Setup time in means of transport ignored by TP/VS Optimizer

Hello Gurus,
I have a requirement of having a break for vehicle resource after each trip to carry out certain routine activities. I have modeled setup time of 2:00 Hrs in means of transport  for this. However when I run the TP/VS optimizer, it plans two consecutive shipments without considering any setup time.
Any idea on how to achive this requirement?
Regards
Sandeep Patil

Hi Sandeep.
In the transaportation lane, in the means of transport settings, there is one field u201CAddnl Retentn Per.u201D
Additional Stop Duration for a Transportation Lane (hhh:mm)
Did you think to use this ?
Additional Stop Duration for a Transportation Lane (hhh:mm)
The stop duration indicates the time that a means of transport is not in motion between two locations. It thus represents an addition to the duration of actual transportation. The duration of transportation represents the pure travelling time (working time, net transportation time), whereas the stop duration is defined as a gross time (that is, it relates to both the working time and the non-working time of the means of transport).
Regards
Datta

Similar Messages

  • Planned Delivery Time and Transportation duration- Tlane and Means of Transportation

    Dear Experts ,
    I have question regarding lead time calculation my SNP
    I have
    Start Location : A
    Destination location: B
    I maintained Planned delivery time in ECC- material master as 10 days  and cifed to Tlane Product procurement as 10 days
    and leave empty in the transportation duration empty so the total lead time is 10 days from start location A to destination location  B
    now
    I maintain 24 hours in Means of transport as transportation duration by truck
    now the lead time is 11 days from start location A to destination location B
    Now
    i leave empty planned delivery time empty and maintain Means of transport duration as 48 hours
    so the lead time is 2 days from A to B
    does my understanding is correct or not advise please
    Regards
    Raj

    Hi Raj,
    Take a look of these notes. Specially SAP note 379006. This note explains how the system sets the times in ECC and APO. Basically, It recommends a BAdI in order to match the delivery date in ECC and APO (transit time). What I recommend is to set delivery time equal to 0 if this is possible in your company.. This is not an SAP recommendation, because the delivery date is a key master data in the purchasing process and making it equal to 0 could not be allowed.. Now, if its possible in your case, it is the easiest way to ensure consistency...
    These are the notes:
    379006
    - Transport duration and planned delivery time in APO and R/3
    441622
    - Supplying-plant-dependent planned del. time/trans. time
    624982
    - Incorrect dates for RBA controlled stock transfer
    Kind Regards,
    Mariano

  • Safety days supply not followed due to change in Means of Transport in SNP

    Hello All,
    I am facing a strange issue regarding the SNP heuristics and means of transport. We observed that the system was not respecting the safety days supply. For example if we had a receipt in bucket 'N' and there is a violation of safety days supply in bucket 'N-1'. When we un a heuristic ideally system should delete the receipt in bucket 'N' and create a new one in bucket 'N-1'.
    But we observed that the system is retaining the existing receipt in bucket 'N' and also creating a new one in bucket 'N-1'. This is making the available days supply to increase manyfolds and the whole plan looks inconsistent from Safety Days point of view.
    After analyzing the issue i observed that if we have existing receipts using a Means of Transport 'X'. Now if we run the heuristic using a Means of Transport 'Y' then the system doesnt touch the existing receipts. If I run teh heuristics using the existing Mean of Transport then it works absolutely fine.
    Kindly suggest.
    Regards,
    Abhi

    Hi,
    when you check all products flag it means the means of transport is available for all products and not product specific, to select the MOT for SNP you need to check the aggrgtd plng flag.
    Also safety stock has nothing to do with MOT, SNP heuristic plans based on checks the quota arrangement if its for multiple MOT it will distribute the PR based on the ratio in quota if both MOT are able to meet demand on time, otherwise it will violate quota till the time both MOT are not capable of meeting the demand on time.
    If no quota is defined it will check for which lane is able to meet on time n if their are multiple lanes which can fulfill demand on time then it will choose MOT with less cost.
    Have you got multiple MOT for a source destination combination to be considered for SNP heuristic?
    Just check your design again and explain the problem again as this is not the standard expected behavior.
    Thanks,
    Sanjog

  • Extending Validity of Means of Transport in TL

    Dear All,
    Couple of questions:
    1) Is it possible to extend the validity of a Means of Transport in a Transportation Lane by increasing the 
        End Date?
    2)  Is it possible to increase the end date for SKU maintained on this lane?
    If yes? how?
    Many Thanks and Regards
    Amod

