Setup Matrix

We are using repetative manufacturing, I want to know if I can group all materials by set-up time - hence reduce change overtimes from one group of products to the other.
Can I use Setup group category & setup group Key with planned orders.
Thanks in advance.

1.Set up grop key and categroy will not help in the REM manufacturing table.
2.This setup group and matrix will help in the capacity planning only.Where dispatching can be done by grouping at the setpu group key etc.
3.Even that would complicate the things becuase again we need to check what things system has pushed.
4. But int he capcity planning table -graphical it can belp you to highlight the order by the setup grou key .
5.So if you are looking for a funcitoanlity of grouping the materials in the setup group then that is not possible.
let us know if you have anydoubts..
reg
Dsk

Similar Messages

  • Using the PPDS setup matrix

    Hello All -
    I have 3 products A,B and C which  are run on a single line during a particular week(day). We have certain set-up times when we move from one product to another. Here are the set-up times:
    The sequence in which these products run on the line is decided by the plant scheduler during production planning. The production planners run heuristics and peform manual changes to the planned orders. They know which product runs in which shift but they do not necessarily adjust the planned orders to the hourly level.
    What we would like the system to do is somehow incorporate the set-up times when we move from one product to another.  We would like to see the the resource being consumed during the set-up time.
    Also, we are not in a position to use the optimizer. So any solutions involving the Optimizer are out of scope. Just want to achieve this using heuristics.
    To achieve this, I have created the following master data:
    1) Created 3 setup groups SG1(A), SG2(B), SG3(C).
    2) Created a setup matrix SM1 and set up the transitions for   all the above combinations.
    3) Assign the setup group to operations in a ppm
    4) Assign the setup matrix to the resource
    I then created 3 planned orders in production planning for the SAME day. All 3 have the same availability time 23:59:59 and based on run-rates we have different start times.
    I have the following questions:
    1) Which DS heuristic should I use to adjust the start times and the end times of these orders by considering the set-up times in the setup matrix?
    The resource should basically be consumed during these setup times. I have looked at "Reschedule" function in the DS planning board but I get an error when I run this. Please see end of this post for the error. The message says I may not have free capacity, but I do. I am using backward scheduling and infinite.
    2) Is there anyway the set-up times/matrix can be considered during production planning itself and not during detailed scheduling?
    3) Can the option of "Schedule Sequence" work for my scenario.
    Appreciate all your help.
    Varun
    Error during scheduling
    Message no. /SAPAPO/OM043
    Diagnosis
    The system could not schedule an order, operation or activity.
    This could have the following causes:
    The resource does not have any free working time or capacity.
    If you have set planning direction backwards in the strategy profile:
    There is not enough working time or capacity available for scheduling between now and the scheduling date.
    If you have set planning direction forwards in the strategy profile:
    There is not enough working time or capacity available for scheduling between the scheduling date and the end of the planning area.
    If you plan characteristics-dependently:
    You have assigned characteristics to operations of the order that do not agree with characteristics of the resources on which the operations are to be processed.
    The system cannot find any suitable characteristics on the resources and so it cannot schedule.
    Procedure
    Depending on which of the above reasons is the cause, change the following settings:
    Change the working times and capacities of the resources.
    Set the planning mode "infinite planning" in the strategy profile.
    Activate the planning direction forwards or backwards and reverse in the strategy profile.
    Change the characteristics that you have assigned to the resource.

    Thank you all -
    It was a mistake on my part. I was supposed to create a new "set up" activity before processing activity and make that relevant to set-up. I had the processing step checked for setp all this while. Now its working.
    Thanks
    Varun

  • PPDS: I have a setup matrix in SAP ECC 6.0, and want to transfer the same to APO using Core Interface.

    PPDS: I have a setup matrix in SAP ECC 6.0, and want to transfer the same to APO using Core Interface. Has anyone done it before?

    Hi Subhash,
    Please open this link to see the details:
    http://help.sap.com/saphelp_scm70/helpdata/EN/89/bd3e42ce98033be10000000a1550b0/frameset.htm
    You perform the data transfer in the following sequence:
    Plant
    Setup groups
    Work centers
    Routings
    You check the setup groups in SAP APO.
    You create the setup matrixes in SAP SCM.
    Thanks, Marius

  • Document for PPDS Optimizer Setup Matrix

    Dear All,
           Can I have a document or an implementation guide for PPDS Optimizer Setup Matrix?
    I have already checked the SAP help and Certification Material about this topic. But there is no more information on this topic. It will be great if you provide a document where I can learn from the scratch.
    Thanks a lot.
    Regards,
    Ram.

