Settlement of WBS - KI235 - Account Requires an Assignment to a CO Object

Hello,
Im having an issue when running settlement on a WBS Element.  The settlement rule on the WBS element indicates that settlement is to be charged to GL Account 629080.  I checked the WBS Element, and there is a cost centre entered on the settlement rule as well.
My issue is when I run settlement, I receive the following message:
Message no. KI235 - Account 629080 requires an assignment to a CO object
I have no idea why settlement is not picking up the cost centre on the WBS Element itself. 
Does anyone have any ideas as to what I can do to settle this WBS Element?  We do not want to update the OKB9
table and enter a default, as each WBS is for a unique Cost Centre.
Thanks!
Edited by: Robert Collia on Jan 13, 2011 10:55 PM

Hi
We had the same issue followign a recent upgrade and I couldn't work out why the settlement couldn't read the cost centre from the settlement rule.
It turned out that we had overwritten an oss note.
Take a look at sap note 1296568 - point 5, this should tie in with what you want your settlement to do.
This then refers to note 483340, this is the note we had lost.
Hope that helps

Similar Messages

  • Error KI235 - Account requires an assignment to a CO object

    Hi gurus,
    I just wanted to ask re: thjs issue of ours wherein we can't release a billing document to accounting (VFX3) and system issues error message - KI235 (account assignment missing). In OKB9, the profit center assignments have already been set. The problem seems to originate from 1 item in the document wherein the profit center is not populated, thus no CO object can be obtained. I checked the material for that line item to verify why the profit center is not being populated automatically. I found out that the material is non-valuated goods.
    The question now is, what do I need to do to push through with the transaction? I checked in VF02, and unfortunately, we cannot manually input the Profit Center from there. Any suggestion or help is very much appreciated.
    Thanks

    Hi
    To rectify the billing document, please proceed as follows:
    Option 1:
    1. Cancel the billing document
    2. Modify the sales order to include profit center
    3. Then, create the billing document which will have profit center assignment.
    Option 2:
    1. Maintian the relevant cost center for that cost element (temporarily) in KA02
    2. Then release the billing document using VFX3.
    3. Remove the temporary assignment of cost center to CE.
    Regards

  • Error message KI235 "Account & requires an assignment to a CO object

    Hi,
    I am in the SAP Release SAP ECC 6.0 and I can not make a GOOD RECEIPT for a PURCHASE ORDER (transacction:MIGO); the system displays the error Message KI235.
    In another hand, I have checked the cost Account and I is possible to make an invoice using this account, so I don't know what could be the problem.
    Thanks in advance,

    Hi Juan,
    Which kind of purchase order is it? Is it a subcontracting purchase order? If not, are you buying a standard price controlled material and the purchase order price is different than the standard price? Are you posting the goods receipt into the previous period?
    Please, let me know.
    Esther.

  • Account requires an assignment to a CO object - Message no. KI235

    Hi
    While posting goods receipt, i am getting the following error: Account requires an assignment to a CO object (Message no. KI235). Can anyone pls tell if this is a MM, FI/CO, SPRO settings issue?? How to go about resolving the error.
    Thanks.

    Hi,
    Check the links;
    Account 400011 requires an assignment to a CO object
    Account requires an assignment to a CO object
    For more check the NOTE:367813 -> KI235 for goods movements:
    Regards,
    Biju K

  • Account requires an assignment to a CO object - KI235

    Dear Sap Experts,
    We just activated new GL functionality, when testing few scenarios from sales we got an error as "Account requires an assignment to a CO Object". We created sales order with profit center and while doing PGI we are getting such error , we have created COGS GL as revenue element. Can anyone guide us how we can fix this issue..?
    Thanks,
    Lokesh

    Hi Lokesh
    Is this COGS account assigned in OBYC- GBB/VAX??
    This should not be made as a cost element as per SAP recommendation
    Br. Ajay M

  • FIINT transaction : Account  requires an assignment to a CO object.

    This is related to FINT transaction in FI . After executing and clicking on "process forms for all interest items"  getting message
    Account  requires an assignment to a CO object.
    Also the Gl code account displaying is incorrect .
    Please suggest.

    Hi,
    Use transaction code: KA02: enter G/L account(Cost element) and in default acct assinmt TAB,assign the Cost Center and save.
    Now try ur transaction.
    OR
    Check the field status of the account  in FS00. If this account requires CO object as mandatory then check whether a cost element is created or not , this error normally occurs when CO object is mandatory but relevant cost element is not created.
    Example: CO object may be cost center, cost element, WBS element
    OR
    Use t.code OKB9 and assign G/L account to cost object with ur company code and save.
    For more check the link
    http://www.sap-img.com/financial/requires-an-assignment-to-a-co-object.htm
    Regards,
    Biju K

  • Confirmation: Account ***** requires an assignment to a CO object

    Dear all experts,
    I am trying to do confirmation for my production order in CO11N. However, i have received this error meesage when i am trying to save / post.
    "*Account ***** requires an assignment to a CO object*"
    Message no. KI248
    = secondary cost element
    Base on my understanding,  Secondary cost element will not assign to CP Object.
    Is there any solution ?
    Thank you.

