Shopping cart is awaiting for approval even it does not need

Hello friends,
I am doing configuration to srm 5.0 .
my shopping cart is waiting for approval even it doesnot need approval.
Even when i create direct material purchase order the PO is going to approval.
i have clearly defined the start conditions.
what could be the possible reasons for this situation.
Thank you in advance for your valuble suggestions.
with regards,
mahesh

Hello Yann,
I am using simple starting conditions based on price less than 1000 euros.
I have done the same configuration to SRM 4.0 also based on prices.
I have activated workflows for shopping cart
1.with out approval
2.one step approval
I have followed the configuration document carefully.
Could you suggest what could be possible other reason.
with regards,
mahesh madasu

Similar Messages

  • Shopping Cart is awaiting for approval even it is not needed.

    Hello friends,
    I am implementing SRM 5.0 and i am facing problem related to approval of shopping cart.
    Even the shopping cart does not need any approval the status is showing as
    it is awaiting for approval.
    When i go in to detailed through transaction sw2i_freq the system status is in " error".
    What could be the possible reason for this situation? .
    i am using SRM 5.0 with service packe 6.0.
    I appreciate your valuble answers.
    Thanking you,
    Mahesh Madasu.

    Hello Mahesh,
    If the error message is like Error when processing node '0000000241' (ParForEach index 000000), check the note 962488 "Workflow definition '&' not in version '&'".
    Regards,
    Masa

  • Hi,When I submit the budget for approval, it is approved and base lined when we submit it for approval. It does not go in approval hierarchy. We want it to flow through approval hierarchy.

    Hi,When I submit the budget for approval, it is approved and base lined when we submit it for approval. It does not go in approval hierarchy. We want it to flow through approval hierarchy.

    Hi Amit,
    if I understand correctly, you just need for a particular object a tooltip to be showed.
    There is no such functionality hence you used the trick of using a hyperlink, which if clicked generates undesired behavior.
    Hyperlinks don't allow themselves to be disabled, therefore if you are using that workaround you must cope with that.
    I would suggest to create an Idea at [https://ideas.sap.com] for having in the properties of an object a tooltip, then post the link to the idea here and other users will vote if they like the idea.
    Thanks and regards,
    Simone

  • What is the advantage of exporting mpeg-dvd vs mpeg for dvd if mpeg does not need to transcode audio

    What is the advantage of exporting mpeg-dvd vs mpeg for dvd if mpeg does not need to transcode audio and also burns to dvd?

    The MPEG2-DVD preset also produces a DVD spec-legal file.  If you use the generic MPEG2 preset, you can too easily create an out-of-spec file that will have to be re-transcoded by En.
    Jeff

  • SC status is still in Awaiting for Approval Even after PO and confirmation creation.

    Hi Experts,
    We have SRM 7.0 with Classic scenario, Here we have strange case where for One SC already backend PO created and Confirmation is done. Still SC status is showing as Awaiting for approval. Kindly Help me to solve this issue.
    Thanks in advance
    BR,
    Basu

    Hi Basu,
    What is the workflow framework that your are using. Is  it application controlled workflow?
    1.     Go to T code BBP_PD and check if the workflow triggered for the shopping cart is in in-Process status. If it is in in-process status copy the header workitem and go to T code SWPC , remove all the values displayed in the selection screen just enter the header work item ID and execute.  If you are able to see any entry after execution select it and click on continue workflow. this will fix your problem.
    2.     Check in transaction SM58 to see if there are any failed entry on the day of shopping cart creation , if there is any entry in failed status please reprocess the LUW.
    hopefully any one of the above steps will fix your issue.
    Regards,
    Suresh

  • Settings to recall shopping cart when awaiting approval

    Hello
    We are on SRM 7.0.
    In SRM 7.0 when SC is in awaiting approval and requestor press edit then shopping cart can be recalled. What are the settings / sap note required for this.
    Thanks,
    Ashish

    Hi
    Are you a creator of shopping cart and trying to edit the cart while awaiting for approval ?
    or
    some once created and are you trying to edit the cart in awaiting for approval?
    what is your SP ?
    Note 1491389 - Monitor SC:delete shopping carts in status awaiting approval
    You as an administrator go to Monitor shopping cart transaction and select a shopping cart which has status 'Awaiting approval'. When you try to 'Delete' the cart, system throws an error 'Change mode only possible after recall'
    Other terms
    CANCEL_PROCESS_FOR_RESTART /SAPSRM/IF_CLL_MMS_SC~DELETE BBP_MON_SC 'Process controlled workflow'
    Reason and Prerequisites
    If the system is using process controlled workflow, the workflow has to be recalled prior to the deletion of the cart.

  • Shopping cart awaiting for approval

    For the documents shopping cart, RFX we dont have any approval proceedureonce the shopping cart is created it gets auto approved.
    But for the documents in the approval tab shows automatic approval for the documents, but in the query report for the the document shows awaiting for approval.
    Can you guide me on this
    Thanks in advance

    Hi,
    What is the document status and workflow status in BBP_PD transaction?
    I guess there is some error when creating follow-on document.
    Regards,
    Masa

  • Shopping cart in status awaiting for approval

    HI ,
    Scenario is
    case 1     SC is created and ordered, but status is having awaiting for approval.
                    when we did dummy changes in SC and ordered, then we got approved stattus.
    my problem why in first case work flow is not started .
    Appreciate your efforts and will be rewared.
    Regards
    Ramakrishnaiah Y