    Hi Ram,
    See wiki page:
    General PPDS wiki page
    http://wiki.sdn.sap.com/wiki/display/SCM/APO-PPDS
    Setup Matrix Generation in a Complex Manufacturing Evironment
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/00a618c4-8aad-2b10-6ebb-f70cb4470195
    Oficial doc
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/00a618c4-8aad-2b10-6ebb-f70cb4470195?quicklink=index&overridelayout=true
    Hope this help.
    Luiz Giani

  • Scheduling using  Setup Matrix in PPDS

    Hi Gurus,
    We are using PPDS Steup Matrix for scheduling orders. We have scenario that from product A to B, there is a changeover. And after producing A or B for certain hours, there is a cleanout of certain hours.
    Ex- Orders A for 5 hrs, B for 5 Hrs. Setup Matrix: A-B=1 hr and Max order ( A or B)=7 hrs after which cleanout should happen.
    While scheduling , A(5hrs) (Setup) B( 5 hrs), this is acheived.
    But result should be A(5hrs)(Setup)B(2hrs)(Cleanout)(B 3hrs)
    Please give your valuable inputs. How to map extra Cleanout ??/ Should we ceate another setup matrix for cleanout?? Can system take multiple setup matrix???
    thanks,
    Priya

    Hi Priya,
    I think Your case can be achieved through campaigm planning.
    Create a setup group 'PROD' in ECC.
    Under setup group 'PROD' maintain setup keys as 'A' & 'B'
    Assign these setup group and setup keys in master recipe.
    Maintain the same setup group & keys in APO also and than CIF PPM.
    Maintain the setup matrix and assign it to resources
    Create a campaign profile for 'PROD' with no of chargers(Orders) as 7.
    Now schedule orders by using optimization.
    After that create campaigns by using campaign heuristics on the resources.Campaigns will be created for every 7 hours.
    And then create cleanout order by using cleanout heuristics between campaigns.
    By this you will achiece setup between products and change over after your max run length also achieved by cleanout order between campaigns.
    Hope this is clear.
    Regards
    Sravan

  • Setup Matrix and PDS

    Hello All,
    Can a setup matrix be used in combination with a PDS? I created a setup matrix and then went onto to create setup transitions and found that it is only configured to accept and PPM Plan and not PDS. Is this how it is or am I missing something completely?
    Thx

    Hi Vishy,
    There is no rule which prevents usage of PDS for set up matrix.
    You can very well use PDS data with set up matrix.
    I hope there will be some configuration missing in your set up
    to generate the required scenario.
    Regards
    R. Senthil Mareeswaran.

  • Same setup matrix for both fert and halb products

    Hi,
    at present we are using a setup matrix in apo for fert products, which is built on the setuptimes/groups of the halb products.
    can i use the same setup matrix for the halb resources, if we want to use the sequence dependent setup planning for the halb products..our fert is the combination of halb and packing..
    Thanks,

    replace the existing rules with one that does not specify the port [L3 rule].
    However, you can't use arrowpoint cookie anymore.
    And you can't use 'advanced-balance ssl'.
    Another solution would be to use an SSL offloader to decrypt the traffic and have the cookie inserted in the https traffic as well.
    Regards,
    Gilles.

  • Where to assign setup matrix ?

    Hello to all SAP Expert,
        I have one problem regarding setup matrix assignment. I have created setup matrix, but where to assign this so that I can reduce my setup time required.
    Thanks in Advance.
    Regards,
    Yogesh

    Dear,
    Set up group and transition matrix :- Setup group key is defined in the operation in the routing and then the transition times between setup keys is maintained in configuration. in work center CR02  default value tap you will get field for Setup Type Key.
    Regards,
    R.brahmankar

  • Extending the setup matrix use

    Hi
    we would like to extend the setup matrix use for the halb products now, currently we use the setup matrix for the fert products and it works fine. our fert = halb+packing, when extending the setup matrix use to the halb products what changes need to be done.
    do we have to create a new setup matrix for the halbs or..can you pls share your ideas..

    Hi, its advisable to create a new setup matrix for the halb product.
    Ensure all the w.c on which setup sequencing is to be done are single mixed resource.
    Assign the newly created setup matrix to single mixed resource
    In the routing assign the setup group
    Re transfer your PDS
    create a test planned order in APO rrp3 and test if the setup group is arriving or not
    You ca use the existing sequencing heuristics
    Regards
    Amlan

  • Sequencing using setup matrix

    Hi all,
    We are able to sequence based on setup groups using heuristics in PPDS (either ascending or descending manner) but setup time is not getting picked up during changeovers from one setup group to other, as per setup matrix.
    Any suggestion

    Hi,
    kindly post your querry in the ERP- SCM to get quicker response.
    reg
    dsk

  • Setup group and setup matrix

    Hi Gurus,
    Please brief me on the significance of setup group and setup matrix in APO and the effect of the same in planning?
    Thanks,
    Prasanth

    Hi Prashanth,
    Setup group tries to group products with similar characteristics.
    Setup matrix provides the sequence in which the set up groups
    can be executed.
    Setup sceanrio is used in cases where in the time taken for switching
    over from one product or group of products or category of products or
    charactersitics of products which is called as predecessor to another
    product or group of products or category of products or characteritiss of
    products which is called as successor.
    Say for eg, if you are having a scenario wherein
    you need to manufacture products with low weight,
    medium weight and heavy weight products.
    You can define in the set up matrix that for switch
    over from low weight to medium weight products for
    manufacturing, the set up time involved in 2 hours and
    the setup cost involved is Rs.100,
    Similarly, for switching over from heavy weight products
    to medium weight products, the set up time involved
    is 3 hours and the set up cost involved is Rs.50.
    Based on this information, system will frame a matrix
    of information and use during planning.
    Hope this information is clear to you.
    Please confirm whether your issue is resolved.
    Regards
    R. Senthil Mareeswaran.

