Shift wise confirmation report
Hi
Is there any report in SAP to see the shiftwise confirmation reports in Production.
Actualy my management wants to see the work center wise list as well as confirmation is done or not of that stage.
E.G. Pre turning material in this operation is
1) Threading in
shift 1 15 nos
shift 2 17nos
shift 3 15 nos
total ---47 all these operations are first confirm in SAP or not
this they want to tally with physical qty achieved or not
Is it possible in COOIS?
how or what else changes to be made in system?
Thanks
Pert
Hi,
It can be possible with some ABAP development, If you able maintain the shift field in confirmation screen (CO11n). The data entered here will come in COOIS confirmation report.
Shekhar
Similar Messages
-
Shift wise confirmation and shift wise production report
Hi Guys
To get shift wise production confirmation and reports, I have maintained the following setting ,
1- maintained shift sequence and with shift grouping,
2- assigned the shift grouping to work centers,
other theses settings, what other setting to be done for shift wise confirmations and also production reports,
thanks in advance,
mohan.mHi Mohan,
We had similar requirement for our manufacturing plant.
We have done Z-Development for
1) Shiftwise - Linewise Production
2) Shiftwise - Beltwise Packing
1) for that we have define new control key
2) That key assigned to master recipe.
(Why new control key ?
New control key is defined specifically to generate this report. Because Auto GR is done only at the end of packing and not at the end of shift. But we want report for each shift. That's why after each shift end proposonatly that much qty is confirmed by new control key. However actual Goods receipt is only happened while completing total manufacutring or packing)
3) That control kept as base of Z-development.
4) As far as shift timings are concerned, we have taken actual shift timings of our manufacturing plant.
Hope this will help to resolve your problem. -
hi Exprts,
Process:
I shift starts at 6.00 am and ends at 14.00 hrs
II shift starts at 14.00 hrs and ends at 22.00 hrs
III shift starts at 22.00 hrs and ends at 6.00 am (next day)
3.We confirm the qty in the t.code CO11N
The requirement is : How to take the Shift wise production report? , and also a report which shows consumption of components against production order in a shift.
Regards
RameshDear Ramesh,
check this link to first post the confirmation shiftwise ,both in CO11N and CO15.
http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/c0fa9a04-376a-2c10-c396-86d32ac80614?quicklink=index&overridelayout=true
Further to this you can get the shift wise production report using COOIS.
Regards
S Mangalraj -
Hi Friends
I am able to do shiftwise production confirmation.
Shiftwise production confirmation is possible as of SAP ERP 6.0 Enhancement Package 3. But i want shift wise production reports. Is there any standard reports?
Please suggest
TaraDear Tara,
You can get the shift details in the report COOIS.
Select the profile confirmation in the input screen and execute the report.
Click on Change layout and select the field for shift definition and you will be able to get the shift details.
check and revert back.
Regards
Mangalraj.S
Edited by: Mangalraj.S on Sep 30, 2009 10:57 AM -
Report on power generation from each plant and shift wise(PP report)
Hi,
i got one Functional spec on pp module. this FS main object is calculate the daily smelter performance.
Based on this FS I will make a report on POWER GENERATION FROM EACH PLANT AND SHIFT WISE.
so please can anyone of you advice to me , is there any standard extractors and standard cubes or ods are there for make this report.
Regads,
Suresh.Hi,
here i mentioned tables,fields and logic according to Fspec.
S.no Report Field SAP Table-field Logic
1 Shift AFRU - KAPTPROG
2 Unit MKPF-VERID Pass MATNR and VERID to AFPO and fetch AUFNR for all VERID and pass AUFNR to AFRU and fetch KAPTPROG and GMNGA for that particular BUDAT
3. Total Generation - ADD all the unit GMNGA for Individual KAPTPROG
4. Total Auxiliary Consumption - Pass MATNR and AUFNR to MSEG and fetch the MBLNR and MJAHR. Check MSEG - MBLNR and MSEG u2013 MJAHR = MKPF - MBLNR and MKPF u2013 MJAHR
and fetch BUDAT for that particular date and pass it those MBLNR and MJAHR to MSEG and check for movement type 201 and fetch MENGE.
5. Export to GRIDCO - Pass MATNR and AUFNR to MSEG and fetch the MBLNR and MJAHR. Check MSEG - MBLNR and MSEG u2013 MJAHR = MKPF - MBLNR and MKPF u2013 MJAHR
and fetch BUDAT for that particular date and pass it those MBLNR and MJAHR to MSEG and check for movement type 261 and check for Field SHKZG if H fetch MENGE.
