Shift sequence in CO11N ?

Dear guru ,
in the confirmation of the operation of a production order (CO11N) i want to enter the shift sequence
for the work centre capacity involved.
Itu2019s this field available in this transaction ?
Thanks a lot.

Dear,
Shiftwise confirmation is now part of SAP standard! The new functionality is now part of ECC6.00 Enhancement Package 3, see help.sap.com for further information and assistence,
http://help.sap.com/erp2005_ehp_03/helpdata/EN/46/f2a5ce3cd767f9e10000000a1553f7/frameset.htm
Use Release Ecc6.00 with enhancement 3
Otherwise you need to go for Z development.
Regards,
R.Brahmankar

Similar Messages

  • Shift sequence query in PP work center

    Dear All,
    I am having one problem while maintaining shift sequence in work center. I have maintain all config settings in OP4A shift 1 shift 2 shift 3 but when I create work center and select shift sequence, it is only taking shift 1 and not all 3 shift for all 7 days.
    Can anyone tell me the solution?
    Thanks in advance.
    Regards,
    Max

    Dear Santosh,
    Thanks for the valuable inputs.
    I have created following sequence in OP4A.
    1, Create a Group eg. CB
    2.Create a shift definitions like SHIFT1,SHIFT2,SHIFT2, START/END DATE, START/FINISH TIME OF SHIFTS, NO BREAKS ARE THERE and assign it to group.
    3. Define individual shifts SEQUENCE DAYWISE wrt to groupo.
    4..Assign grouping in capacity header of work center.
    5.Now go to add interval option and create a new version of capcity which contains desired shift sequence from the shift group assigned.
    7. assign proper valid froma and valid to dates.
    8. In capacity header screena ssign the newly created capcity vesrion as active vesrion.
    BUT STILL i WILL ABLE TO MAINTAIN ONLY FIRST SHIFT SEQUENCE FOR ALL 7 DAYS.
    SYSTEM IS NOT SHOWING 2ND AND 3RD SHIFT.
    PLEASE HELP ME OUT.
    THANKS
    MAX

  • Assignment of shift sequence in work centre

    I have already created the grouping key & shift sequences in OP4A. There are 7 groupings when I see in OP4A. But when I try to assign them in CR02 capacity header screen , I see only 3 grouping keys. I dont see the one I have created too. What could be the reason?

    Please check you have any letters in grouping code?
    use only nunmbers - it will appears
    instead of AA, AB, AC create with 11,12,13
    Please close the thread if answer is okay, otherwise revert back

  • Shift sequence

    Hi all ,
    What is the use of shift sequence ?
    I have defined Shift sequence , assigned to work center Etc .
    But  whr does the same will appear or what is the use of the same .
    (HR module is not implemented here )
    Regards

    Hi venky
    Normally the available capacity of that particular work center is calculated from the data we are giving in the capacity header/Available Hrs from - To and the break time, the number of work center and efficiency
    If we give shift definition and shift sequence. We have to assign that in shift group in the capacity tab.
    The available capacity will be calculated from your shift definition and brake time which is given in your shift group.
    if your shift start time is 06.00 end time 14.00 break time is .5 hrs. Then Available capacity per day is 7.5 Hrs.
    If your are giving shift sequence also 14.00 to 22.00 - 22.00- 06.00. Then the available capacity 7.5 X 3 = 22.5 Hrs per day.
    Regards
    J. Saravan

  • Shift sequence in available capacity

    hi, all SAP experts,
      my question is as follows
    I created grouping in which shift sequences are defined and i assign this group to work center in capacity header. So work center should have to select shift sequence in capacity tab but i enter manually start time and finish time in capacity header.So why systm can't show interval of available capacity daywise automatically through grouping or is there any setting for this?
        thanks in advance
    i will look for points also
    regards
    Nitin Nerkar

    Dear,
    In work center change transaction capacity view
    assign this grouping no XX.
    Enter active version = 1
    Then Click on interval and shift push button (left top)
    follow the menu path Edit>insert>insert interval
    enter
    valid from and valid from field
    enter shift sequence and remove the data if there in any other filed and click on ENTER. all the days in week are defaulted with the shift seq you defined.
    It will work for you.
    Regards,
    R.Brahmankar

  • What will happen if a maitain both standard available capacity and grouping key ( shift definition and shift sequence) in the capacity header of a work center?