    Hi Vaibhav,
    Thanks for your inputs.
    I knew the entries could not be edited. I had tried it earlier before posting this message. Neither the means of transport nor the SKU end date is editable.
    As you have mentioned, I had already tried deleting the entire entry in means of transport and SKU list. Before trying to delete the entries I had deleted all transaction data on this particular TL for all SKUs existing on this lane. But the meassge I get every time is "There are orders existing on that particular means of transport or for that particular SKU".
    Futher investigation reveals that both the means of Transport and the SKU still have orders existing in test version which I have copied.
    I know I can create a new means of transport with validity start date matching with the end date of the earlier means of transport. The same thing can be done for SKU's on this TL as well.
    My question to you and other experts on this forum  "Is there still some way in which I can increase the validity and avoid creating multiple entry for same means of transport and same SKU on a particular TL?"
    Thanks for your help
    Regards
    Amod

  • Basis of picking means of transport in APO

    Please help me in understanding basis of picking means of transport in APO and what is the link between R/3 means of transport and APO means of transport.
    Manish

    In R/3 the means of transport is recorded in Shipment document. It contains all the information necessary for carrying out transportation. The means of transport necessary for a shipment is reflected in the system as a handling unit. These handling units contain information about tare weight and -volume of the means of transport as well as the weight of the packed handling unit. Information about the country providing the means of transport, details about the driver and travel time are also included in these handling units. Handling units that have already been created for delivery items are copied into the shipment document where they can be packed further, if necessary. Delivery items that have only been partially packed or not packed at all can be packed in the shipment documents.
    In APO the means of transport is planned in TPVS. If the client do not have TPVS implemented, the means of transport are taken based on the locations, products and cost as well.
    The difference between the R/3 and APO means of transport I see is that in APO there is product specific means of transport wherein we can assign the means of transport for specific products based on its demand or perishability. For example, if we have a Tlane between US and Ind, the possible means of transport could be by AIR or by Water. For a product which is a primary and active product for a company, the means of transport can be assigned as Air rather by water.

  • Product spec means of transport

    Hi Team,
    We have means of tranport Truck and Rail
    Truck - Transport Duration of a Transportation Lane - 48 hours
    rail - Transport Duration of a Transportation Lane - 336 hours
    I have maintained product spec means of transport in tlane master i.e.Rail - 336hour
    But when i checks product view I could see "start date' and "avia/req date" is only showing two days (48h) transit.
    Question - After maintaining product spec means of transpor- "rail" why system is taking truck time instend of rail time ?
    Please advice me
    Rgds
    SDB

    Hi SDB,
    Please check if the Check box for "All Products" in MOT is selected for Truck MOT. This setting can caue the issue you are facing.
    Regards,
    Ravi

  • Update Means-Of-Transport Type in a sales order

    I want to Update Means-Of-Transport Type in a sales order. You can find this field (VBKD-TRATY) in Sales Order->Header->Shipping.
    I couldnt find this field in BAPI_SALESORDER_CHANGE.
    Is there any function module which wud update it?

    Means of transport will be decided at the time of shipping in delivery .
    So LIKP-Traty will be the means of transport .
    i dont think there is a Fm to handle this .
    Let us check if someone has a solution.
    regards,
    vijay

  • Optimiser with means of transport

    Hi Experts,
    Pls spend some time to understand the below requirement and the design.
    Requirement- there are two plants, P1 and P2. Material M moves from P1 to P2 using a train R. The train can move 2100 tonnes in one trip.It takes 2 hrs to go from P1 to P2, hence it can make only 6 round trips between P1 and P2(i.e. 12 single trips) in a day. Hence APO should create only 6 orders in a particular day with max of 2100 tonnes as quantity for each order.
    Master data-
    Plants- P1, P2
    Material-M
    Resource(train)- R(bucket resource)
    Tlane- P1-->P2
    There is one SNP planning book and there are two data views- daily and monthly
    System design
    Max lot size for M at P2 is maintained as 2100
    Max bucket capacity for the resource= 6*2100= 12,600
    Means of transport for T Lane P1-->P2 is maintained as 'All products'. Transportation duration is set as 2 hrs
    Product specific means of transport is maintained for M, with consumption as 12 Tonnes
    Results-
    There is a requirement of M at P2 for 12,800 Tonnes. Stock of M at P1 is 12,800 Tonnes
    When I run optimiser on monthly view- it creates 6 orders with 2100 qty and one order with 200 qty, but all on one day-violating the rule of 6 orders only in one day
    when I run optimiser on daily view- it creates 6 orders with 2100 qty in one day and one order of 200 qty on the next day
    Query-
    1.Why do we need prod spec means of transport when the means of transport is defined as 'All products'
    2. What is the use of maintaining consumption as 12 Tonnes
    3. If I just go by transportation duration of 2 hrs, so the train makes 24/2=12 single trips, or 6 round trips. Hence 6 orders should get created with 2100 tonnes each in a day. But this does not happen and no planning happens in this case
    4.Why do I get different planning results when I use daily and monthly bucket views
    Would be very helpful to analyse the design and the concepts if someone can give some pointer
    Regards
    Manotosh