6. Import to GRIDCO - Pass MATNR and AUFNR to MSEG and fetch the MBLNR and MJAHR. Check MSEG - MBLNR and MSEG u2013 MJAHR = MKPF - MBLNR and MKPF u2013 MJAHR
and fetch BUDAT for that particular date and pass it those MBLNR and MJAHR to MSEG and check for movement type 101 and check for Field EBELN and fetch the MENGE.
7. Smelter Consumption - Pass MATNR and AUFNR to MSEG and fetch the MBLNR and MJAHR. Check MSEG - MBLNR and MSEG u2013 MJAHR = MKPF - MBLNR and MKPF u2013 MJAHR
and fetch BUDAT for that particular date and pass it those MBLNR and MJAHR to MSEG and check for movement type 201 and check for Field WERKS 1400 and display MENGE.
8. Net Export / Import (MW) - Difference between Export to GRIDCO and Import to GRIDCO
Based on these information ,can please anyone advice to me, is there any standard extractors ,cubes and ods for make this report.
Thanks,
Suresh. -
Dear All,
I have activated EP3 object "log_pp_SRN_CONF" for shiftwise confirmation and updating process completed without any error. However in IMG at OPK4 - "individual operatioin general" tab, system is not displaying shift related new feilds. Here interesting point is that when i m creating worcenter masterdata it shows new shift related feilds.
I have searched SDN but there is not such kinda problem reported earlier. Please help me n sorting out this problem.
Thanks
NavaidDear
Please check the set up in OPK0/OPK1 and also OPK4N
Refer earlier posting : Operation Confirmation through CO11N
Process Order Confirmation Screen
Regards
JH -
Shift wise production booking report
Hi experts,
Is there any way to get the shift wise production report?
Through MB51 & with mvt 131 /101 , we get all the production booking for a period but user required this information on shift basis.
If any body had done some Z development, kindly communicate
MarutiDear Maruti,
I you are working in ECC 6.0,you can use enhancement package 3 and do the confirmation in shift basis and also get the shift
details in the COOIS report.
Check the article,
http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/c0fa9a04-376a-2c10-c396-86d32ac80614
Regards
Mangalraj.S -
Daily Shift wise Report, Dash board reports
Dear all
With refering to the present project in 4.7 version the customer requirement is below.
1. Shift wise maintenance report - Here they are presently maintaining Section, shift, Date, From time, To time , Job descriptions, attenede by remarks.
In another coloum in same sheet they needs
From time, To time , Delay descriptions, attenede by remarks.
Then thirs is communication for next shift- there they are writing the texts which they are saying to next shift guys.
2. Another what they wants is regularly top managers wants to see the maintenance details ( prev order, down time, consumption cost etc ) in their system dash board(screen) . they are not willing to go sap. How to do this thro .Net or workflow . This is report should be fulfiiled by us.
3 Shutdown Planning report- here they are maintaining the date wise job hours in graphical form. How we can activate this
I request you please have some idea about this.Dear Nandip/Iftikar,
Dear thanks 4 ur answers. I have asked the same with our abapers , but they are new and not able to help. i have well tried with notification customer table addition in spro. but its not helping as required.
The thing is i cant prepare the specs for this report. Example for shift we can create Z table. But Processing job description, Action taken, delay reasons how i can prepare the specs.
I request you to share your Program or specs please then its better for us. please send at thennarasu_kandasami@ welspun.com
Edited by: thenna arasu on Jun 2, 2008 2:12 PM -
Shift wise process order confirmation
Hi Guru's
My client is asking about shift wise confirmation of process order.
wht r the step will I follow to maintian the desire requirement.
Please explain with example upto order confirmation, wht r the field to be check & wht should be the input I give the field.
If any body sent me the doc related to the problem
I'll be thankful to him.
My ID:- [email protected]
ParminderParminder,
Basically your shift definition is for capacity planning/scheduling in the desired way
Create a process order ,Hope you would have also maintained your recipe with timings
"<b>wheer the impact will be come of this configuration.either Process order creation or order confirmation</b> "
The proces order will be scheduled(<b>at the time of order creation</b>) as per the timings mentioned in the recipe & the shift definition in the resource
Then you do phase wise confirmation-Time ticket/Time event
As per your reply what i understand is that in 3 shifts your process order will get over
So your shift supervisor will confirm accordingly
Hope this is useful
Revert back if you have any further queries
Reward points if useful
Regards,
SVP
Message was edited by:
SVP -
HI,
Can any through light on Shift wise confirmation. IF u have any program or enhancement please do favorable.
