Settlement of customer project--without COPA

Hi guru's,
We do not have COPA in place here...so how to settle our project.
please provide me any revlevant doc regarding settlement from the config as well as execution of settlement point of view.
I need to sit with my CO consultant.
My counter part CO Consultant has not worked with PS integration so he is not having idea about the settlement for projects....i need to make him understand.
Please help me.

Recommendations in Customer Projects
In customer projects, the actual costs are settled, but accrued amounts (such as costs of sales or inventory from which revenue can be generated) are not. You carry out this settlement at billing element level.
For customer projects which you settle in full to Profitability Analysis, it is a good idea to generate the settlement rule using a strategy defined in the IMG. The standard system we deliver includes a strategy for automatically generated settlement rules for customer projects.
The system uses this strategy to generate the following:
u2022     For all billing elements:
o     Results analysis key
o     Settlement to profitability segment
o     A settlement profile providing for settlement in full
u2022     For all other WBS elements
o     No results analysis key
o     A settlement profile providing for no settlement
If account assignment elements within a billing structure do not contribute to the cost of sales, you can change the settlement rule manually.
If you maintain the settlement rule manually, we recommend you proceed as follows:
u2022     Use a project profile with a settlement profile that forbids settlement. This initially prevents settlement for all the WBS elements in the project.
u2022     Change the settlement profile in the billing elements manually. Define a settlement profile that permits settlement.
u2022     If you want to settle account assignment elements (in whole or in part), you must change the settlement profile for account assignment elements manually.
You change the settlement profile in the settlement rule for the object by choosing Goto  Settlement parameters. There is a parameter in the settlement profile which you can use to define whether settlement is forbidden, allowed, or required.
Avoid making settlements within the project hierarchy. These can adversely affect system performance.
For more information on settling customer projects, refer to  Settlement in Product Cost Controlling .
Regards,
ANSAR

Similar Messages

  • Close of Customer Project without Settlement

    Hi All,
    Is it necessary to have Settlement rules for the Projects that are Subject to Result Analysis.
    We want to Close the Customer Project without settlment, Since the RA has been carried out for this project.
    When we are trying to Close the Project.Error Message.Still WIP Exists for this Project.
    Please suggest what is the best way to close the Project without carrying settlement Run.
    Regards,

    Try this,
    Create a settlement profile as "Not for Settlement", check the radio button for "Not for Settlement" and in the valid receivers maintain the option in the dropdown as Settlement optional or Settlement Not Required. Assign this Settlement profile to the project profile as well as maintain it in the settlement strategy for the respective Object.
    Once you are done with this, run your usual scenario and then try to close the project without running settlement. See what happens and revert with your findings.
    Regards,
    Gokul

  • Problem while settling the customer project

    Hi
    I am trying to settlement of customer project, but  while doing so It says investment measure rather than processed when trying to generate settlement rules – bal of $5000. Please can any body tell where would be the actual problem.
    Thanks & Regards
    Satish

    Hello Saurabh
    I have not assigned any invest profile in project. But in the table PRPS for all these
    WBS elements an investment profile has been assigned. When I make settlement run
    CJB2 it say processing is done with out error. But in the processing category the following message is displayed. The project is Customer project.
    Thanks & Regards
    Satish

  • Settlement in Customer Projects

    Dear all,
    In our scenario, we have customer projects which are settled to Profitability segment. The client doesn't want to settle the projects periodically. The client wants to settle the project only onces when the project is over. In this case the project will hold cost till the last day.
    Client intents to use RA only for information purpose and not for posting the RA value on the project. Hence clients decision seems genuine.
    What are the impact of this decision? How often do we really have to settle the project in this situation?
    What is the impact of not settling the project at all?
    Request your opinion on this issue.
    Warm regards,
    Srinivas Potluri

    Hi Srini,
    The business process as required by you is possible & i don't think there will be any impact. Project settlement can be made on completion of project iteself, n't periodically as your identifying cost / revenue externally.
    RA can be used to identify calculated revenue / cost & n't to consider real posting into FI.
    Few queries, i would like to ask on your  business scenarios. If the project settlemnt is after completion of project only, how project profitability is obtained from period to period. How is balance sheet reporting for the ongoing projects.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Customer project settlement to sales order item