    Hi Kaushik,
    Thank you so much for your prompt reply and help. However I still have some query.
    1.As per my understanding we do not actually need prod spec MOT when all prod incator is there.I think some older versions of optimizer do not consider all prod tlane (I am not too sure abt it).But if all the prods for a specific plant can not be transferred through same MOT then it is required.Also if the res comsumption and the cost is different then also it is required.
                 - Your justification to have a separate MOT is absolutely valid as long as we need different MOT for any reason(cost, duration etc). But here there is only one product M being transferred between P1 and P2.
    2. Resource capacity will define the capacity in terms of total transportation capacity and consumption is required to do the planning.Like if the consumption is not maintained the capacity becomes as infinite.So there will be more than 12600 tons transported.
               - We define the resource max capacity and the utilisation. If the utilisation is more than 100%, I understand that it will try to supply more than 12,600 tonnes. But here the utilisation is maintained as 100%. What will happen if I maintain consumption as 10 Tonnes or 10 BBL or anything other than 12 T as currently maintained?
    3.There is a difference between scheduling and capacity.When you say 2 hrs but parallaly another tran can also go and transportation can happen.But when you define resource and capacity then you restrict the same.This is constrain plng but that duration of 2 hrd will not put any contraints.
           - The transportation resource is assigned to the T Lane. Hence whenever the T Lane is used, only the same resource is used for transportation. Hence we can not have more than one resource(R) acting simultaneously.
    4.If you see the results are same only difference is the period.Check the resource capacity view.I think you can see the capacity planned correctly and also the monthly view check the strt and end date.
           - As per the concept, SNP does bucket planning. Hence it will consolidate all the demands in a bucket and would create orders for the qty equal to the demand qty either at the begining of the bucket or middle of the bucket or end of the bucket. It will split the orders based on lot size or any other parameters defined. Hence I am getting multiple orders with 2100 qty(Max lot size) on 1st of the month. But the resource capacity is overshot in this case.

  • Operation split in setup time formula

    Hi, while creation of Work centers, i have seen the formula for setup as setup * operation splits. what is meant by operation split? pls explain?

    Hi,
    Operation split means no. of workcenters.
    It is used in workcenter scheduling tab processing formula.  For example operation split is 2. Say a process required processing time 1hr in one machine scheduled from 9.00am to 10.00am . If operation split is 2, system scheduled from 9.00am to 9.30am due to 2 machines.
    And it is used in capacity tab setup formula. For example operation split is 2. Say a process required setup time 10mins in one machine. If operation split is 2, system will calculate setup time is 20mints because 10mints x no.of workcenters (split).
    Regards,
    Dharma

  • Cannot setup Time Capsule

    I have a Comcast gateway cable/router. I am unable to setup Time Capsule, after dozens of resets, hours with both Comcast and Apple support, and two visits from Comcast field techs. I took the TC into the nearest Apple store for service. The device was still under warranty. The "genius" confirmed a defective TC, so I got a new one. Brought it home, tried to set it up following the directions, and still no luck.
    I am able to set up using an Airport Express but not TC. Is it possible that the replacement is also a lemon?
    Fortunately, I have established a wifi network using the Comcast gateway. But it uses only the 2.4GHz channel, which dramatically reduces download speeds as compared to 5GHz channel.
    I am certainly open to suggestions and advi

    The TC should be in bridge mode.. plugged into the comcast router. Do the setup before you plug it in... if it fails, use ethernet directly to the TC and give us a few screen shots of the summary page.
    I would also use 5.6 utility.. frankly I think you can get in a knot if you use 6.1 because it auto sets things it shouldn't.
    How to load 5.6 into ML.
    1. Download 5.6 for Lion.
    http://support.apple.com/kb/DL1482
    Click to open the dmg but do not attempt to install the pkg.. it won't work anyway.
    2. Download and install unpkg.
    http://www.timdoug.com/unpkg/
    Run unpkg on the desktop.. it is very simple.. drag the AirPortUtility56.pkg file over to unpkg.. and it will create a new directory of the same name on the desktop.. drill down.. applications utilities .. there lo and behold is Airport utility 5.6 .. drag it to your main utilities directory or just run it from current location.
    You cannot uninstall 6.1 so don't try.. and you cannot or should not run them both at the same time.. so just ignore the toyland version.. the plastic hammer.. and start using 5.6.. a real tool.
    For screen shots see this post.
    https://discussions.apple.com/thread/4668746?tstart=0

  • I am trying to setup time limits in airport 5.6

    I am trying to setup time limits for internet usage in airport 5.6—
    but i don't get a timed access control "option. Tried on both imac and macbook pro.