    Hi refer below thread:
    Please review the SAP note
    367813 - KI235 for goods movements: What should be done?
    Account requires an assignment to a CO object - Message no. KI235
    Regards
    Santosh Sarda
    Edited by: santosh sarda on Jun 10, 2011 6:35 PM

  • KI 235 Account requires an assignment to a Co object during GR/IR clearing

    Hi All,
    I have an above issue during GR/IR clearing.  The scenario is below
    We have maintained three currencies
    AED-Company code currency
    USD-1st parallel currency
    INR-2nd parallel currency
    At the time of GR/IR clearing, it is giving the above error for the Exchange Gain / Loss GL account maintained.  There is no difference in the company code currency, but the difference of 0.01 is appearing in the USD amount which is posted to Exc Gain/Loss account.  But at the time of doing the automatic clearing account vide transactin code f.13 it is giving the above error.  We have already done the setting in OKB9 and have assigned the cost centre to the respective GL account as per different profit centre.
    Kindly inform if anybody has come accros this issue and how it was resolved.
    Thanks
    Mahesh

    Hi Raheem,
    I am running transaction code f.13 GR/IR clearing account.  We have maintianed 3 three currencies. 1st AED-co code currency, 2nd usd- parallel currency, 3rd INR- parallel currency.  At the time of clearing system is giving above error of account requires an assignment to a co object for GL account of Exchange Gain/Loss account.  The exchange rate difference is coming for the 2nd currency ie USD.  In the leading ledger there is no problem.  We have done the setting in OKB9 and assigned the co object for Gl account of Exchange gain and loss.  Hope you have understood the issue.  Is there any solution apart from the setting in OKB9.
    Mahesh

  • MB1B Mvt Type 413 E - GL Account requires an assignment to a CO Object

    Hi,
    We are trying to transfer stock from one sales order to other, system is giving the error " GL Account requires an assignment to a CO Object".  Movement type 413 E through MB1B. We are using MTO scenario.
    The question is that we are giving both the sales order number (from and and to) whic are itself CO Object then why is the sytem asking for another assignment?
    Kindly advise.
    Thanks & regards.

    Dear,
    As suggested, contact FI consultant for suitable assignment.
    Secondly, Check  : http://www.sap-knowledge.com/archives/2388
    Regards,
    Syed Hussain.

  • First Dep Run - Account requires an assignment to a CO object

    Hi,
    We did a legacy data transfer for this november, for a whole company code Fixed assets. We run the initial load in our testing environment and now we are trying to run the first month depreciation (Nov09)
    When we run Nov an error message is displayed (Y00_FI024 Account requires an assignment to a CO object). It seems to be very clear, no Co object assignmet there but it is not that simple.
    Every assets has an unique Cost Center,actually I tried a manual posting to this cost center an it is possible. Later I reviewed the ACSET config  and it is set as follow.
    KOSTL     Cost Center     *     Generic Trans. Type     APC Values Posting
    KOSTL     Cost Center     *     Generic Trans. Type     Depreciation Run
    Actually I can review the Journal entry that is trying to post and all the information is there: Doc type, posting key, Gl accounts (with the correct account determination), cost center.
    I don't really know what else to check.
    Could you help me with any imputs? maybe something missing in the configuration?
    Regards,
    Adela.

    Done,
    It was a validation that is set for this company.

  • G/L account requires an assignment to a CO object

    Hi All,
    In transaction VL02N when i am entering outbound delivery number and trying to post goods issue it is giving me error as specific G/L account requires an assignment to a CO object.
    Outbound delivery number i got from sales order through transaction VA02.
    Can any one tell me why this error is coming and how to sort it out?.
    Thnaks.

    Hi Raymond,
    I understood what you said. Let me explain my requirement in brief .
    We create order through VA01 transaction, we used to put cost center at the time of data entry for particular material so that for the G/L which is showing this type of error has not assigned any fixed cost center.
    When i'll put cost center through FS00 to that G/L then i think it will also affect other entries. And finance people don't want to assign any fixed cost center to that G/L as at the time of data entry they used to put it manually.
    And basically this problem is coming for few materials in the same order, when i am trying to post outbound delivery of those materials .
    any solution for this ?
    Thanks.

  • ABT1N   Account **  requires an assignment to a CO object

    Hi Dear,i am using tcode ABT1N to transfer asset within inter-com entity,but i got error "Account ******** requires an assignment to a CO object"
    my understand is cost center already entered in asset,then that GL will auto-derive cost center from asset master as CO object assignment,why still have that message?