    Hi experts
    I wish to settlement the customer project to sales order item. Accordingly the settlement profile is defined.
    However, w.r.t. settlement strategy, what is the relevant account assignement category?
    It cantains the eligible values:
    AAC                  Description
    -           No receiver
    1           Profitability segment
    2           Requesting cost center
    3           Responsible cost center
    4           Copy rule from superior object
    Please suggest the correct setting.
    warm regards
    ramSiva

    use BADI - WBS_SETTLEMENT_RULE
    this BADI allows you to generate settlement rule as you want

  • PS Implementation without COPA

    Hi Gurus,
    Can anybody clarify following queries.....
    1. Can we implement PS Module without COPA Module.
    2. If so, what will be the settlement object in settlement rule. (WBS Settlement)
    Note: We are implementing PS module for Customer Projects and COPA is not in our implementation scope.
    Regards,
    Ganesh Ck

    It is ideal to have PS module along with COPA. However we can implement just the PS module. The only small issue that we would have is settlement of revenues. We need to settle revenue only to revenue GL accounts You have is create appropraite allocation structure:
    1. Create allocation structure
    2. Create 2 assignments "Rev" and "COST"
    3. For source assign all cost related accounts to "COST" and revenue related accounts to "REV"
    4. For settlement, the receiver category can be cost center/wbs element for "COST". The receiver category has to be GL accounts for "REV"

  • Without COPA customer project settlement

    Without COPA customer project settlement - where it should get settled ?
    MGK

    Should it?  Well, first you need to know why do you want to settle.  If you have RA to be posted for example.

  • Customer project Settlement

    Dear All,
    i am working in customer projects. Actual cost and revenues r flowing.The RA key to the top WBS Element which is also billing element. I heve done the revenue based result anlaysis.Profit and loss are showing in RA. Now i want to settle the project to CO-PA.
    Given settlement rule to top WBS Element and all other lower WBS element have profile not ot settle.if i run settlement CJ88 then nothing is flowing and not any error.
    Need solution.

    Dear,
    i m settleing the lower level WBS Element to top WBS Element which is billing element and result analysis is done for that top wbse .Then i want to settle the top wbse to profibility segement .Then after trying some config steps and defining PA transfer strature settlement of lower level wbse to upper level wbse is going well and accounting document is creating well.And CJI3 report its flowing well.
    but in top WBSE the rule is profibility segment.I've done the result analysis and the net value (revenue-actual cost)
    is also showing.That value is on the lower level wbse and that only value is going to TOP wbse after settlement.
    but now i want to settle this top wbse but its showing no accured cost or revenue.
    Is the process i m using is correct or i've to do it by some other method.The RA valuation method is revenue based.
    sukhveer

  • After Settlement, Cost not transfer from one WBS to another WBS in customer project

    Hello Experts,
    I am trying to settle cost from one WBS (i.e. XYZ-000014-1) to another WBS (i.e. XYZ-00001)in customer project.
    Its a revenue type of project.
    I have added 4 internal activities in an network under one WBS (i.e. XYZ-000014-1).
    Got actual values after confirming activities, then settle that network cost on WBS (i.e. XYZ-000014-1)  through CJ88.
    Now while trying to settle that cost from WBS (i.e. XYZ-000014-1) to WBS (i.e. XYZ-00001) through CJ88, system not showing any result.
    Kindly give ur valuable inputs.
    Regards,

    Kindly tell me that is it a standard functionality of SAP that through CJ88 we can transfer cost from WBS to WBS.
    Technically ,Yes.Cost is actually transferred from one cost object to another cost object.
    I hv discuss the same with some of my frds ...some are denying the same that its not a standard functionality of SAP to transfer cost on same cost object.
    Instead of 'transfer' I would rather use the word 'settlement' . Practically, they are right as projects-WBS are temporary endeavors of companies, and cost can not reside on WBS permanently as it has to settle to some entity (organizational unit) which can be accounted during the reconciliation of their chart of accounts and balance sheets.
    SAP has provided us an option to settle our cost to WBS and hence its standard . Generally, we use it when we have 1 WBS at level 1 and all lower WBS's costs is settled to this WBS . Here, we specify Level 1 WBS as the receiver of cost of these lower WBS.
    Hope,I am clear here.
    Regards
    Saurabh

  • About Generating Settlement Rule in Customer Project

    Hi Experts,
    I am doing the exercise of customer project T-100## in CA830.
    While generating the settlement rule, the error log appeared: No profitability segment could be determined for the billing elements. So the settlement rule generation failured.
    May somebody guide me how to solve this problem.
    Thanks in advance!