    Hi all,
    Im little confused with the capacity header in work center. In the capacity header there is one place to give start time, end time, length of break and number of individual capacity. And in grouping key i can define the shift and shift sequence. So if im maintaining both of these ( standard avilable capacity and grouping key), which will be considered to calaculate avilable capacity?

    Hi
    If you are running three shifts ,please maintain the data as given belwo
    start :00:00:00
    End:23:59:59
    Break :03:00:00 ( 1 Hour per shift so 3 hrs for 3 shifts)
    No.of individual capacity :1
    System will understand that it is round the clock operation with total three hour brak and you will get 21 hour per capacity
    Hope this helps
    regards
    Prakash

  • About the shift sequence setup in capacity categary

    Hi
    Harish here
    Can any body give me the technicality behind the planning, how shift sequence will consider.
    For ex: i have created the wc and for that i have created the capacity as machine. in the capacity header i have entered the factory calendar and start time as 9.00 am and end time 5.30 pm and break as 1h. also i have created the group of shift sequence in that i have taken as general shift. that is only one sequence ( 9AM-5.30PM no break consider) that has been assigned to above category
    How the system is selecting the sequence for the group (enter in capacity catagory) as well as calendar and arrives the dates of schedule.

    ...

  • Shift sequences

    Hi team,
    plz can anyone tel me how to define the shift sequence in detail,i have been through this path but the sequence key its not taking ,on what basis it should be given
    SAP Reference IMG u2013  Production Planning for Process Industries u2013 Master Data u2013 Resource u2013 Capacity Requirement Planning u2013 Available Capacity u2013 Define Shift Sequence

    Dear Pravin,
    Step wise try to do like this newly,(T.code = OP4A)
    1) Groping:- Define new group say -95 ok with name TEST.
    2)Then Click on Work break schedules:- New entry-
    0001 0  BK1 12:00:00 12:30:00        0,50
    0002 0  BK2 18:00:00 18:30:00        0,50
    0003 0  BK3 03:00:00 03:15:00        0,25
    3)Define Shift definitions like as,
    A First Shift 01.01.0001 31.12.9999 07:00:00 15:00:00 7,50  0001
    B 2nd Shift 01.01.0001 31.12.9999 15:00:00 23:00:00 7,50  0002
    C 3rd Shift 01.01.0001 31.12.9999 23:00:00 07:00:00 7,75  0003.
    4) Define Shift sequences
    SH1  1   Frist Shift       A A A A A A A
    SH2  2   Second shift   B B B B B B B
    SH3  3   Third Shift       C C C C C C C
    Then Assign it to your work center.
    Regards
    R.Brahmankar

  • Shift sequence of a workcenter changed AFRU not updated

    hi all,
    i have an issue with the change in work center's capacity.
    by changing the shift sequence of a work center and then booking the hours against it, i can not get any update in AFRU in neither of its field ISM01, ISM02 ISM03....
    what could be the reason? or  am i missing anything?  do i need to do anything more after changing the capacity related parameters?????
    waiting for your master comments, valuable inputs?
    best regards,
    Maulin

    hello Thaila,
    first of all thanks for yout reply,
    in fact we have a schenario where we book the hours with event type B10 and B40. without any yeild confirmation.
    and we consider the duration between the  B10 and B40 as activity duration (in terms of hours).
    so when i change the shift timings in the work center and post the hours in B10 and B40, there is a miss match. e.g. B10 i posted at 17.06.2009 10:30:00 and
                             B40 i posted at 17.06.2009  16:30:00 so in ISM01 or in ISM02 (based on activity and std values maintained) it should updated as 6 hours....
    so it may possible that after changing the shift i am missing some other procedure.....
    i hope this would have clear the question you had...
    best regards,
    Maulin

  • Assignment of shift sequence to work centre

    I have created a new shift sequence. where can I assign it in the work centre?