    What are you setting it up as.. join wireless network .. the very worst setup, it will disappear.. reboot the whole network in order modem. router TC.. clients and it will likely reappear.
    Tell us what network setup you are using..
    If you setup with cable to a computer completely isolated from the network with TC also isolated.. finish the setup of everything you want. .before update.. then plug it into the network. .then restart everything in correct order.. it will work most of the time.

  • How to check open deliveries and open sales order using means of transport

    Hi,
    I want to check open sales order and open delivries which is having "ABXP" means of transport type .Can anybody suggest me to check in which table or any transa

    means of transport type
    Please reconfirm whether the above statement is correct.  Moreover, you yourself can check at your end by opening any sale order, go to that field, press F1 and press the "Technical Information" icon so that you can see the corresponding table name and field name over there.
    G. Lakshmipathi

  • How to make means of transport field as a mandatory field  in MV45AFZZ

    Hi All,
    I am new to User-Exits.
    In Sales Order creation I have got a requirement In such a way that based on Sold to and Shipto Party Combination of sales order
    I have to make Means of Transport Field as a Mandatory Field.
    I have gone through the Program MV45AFZZ.
    Please let me know how to do it .
    Regards.
    Rohit.

    Hi ,
    Write code in Save_Document_prepare In program MV45AFZZ.
    Constant :c_flag type c .
    if c_flag  eq space.
    IF VBAK-VSBED EQ '01' AND VBKD-TRATY IS INITIAL.
      MESSAGE E0001(SABAPDOCU) WITH 'Enter means of transport'.
    endif.
    c_flag   = 'X'.
    endif.
    Regards.
    Eshwar.

  • The necessary shipping materials and the means of transport

    The answer of the question below is "d. Shipping point". On the other hand, shipping type (shipment type determines how the goods will be transported - tuck, train, ship etc....) is entered in the "shipment type" at the customization.
    Taking into consideration this fact, why is the answer of this question is given as "shipping point"?
    What part of the company is responsible for the type of shipping, the necessary shipping materials and the means of transport?
    Only one answer is correct.
    a. Sales Organization
    b. Transportation planning point
    c. Shipping condition
    d. Shipping point
    e. Warehouse

    hi
    As per my knowledge, normally goods are transported from Plant through shipping point, So ultimately shipping point is the responsible for that.

  • When I create a Planned order using PDS, the Setup time is coming as 0.

    We have been using PPMs for a long time, and now we are trying to migrate to PDS.
    We are currently in SCM 7.0.
    I successfully created the PDS in APO (using CIF from R/3). In the PDS (in APO), for a particular activity, I see the  activity type is "S", and the Activity Duratiion (Fixed) is 43,200 Seconds.
    However, when I create a planned order using this PDS, the activity time is zero (End time = Start Time).
    When we use the PPM the setup time comes correctly.
    Any help will be appreciated..

    Senthil,
    Thanks for your views.
    I have checked all that you have suggested, and it is okay. The issue still persists.
    One thing that I noticed was that it is working fine in the old SCM 5.0 environment - the setup time is coming correctly in the planned order.
    However, we have this issue in the new SCM 7.0 environment. Is there something that is different in SCM 7.0 in terms order explosion ?
    Reagrds,
    Sastry

Maybe you are looking for

  • Simple button help needed!

    I want to make a simple round button that glows when you mouse over it and depresses when you click it. Apparently to do this I need to use Filters to make the glow and bevels. But Filtersonly work on movie clips, buttons and text. So I make a circle

  • HP LaserJet 1536dnf MFP driver download not working

    Not working since I upgraded Windows . Also completed uninstall, complete reinstall, should be plug and play, went to Hp site downloaded driver specific to this printer, gets almost to the end, even shows that scan operation should work but then erro

  • GI at the time of GR

    Hi, I have a requirement wherein, one particular component has to be Goods Issued automatically, only at the time of Goods Receipt of the Production order. What are the various ways / work around by which this can be acheived? Note: I don't want to u

  • Connecting an older MacBook Pro to Current Dual (Mac) Display Monitors

    I am thinking of buying dual displays (24-inch) and I have a MacBook Pro I bought in 2007: It's an OS X (10.4.11). I'd like to be able to connect this laptop to the dual displays, but I've read that there may be issues with connectivity with the "old

  • Ipad does not download when locked

    Every since i upgraded to ios 7, my ipad 4 refuses to download apps when locked. Its no problem with small apps as i can leave it unlocked but when i have to download big file(apps) its a problem as i have to leave ipad unlocked for successful downlo