    Hi,
    Please have a look on the following tips to solve this issue:
    1. Check the settings in the following customizing                                                                               
    SPRO -> Asset Accounting -> Integration with the General Ledger -> Additional Account Assignment Objects                                                                               
    In there you must find Cost Center / Internal Orders as ACTIVE                                                                               
    2. All asset masters must have defined a cost center / internal order    
    in table ANLZ.  You can check this information by trx. SE16.                                                                               
    3. In "field status group" of account assignment, cost center and  internal order must be optional.                                                                               
    To check this information, you can go to trx. AS02, double click on account determination, then select tab "Create/bank/interest".                                                                               
    4. Check if you have set additional cost center determination by trx. OKB9 that can be affecting the "cost center" derivation.                                                                               
    5. If company code has been defined as "Business area fin.statement";,  then Cost Center won't be derivated from Asset Master. Check txn OBY6.                                                                               
    6. Please verify the settings of:                                                                               
    SPRO -> Asset Accounting -> Integration with the General Ledger -> Additional Account Assignment Objects
    -> Specify Acct Assignment Types for Acct Assignment Objects                
    There for your company code, for all transactions (*) cost center must  be active, so it will be derivated from Asset Master.                                                                               
    I'd also like you to have a look on the following SAP notes:             
    684659: FAQ concerning account assignment objects as of release 4.70 ;    
    106968: FAQ: Account Assignment Logic                                             
    049127: Cost center account assignmnts in Asset Accounting                                                                               
    In case of using Public Sector:                                          
    489816: Incorrect update of account assignment objects                   
    516909: FI-AA: Changes in IS-PS Release 4.62 ;                            
    regards Bernhard

  • Account  requires an assignment to a CO object-very urgent

    Hi experts,
    I have 2 questions
    1.while  doing transaction MI07 -post inv.differences its giving an errorr <b>Account requires an assignment to a Co object.</b>
    2.while doing transactions called MIGO  for a particular PLANT its not trigerring an GL account and giving an errorr as <b>Account requires an assignment to a CO object</b>
    pls try to slove this issue.
    points are considered.
    Thank you and Regards
    sasikanth.

    Hi
    While doing MI07 it requires a posting to a P&L account for the difference as it is going to be charged off, and if this GL account is a Cost element it will ask for a Assignment to CO object. You can default it in OKB9 for the Gl account based on the profit center and G.L account combination since Profit center will be obtained from the material master assignment it can be done this way.
    In transaction MIGO which is for Goods receipt it posts to Fi automatically through the configuration in OBYC. If standard cost is maintained then there may be a posting to price difference account hence it will also be a cost element due t which it required an CO object. For this also you have to maintain a Co object in transaction OKB9
    This will solve your problem.
    Anand

  • Account requires an assignment to a CO object as settle a refurbishment ord

    We have an outstanding refurbishment order which can't be settled. The system gave a message like "Account XXX requires an assignment to a CO object". In settlement rule, the refurbished material was set as a receiver. Others refurbishment order were normal and can be settled. We have checked the configuration of settlement profile and cost allocation structure. No problem was found. Where can I start to solve it? Any comments will be appriciated!

    Hi
    Same problem we have automated by work flow
    Is there any ocst on order ?
    what we have a found a way that this order is to be confimred & materiral issued to be posted only after work order gets teco
    We have valutaion type material c3 as price =001 which is lowest
    so in between if the order is settled there is now cost
    & if the work is finished then it will automatically settled by work flow
    Regards
    Pratap bhikaji

  • Re: Account requires and assignment to a CO object.

    Hi Friends,
    I have a problem in Controlling can u please solve for me.
    Question: Account 21460001 requires an assignment to a CO object.
    Can you give me answer in detail.
    Awaiting for your urgent replies & Have a nice day.
    Points will be assign
    Thanks in advance,
    KUMAR.B

    Hi
    In case of Controlling module following are the objects with reference to which the information flow to CO.
    1. Cost Centre
    2. Sales order
    3. Production order
    4. WBS
    5. Network etc.
    In your case please check the particular account in OKB9 Transaction where the automatic assignment set.
    If you set the cost centre in cost element it will always post to the same cost centre or you have to change the cost centre regularly as and when the same account partains to different cost centre.
    If the above answer is helpful kindly assign points
    Thanks & Regards
    Mahesh

Maybe you are looking for

  • Error while starting the Database

    Hi, I am getting the following error while starting the Database instance. ORA-03113: end-of-file on communication channel. How to fix this issue? i tried some of the options mentioned in docs in metalink. But still i am not able to fix. Anypointers

  • How to print multiple fields in single barcodes

    Hello friends, How to create a single barcodes with multiple fields in smartforms and retrieve same multiple fields while scanning also. My requirement is, i want to create barcodes which contains material no, serial no, material description and quan

  • Question on Data Driven Graphics (non-English)

    I am trying Data Driven Graphics with Illustrator CS4 on Win. The program works fine with English XML data, however when I try other non-English language, Illustrator cannot show characters like é,è,ë. The data is in XML UTF-8 encoding. Anyone could

  • Alternative for session variable in OBIEE Translation

    Hi all, I am working on translating OBIEE reports to various languages. I am using specific xmls for particular language which has entries for translated text. Now in few of the reports I have case statements/BINs defined in column formula. This 'col

  • Static vs Singleton for cache

    Hi! I'm developing a web application, where I want to cache some Java objects in a HashMap. The Objects will then be fetched using something like this: Cache.getPost(String key); But I'm not sure if I can use a static method and a static HashMap for