    Hi Balakrishman,
    In my case, the fields of Business Area/Profit center have already been maintained. I think there must be other reasons that result in these error. Hope we can discuss further. Thank you for your help!
    Regards,
    Allen

  • Settlement  for Internal and Customer Project

    Hi Guys,
    I am new to SAP PS.
    I have a R&D project(Internal Project) and a Customer project. I know internal project is treated as  Asset and settled as AUC, but can we settle it in any other way apart from cost center and GL account.
    Then what about Customer project. I want to know how can we settle these both project and what are the setting and what are settlement rules used for settling Internal and Customer project?
    Please need your help.
    Thanks and Regards,
    Roshan Malaruthu

    For Internal/Investment project, you can settle all actual line items of CJIC/CJI3 to AUC then final settle capitalized items of AUC to FXA i.e. on fixed Asset using final settlement rule.
    Note: You can also use GL Account or Cost Center here for settlement receiver.
    Before doing this, you need to configure investment & settlement Profile. And assigned them to your Project Profile.
    For Customer Project, As Santosh said is correct, you have to use Profitability Segment as settlement receiver. Just select PSG as default Obj type in settlement profile.
    Also refer the link below for more details:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/ab7770414111d182b10000e829fbfe/content.htm?frameset=/en/6b/566b34b650f777e10000009b38f83b/frameset.htm
    Regards
    Shishir

  • Settlement of a project to internal order?

    Hi Experts
    In a customer project  we have RA and settlement as a period end process but as COPA is not configured, So can we settle it to internal order? or is it advisable to settle to internal order?
    thanks..
    Edited by: SAP PS on May 25, 2011 7:48 PM

    Hi,
    It is better to settle to a G/l account. for this we need to set in the alocation structure receiver as G/L and settlement cost element with cost element category 21 or 22 (internal or external settlemet) based on the receiver. with this what happens at any given point of time we can see the detailed reports cost element based as well at G/L level also.
    Thank you
    Best Regards
    kishore

  • Settlement fo Wbs element to Copa

    Hi All,
    Iam new to project systems concept. In month end when we settle wbs element to copa.data will flow into F!, profit center and copa, during the settlement to copa
    I want to know what journal entries it will reflect in FI,Profit center and Copa.
    Regards,
    Chandu

    Dear,
             For customer project you should run the result anlaysis and this result anlaysis data you can settle to the COPA.
                                 Then the settled data send to the value field which is given to the PA transfer strature in Settlement profile.
                                              The profit center is debited and credited .
                                               One controlling document is also generated which have cost reduced from WBS element to profibility segement.
    Regards.

  • Error in JSP's for custom project created for SAP-SHRAPP crm/isa/web/b2b

    Hi All,
    we have NWDS 7.3, NWDI 7.3, JDK 1.6.
    Imported the track, created a new custom b2b project. Added the corresponding dependencied on the project folders.
    On build of the custom project, build was finished with some warnings. The depolyment was completed successfully.
    We are able to open the XCM settings of the custom project. And even the application for the custom project is running fine, ordes are being saved, without any error.
    However, when i open any JSP say order.jsp. It has some set of warnings and errors. The error description says ISACORE jar file is not accessible.
    Kindly help, how to solve this issue?
    Thanks
    Ekta
    PS. example of one of the error
    Access restriction: The type OrderChangeUI is not accessible due to restriction on required library D:\NWDS
    \eclipse\workspace.jdi\0\DCs\sap.com\crm\isa\isacore\_comp\gen\default\public\default\lib\java
    \sap.com~crm~isa~isacore~default.jar
    when i go to this location the JAR file is available.