    Hi,
    you need to define the grouping key /shift definition /shift sequence in SPRO.
    Assign the grouping key work center capacity tab pageunder capacity header.
    Regards,
    nandha

  • 9 Day fortnight shift sequence

    Hi PP'ers
    Our company is changing our working pattern to a 9 day fortnight, here we work 1 week with 5 days and one week with 4 days and repeat.. i.e. we have every second friday as a holiday.
    What is the best way to reflect this in SAP such that we cannot plan production on every second friday?
    A shift sequence... I can't seem to find a way to make a sequence longer than 7 days
    A change to the factory calendar?
    any tips appreciated.
    thanks

    dear friend,
    you can create a new holiday calendar and set it in your current factory calendar fixing workdays as well.
    use SCAL
    if you need, you can create a Special rules...
    regards,

  • Shift wise confirmation and shift wise production report

    Hi Guys
    To get shift wise production confirmation and reports,  I have maintained the following setting ,
    1-     maintained shift sequence and with shift grouping,
    2-     assigned the shift grouping to work centers,
    other theses settings, what other setting to be done for  shift wise confirmations and also production reports,
    thanks in advance,
    mohan.m

    Hi Mohan,
    We had similar requirement for our manufacturing plant.
    We have done Z-Development for
    1) Shiftwise - Linewise Production
    2) Shiftwise - Beltwise Packing
    1) for that we have define new control key
    2) That key assigned to master recipe.
    (Why new control key ?
    New control key is defined specifically to generate this report. Because Auto GR is done only at the end of packing and not at the end of shift. But we want report for each shift. That's why after each shift end proposonatly that much qty is confirmed by new control key. However actual Goods receipt is only happened while completing total manufacutring or packing)
    3) That control kept as base of Z-development.
    4) As far as shift timings are concerned, we have taken actual shift timings of our manufacturing plant.
    Hope this will help to resolve your problem.

  • Regarding Shift Activation In ECC 6.0

    Hi, We are implementating  ECC6.0 in our company. We have downloaded the Ecc6.0 enchnacement pacakages from service markets and applied it but still the shift is bnot being actives in confirmation screen
    Please helps us in tghis regards
    Bhupendra singh

    Hi,
    You have to execute following stpes to reflect shift in co11n
    01 SPRO : OPK4 select freely definable screen number & put shift in pushbutton. This will only display shift on conn screen ( No input values)
    02 ABAP Activity;  Create new append structure in table AFRU ,include components & allowed values( shift 1,2,3),activate user exit confpp07 ,activate function group for screen 900.
    03. Change screen layout as per requirement in se51.
    this will make entry of shift possible in co11n as well as saving in table for reports.
    Regards,
    Milind.

  • Capacity- shifts

    Hi, i defined in op4a, 3 shifts and grouped under grouping key xx which is mentioned in capacity heade screen of wcenter. when i go to interval and shifts tab, it shows only 8 hrs capacity. i want here to appear all 3 shifts as defined in op4a. how to show 3 shifts in shiftss and intervals screen?

    Hi,
    You defined Shift sequence in TC: OP4A with 3 shifts by grouping key xx. You maintained this grouping key xx in Grouping field in General data section of capacity header under capacity tab in work center views. Its ok.
    Now you goto Intervals and shifts tab the data which you are getting is system default. ok.
    Now you maintain one more New shift by clicking on Interval Button. You give Valid from and To Date and maintain shift sequence then press Enter.
    Now see you got all the shift details.
    Regards
    Jagadeesh K

  • Shift Abbreviations in Shift Planning

    Hello gurus,
    Anyone ever experienced this?
    i need to update It2003 with a period work schedule rule and not the Daily work schedule rule and it looks as though this is SAP STD that you can only work wirh DWS in shift planning.
    Anyone with some crancking idea of how i can overcome this?
    Regards
    Sher

    Dears...
    I am already using the Enhancement package 4 and business function LOG_PP_SRN_CONF is already activated. But still Shift field is not appearing the confirmation screen (CO11N). Even in the "Single screen entry of confirmations" configuration also (transaction OPK0 in Default tab) Shift and shift grouping fields are in INACTIVE mode. Please let me know... how can make it active. So that I can use the shift field in CO11N transaction.
    If you need any clarification please let me know.
    Regards,
    KN.
    Edited by: Kodand Nag on Feb 6, 2010 11:28 AM