  • Setup Matrix volume Doubts

    Hi experts,
    I have a couple of questions concerning the setup matrix volume.
    1-a)What setup matrix combination volume is considered  as acceptable?
       b)Which is the break point from where performance issues take place?
    3-What happens if the optimizer is optimizing orders and within those orders , there are features which are not included in the matrix.If this eventuality occurs, how the optimizer reacts?
    Regards,
    Analí

    Thanks a lot for your advise Frank!!
    Question Still pending review:
    3-What happens if the optimizer is optimizing orders and within those orders , there are features which are not included in the matrix.If this eventuality occurs, how the optimizer reacts?
    regards,
    Analí

  • Setup/clean-out orders for production campaign

    Hi experts,
    Can you tell me the steps that I have to execute if I want to create in APO PPDS a setup/clean-out order for a production campaign
    Regards,
    Arnulfo Cordero Pradel

    HI Victor,
    In the setup matrix you are suppose to maintain the dummy PPM detains aganist the setup groups.
    means: maintain the following information in setup matrix and try
    Setup transactiopn type: I
    Predecssr: Setup group 1
    Sucessor: Setup group 2
    Setup time: blank
    Unit: Min
    plan: Dummy PPM
    Product: Dummy product
    Regards
    Sravan maturu

  • Change over matrix

    Hi all,
    Can someone throw some light on changeover matrix. Where can I find some materials to read and understand.
    Thanks in advance.
    Mano

    Hi,
    I am sure you must be referring to setup matrix which has the data on change overs.
    you can find the documents on this in the link
    help.sap.com >SCM>APO>Master data > Application specific master data > Master data for production planning > setup matrix
    Hope this helps
    Ram

  • Setup group category & setup group Key.

    Dear Friends,
    I am facing some problem in setup group category... Please check this scenario and let me know...if anybody is having any idea about this...
    My scenario is: I am having a single work center... on which I  can do some machining activity.This WC is used in 100 material routings. but all my 100 materials are grouped into 5 categories. based on the dia... for example 100-120 dia one group 121-140 dia another group like that. If my two successive materials are belong to same group..then.. I donot have any setup time. if my two success materials scheduled on that machine are not belong to same group...then I am having 5 hrs of setup time.
    so here setup time I can not mention in the routing...
    this can be achieved by setup group and setup group key...and through capacity leveling... we can insert this setup time as per the matrix... in the matrix we need to define the setup times between two different groups..
    And here the setup time is almost equal to machining time of one material. max.. they can do 3 materials machining only.. if there is no setup in a day of 16 hrs working. So manageement wants to minimize setup time... so grouping of the materials should be based on the Dia... this is the requirement.
    I hope u understood my requirement...
    Actually I maintained all the setup group categories, setup group keys in the routing and I maintained setup matrix also...
    But during the finite scheduling through Capacity leveling I am not able to consider the setup time in the production order.... This is the problem I am facing... If anybody is having any idea...please share with me..
    Regards,
    Surya.

    Hi Suryanarayana,
    I see that you have defined setup type and setup group keys and also setup matrix.
    Please check the following under SPRO -> CRP -> Capacity leveling and extended evaluation -> Strategy -> Define strategy profile. There is a standard strategy profile to optimize setup times, which is SAPSFCT005 (Fin.sched.for./disp.acc. to setup group). Check the settings under this profile especially the check box "dispatch at best time for set up" to see if it works.
    Best of luck,
    Sharabh

Maybe you are looking for

  • Video playback from Final Cut Pro studders over HDMI

    I have a problem playing back video from FCP. The video output will studder during horizontal pans when I output via HDMI. The audio output is not affected. I have been playing video successfully using FireWire for output in FCP, however, my new vide

  • Error while creating sales order in ECC 6.0

    Hi All, I am creating sales order through VA01. Error comes As "Repairs processing with cost management only for the main item" The material which i am using is finished goods.

  • Error in determining receiver

    Hi Experts,    I am facing an error in one of the file to Proxy scenario. It's giving the following error. SOAP:mustUnderstand="">   <SAP:Category>XIServer</SAP:Category>   <SAP:Code area="RCVR_DETERMINATION">CX_RD_PLSRV</SAP:Code>   <SAP:P1>Problem

  • Text in adobe reader iOS

    Can I insert underlined text or only underline existing text?

  • How to stop Adobe flash Player from automatically opening when I start google browser

    Whenever I open any google browsers i.e. Chrome or google, the Adobe flash player automatically starts.  I want to know is there any settings I can unclick that will stop it from opening automatically.  I want to have the control of when to start fla