    all the SC are of version 7.01
    Thanks!
         ED7
    o SAP_JTECHS.sca     sap.com      SAP_JTECHS      7.02 SP8 (1000.7.02.8.1.20110704191740)
    o SAP_BUILDT.sca     This is DTR component it will be in NWDI(DI BUILD TOOL)
    o SAP-JEE.sca     sap.com      SAP-JEE      7.02 SP8 (1000.7.02.8.1.20110705065623)
    o SAP-SHRJAV.sca
         SAP SHARED JAVA COMP. 7.01//
    SAP-SHRJAV      701 SP4 (1000.701.0.4.6.20110722065102)
    o SAP-SHRWEB.sca
         SAP SHARED WEB COMPONENTS//
    SAP-SHRWEB      701 SP4 (1000.701.0.4.6.20110722073940)
    o SAP-SHRAPP.sca
         sap.com      SAP-SHRAPP      701 SP4 (1000.701.0.4.6.20110722064714)
    o SAP-CRMJAV.sca
         CRM JAVA COMPONENTS 7.01//
    SAP-CRMWEB      701 SP4 (1000.701.0.4.6.20110722064233)
    o SAP-CRMWEB.sca
         CRM JAVA WEB COMPONENTS 7.01///
    SAP-CRMWEB      701 SP4 (1000.701.0.4.6.20110722064233)
    o SAP-CRMAPP.sca
                        sap.com      SAP-CRMAPP      701 SP4 (1000.701.0.4.6.20110722063254)
    o SAP-CRMDIC.sca
         sap.com      SAP-CRMDIC      701 SP4 (1000.701.0.4.6.20110722063636)
    o SAP-IPCMSA.sca
         CRM IPC MOBILE 7.01///
    SAP-IPCMSA      701 SP4 (1000.701.0.4.6.20110722064529)
    o STRUTS.sca
         This was for only CRM 5 I think you should ignore this SC    Note 917001 - XCM configuration failes on OS/400
    o TEALEAF.sca     This was for only CRM 5 I think you should ignore this SC   Note 900660 - TeaLeaf RealiTea Version 4.5 for CRM 5.0

  • PS module ---Functional steps in Investment and Customer Projects in PS

    Hi Experts,
    I  am new in PS module,Pls tell the steps in----->
    1>Investment Project---The steps and transactions in PS according to Flow of  PS module in Investment project from start till end of PS.
    2>Customer Project--The steps and transactions in PS according to Flow of  PS module in Customer Project from start till end of PS.
    I    want to know functionally how the above Projects operate differently functionally with transactions and Flow.
    Regards,
    Rahul

    Hi Rahul,
    In addition to link provided above , please have a look on functional steps for Typical Investment & Customer project scenarios as follows.
    Investment Project
    1. Create a suitable WBS using Project builder.
    2. Plan basic dates manually for WBS elements using Project planning board
    3. Plan costs manually for WBs elements using Easy cost planning
    4. Budget WBS elements
    5. Enter actual dates during the project execution phase.
    6. Assign various documents for WBS elements using Execution Services for updating commitment &
       actual costs.
    7. Calculate overhead costs & carry out settlement to assets under construction or completed asset in
       Asset accounting.
    Customer Project
    1.  Create a customer inquiry in SD.
    2.  Create a project (WBS & Network) using standard structures
    3.  Plan dates using Scheduling
    4.  Plan Resources
    5.  Plan materials by transferring Bills of Material
    6.  Plan costs using Network costing
    7.  Create sales pricing data ( Create quotation bases on project cost plan,Plan revenues for project)
    8.  Create a sales order with a bliing plan in SD
    9.  Create confirmations ( using CATS)
    10. Purchase matetrials & services.
    11. Document variance usign claims
    12. Post Revenues using Milestone billing
    13. Calculate overhead costs,carry out a results analysis & settle results analysis values to profitability
          segment.
    Regards
    Tushar

Maybe you are looking for

  • Anyone using Blackmagic card for preview monitor?

    I have a Blackmagic Intensity Pro card for monitor out to a lcd tv connected via HDMI. The picture on my tv has black bars on the left and right side of the screen (like 4:3 should be 16:9). It is not showing my 1080i60 canvas as it is in Motion. Wha

  • NEED WHY WE USE REFRESH,FREE

    I NEED CLEAR EXPLANATION WHY I NEED TO USE REFRESH,FREE IN INTERNAL-TABLES.

  • What is the Universal Crossword Print Widget?

    The Universal Crossword Print Widget has been discontinued, and there will be no new content. However, you can still receive the Universal Crossword printable by subscribing on your HP web-enabled printer's front panel, or by visiting HPConnected.com

  • Gettting kicked out of itunes

    Hi, A coworker of mine put songs from my Cd's on my IPOD before, and he is trying to do more but he is using a different computer a new one and he can only do 2 cd's so far, he said he has Vista installed on the computer, what is the problem? and can

  • ODAC Release 4 & 5 - Oracle.DataAccess.dll 4.112.3.0

    Has anyone else noticed that ODAC Release 4 & 5 have the same AssemblyVersion 4.112.3.0? Oracle Data Access Components (ODAC) for Windows It took me a while to spot the problem.  I'm using Entity Framework 5 and hit a machine with Release 4.  It thre