Thanks in advance
Regards
NSRDear,
Please follow below link:
http://help.sap.com/erp2005_ehp_03/helpdata/en/46/f2a5ce3cd767f9e10000000a1553f7/content.htm
Which help you in shiftwise confirmations including customization.
Regards,
R.Brahmankar -
Report to show shift wise activities for particular product
Hi, Is there any report exists to show shift wise activities carried on particular product, basically time taken,man/machine utilization,in-process rejection,machine break down etc.? how to generate the same.
Dear Yadav,
This report is something called as workcenter's performance report or as plant performance report.
In standard SAP again CO28 or COOIS or MCP7 or MCPH can be used.
But still in your case only a customized report can fulfill your requirement.
check and revert back.
Regards
Mangalraj.S -
Confirmation report for shipment tracking
Dear experts,
how can i generate a confirmation report for shipment tracking-vendor wise ???
Regards,
Durgesh Tambat.Hi Durgesh Tambat;
Please search in SCN before create a thread , i hope that you will reach your solution.
Regards.
M.Ozgur Unal -
Hi,
While doing set up for Shift Related Confirmation ..
In Confirmation parameters, i could not find Shift / Customer-specific Fields / Subdivision of Quanitities and notification type
I have created Shift Sequence. in Confirmation parameters i have to choose proposal shift. Which i couldn't.
Is there any additional configuration required?
regardsHi,
As Vivek said, You should use ECC 6.0 EHP3 version.
EHP - Enhancement Package.
Pl. let us know, which version you are using.
In earlier version, Shift related confirmation was not possible and hence shift report.
With EHP 3.0 you are able to confirm and take report for the shifts.
Further refer the following:
LOG_PP_SRN_CONF: Business Function Shift Report/Notes, Confirmation
Use
As of SAP ECC 6.0, Enterprise Extension SCM, Enhancement Package 3 (EA-SCM 603),
the business function Shift Report/Notes, Confirmation (LOG_PP_SRN_CONF) is available.
This business function enables you to create and process shift notes and shift reports and to
use enhancements for the confirmation process relating to production and process orders.
The following Release Notes provide you with further information:
o LOG_PP_SRN_CONF: Confirmation of Process and Production
Orders (New)
o LOG_PP_SRN_CONF: Shift Notes and Shift Reports (New)
See also
For more information, refer to the SAP Library under Business Function Sets and Business
Functions --> Enterprise Business Functions --> Logistics --> Production Planning and
Control --> Shift Report/Notes, Confirmation.
Madhava -
How To calculate Total Number of Employee in shift wise
Dear Gurus,
my requirement is calculate the total no.of employees present & absent in shift wise.
My output like this.
Department Shift Present Absent
Information Technology GSFT 56 24
Engine Shop ASFT 124 26
BSFT 155 45
CSFT 80 20
Thanks,
Rajkumar.AHi,
You can make a custom report for this.
If you want to know generally there is a head count report available in OM -
Dear Experts,
I need to have a report that shows all the details of vendor wise payment reports is there any specific transaction codes to resolve this issue
Regards,
Ramakrishnan. SHi
The simplest I Could think of is FBL1N itself with cleared Items. You can always subtotal on Vendor No and Payment Document type. There are other std reports like S_ALR_87012085, S_P99_41000099. It also depends on what kind of information you want from the payment report
Regards
Sanil Bhandari
Maybe you are looking for
-
Does any one have the same problem with their MacBook Pro i5 Intel Dual Core? If the computer goes to sleep (not the screen) and is asleep for a while, when I try to wake it up it doesn't respond. I have to power it downn and restart it and sometime
-
I Actually Like My New Macbook Pro
While there has been a lot of negative posts about Apple's decisions regarding the new Macbook and Macbook Pro, I have to say that I love my new Macbook Pro. For some reason I can type faster on the new keyboard and I prefer the feel of the keys to t
-
An error occurred while trying to access the server
an error occurred while trying to access the server, I keep getting this message when trying to convert, what is the problem, windows 7 user
-
DVD ROM displays, but nor working - Please help
Hi, I have a Pavilion dv4t-1400 and recently upgraded it to Windows 7 home premium. I have a peculilar problem. My DVD Rom is not working. It shows up under "Computer", it has no yellow marks under "Device Manager" If I insert a blank disck, after so
-
Hi, I have PeopleTools 8.50 installed on Windows 7 Professional x64. When I select View in Browser menu item from the Layout menu in Application Designer to see what the my page looks like, Application Designer just shutdowns without error. Also, if