charge costs, how will these be apportioned to both of them.
    I have tried assigning 2business partners to one service contract but after running the service charge settlement, the costs were only settled into one business partner's account.

    Hi,
    please check if the functionality Condition Split, available with Enhancement Package 2 in Business Function RE_GEN_CI_1, might meet your requirement. Further information is available in the release notes of the Business Function.
    Hope that helps.
    Regards, Franz

  • Project Settlement - Aggregating/Settling on new custom field

    At our company, we created a new custom field called "Location Code" that is populated during journal entries through manual input. When an entry to a WBS element is posted with a Location Code value entered, the Location Code value also gets carried over to CO (controlling), SPL, and is in PS. The problem we have is with settlement as it does not carry over the Location Code at the final settlement receiver. For example:
    1. Journal entry is posted to WBS element H01.12345.01.01 with Location Code value entered of "435" (this is a field in the FI document posting screen) for $100. Another entry is posted to the same WBS element but with a different Location Code of "080" for $200. Both entries to the same G/L account.
    2. Settlement is run to settle the 2 entries in Step 1 above which totals ($200 + $100) $300. WBS element H01.12345.01.01 will settle to a cost center.
    3. When we view the final accounting documents (especially our special ledger purpose documents), Location Code value is blank and there is one entry to the receiving cost center for $300. It seems project settlement aggregates entries based only on WBS level and G/L account.
    QUESTION: Is it possible (and if so, how) to get projects to settle these lines individually based on aggregating on Location Code as well as G/L account? We would like to see $200 settle to the receiving cost center with Location Code value "435", and another line settling $100 to the receiving cost center with Location Code "080".
    I hope I made sense. Thanks in advance!

    line item settlement should only be possible if the setting is maintained in the IM Profile and it sounds like your projects don't have an IM profile...  so it shouldn't work.  I haven't used it on a non-capital project but you could give it a shot.
    [-nathan|http://wiki.sdn.sap.com/wiki/display/profile/Nathan+Genez]

  • Service Order settlement

    Hi,
    I need to set-up settlement of a service order. Can anyone tell how to go about it? To which elements does usually a service order settles? Primary/Secondary, is secondary the how does it get posted to G/L ?
    Thanks,
    Pankaj.

    hi pankaj..
      Settlement takes place through settlement rules you have created for the order.The costs are initially collected on the order. They are then transferred to the settlement receiver (Fixed asset ,Cost center ,WBS element,Order ,G/L ccount ,Material ,Asset under construction etc)specified in the settlement rule.
    You can settle an order if:
    1.It is released
    2.It has the status Settlement rule created
    3.Costs collected for it have not yet been settled
    4.A business completion has not yet been performed for it
    Creating a Settlement Rule Manually
    Call up the order in change mode.
    Choose Settlement rule.
    The following cases can occur:
    If a settlement rule already exists for the order, you reach the screen Maintain Settlement Rule: Overview directly.
    Check the settlement rule.
    To change it, go to detail data on the Maintain Settlement Rule: Distribution Rules screen, where you can make additional entries.
    If a settlement rule does not yet exist for the order, you must first specify whether you want to maintain the settlement rule with or without the system proposal for the distribution rule. A screen appears where you can maintain the settlement rule.
    Make all the necessary entries on this screen.
    Return to the order and save it.
    I think this will help you
    kkumar

Maybe you are looking for

  • How to get one crystal report to work with two different backends?

    We have a software that can work with either SQL2008 or Visual Fox Pro backend.  We are trying to compile One Crystal report that will work with either of the two backends.  How to you make sure that your Crystal Report is compiled so that it will wo

  • How do I transfer apps from Itunes to my iTouch?

    Hi! I'm a new apple user.My father bought me a new iPod touch. I have downloaded some apps from iTunes in my PC (Windows 7), and I want to transfer it to my iPod touch. I thought that syncing would do the trick. But there's a pop up message box sayin

  • Error while importing connections back into SQLDeveloper 1.5

    I have the XML export file from version 1.2 which is erroring out while getting imported to version 1.5 The following is the error message: "No connections are defined in c:\SqlDeveloperConnections082404.xml" The export file contents look readable an

  • How to set schedule in JBOSS 3.x?

    As you know, JBOSS can set schedule to do something. So I want to use this facility to schedule a task. The task is as follows, 1. At 23h59'59 everyday, the task will be done. 2. Or At 23h59'59 in the last date of month, the task will be done. I use

  • Clear the Browser cache while Outputting PDFs

    Hi, I am using Servlet to output a PDF (Streams), i am facing Browser cache problem in IE since i am setting Content type to PDF as follows... response.setContentType("application/pdf") i could not able to use follwoing Clear the Browser Cache respon