    Hi,
    When you ordered the cart first, did you check if a workflow was started?
    BBP_PD -> SWI6
    If a workflow was started then expand the workflow in the technical workflow log to see if there are any errors in the log.
    If the workflow was not started then check with the start conditions to see if they match the first cart cart. Refer to note 322526 for other checks to carry out.
    Which release are you using?
    Kind regards,
    Siobhan

  • PO created but Status showing as Awaiting for approval in extended classic

    Hi Experts,
    SRM 5.0 extended classic scenario,SC approved and PO created but status showing in follow on documents node in SC as awiting for approval.
    Can any help in finding solution.Thanks in advance.
    Thanks,
    Babu

    Hi Babu,
    I am facing the same issue in the ECS SRM 5.0 after approving the shopping cart the PO created in EBP but the WF status is waiting and PO is not transmitted to R/3. Below is the status of SC and PO in BB_PD. Kindly suggest what could  be the problem where i can analyze.
    SC
                        Status         Description                    Inactiv
    HEADER     I1015          Awaiting Approval              X
    HEADER     I1021          Created
    HEADER     I1038          Complete
    HEADER     I1106          Shopping cart ordered
    HEADER     I1129          Approved
    0000000001 I1111          Item in Transfer Process       X
    0000000001 I1113          Follow-on Document Created
    0000000002 I1111          Item in Transfer Process       X
    0000000002 I1113          Follow-on Document Created
    PO
    Stats:
               Status         Description                    Inactiv
    HEADER     I1015          Awaiting Approval
    HEADER     I1021          Created
    HEADER     I1038          Complete
    HEADER     I1180          Document Completed
    Thanks,
    Kannan B

  • Shopping cart's One step approval workflow activation

    Hi Gurus,
    Please reply me for, how to create a shopping cart with One step approval workflow activation?
    regards,
    George.

    Hi George,
    The creation of the SC stays the same. Only the event linkage and the start conditions determine which workflow will be started.
    Regards,
    Martin

  • Confirmation ending in Awaiting for Approval Status

    Hi Experts,
    The Confirmation of Goods receipt was working fine till last month. Now For some PO's Confirmation is going to Awaiting for Approval status this is happening only for few PO's and for others PO's Confirmation is happening properly and the status is Posted in Backed.
    I observed that Workitem ID is not created for those confirmation's which are in Awaiting for Approval Status. 
    Please help me resolve this issue.
    Any valuable inputs are Appreciated.
    Thanks and Regards,
    Devananda A J

    Hi,
      First point if you make a GR confirmation means the PO change version will be generated and the PO  workflow will restart for the PO change version.
      Goto BBP_PD  and enter PO number check the PO change version is closed or not. If it is not closed then PO change version workflow will be in Error. If it is in Error then GR confirmation workitem will not be genrated.
    all these things will happen because of if you create a GR confirmation or any changes made to PO when the PO status is still in Transfer status.
    regards,
    Devi

  • After Rejected still Status 'Awaiting for approval'..

    Hello Friends,
      I am in SRM 5 and SP07..
      After SC has been rejected.. The status shows awaiting for approval but inside when i click on the item the status shows 'Rejected'.. And the workitem is not come to back to requestor inbox inside of that the next level approver pull out from the list and error message through as 'Approval step without ad-hoc capability.no preview possible'..
      I am using n-step Badi with WS14000133..
      and also i checked in SWI2_FREQ with TS10407972.. in the Agent 'No agent Available' but i can see the created_by cointainer has got filled with 'USJOHN'.
    please give your thoughts..
    Thanks,
    John.

    Hello,
    We had also faced this problem.
    You need to raise an OSS.
    but we were on 4.0.SP08
    surprised for 5.0SP07 this problem is continued
    you will get a note from SAP to apply
    the note which we got may not be applicable to you
    BR
    Dinesh
    <b>Reward if helps</b>

  • Microsoft Forefront Server Protection for Exchange Registration Service does not start automatically

    Hello,
    I am having an issue when I start my TMG 2010 machine:
    (*TMG 2010 + Forefront protection for Exchange + Exchange Edge server role, acting like a SMTP relay and Antispam filter)
    The service "Microsoft Forefront Server Protection for Exchange Registration Service"
    does not start, it is set to "Manual".
    I tried to find some information about which services should be started and which should not, but I cannot find such information, not even in Technet (my fault probably).
    Thanks in advance.
    Luis Olías Técnico/Admon Sistemas . Sevilla (España - Spain)

    Hi,
    Have you received any errors in event logs when
    you started the Microsoft Forefront Server Protection for Exchange Registration Service?
    Based on my research,
    Microsoft Forefront Server Protection Controller service is a dependency of the Microsoft Forefront Server Protection Registration service and the Microsoft Forefront
    Server Protection Registration service is a dependency of the Microsoft Exchange Transport service.
    The Microsoft Forefront Server Protection Registration service normally only runs for a brief time (less than a minute) when FPE initializes. It then shuts
    down and does not need to be running for transport scanning to occur.
    You can refer to the link below:
    Services
    Best regards,
    Susie

  • System keeps looking for a 'server' that does not exist. Is says the old name of my Airport Extreme. Clicking it away (4x) it gets through.

    System keeps looking for a 'server' that does not exist. Is says the old name of my Airport Extreme. Clicking it away (4x) finally  gets through.

    Other weirdness to report: my neighbor upstairs appears to have a Linksys router network on channel 6. My AEBS is on channel 1 so there shouldn't be interference... but according to iStumbler sometimes the signal leaps to 64000 (keep in mind my own Airport never tops 60)! Is that potentially the problem?
    Might it be possible that your neighbor just acquired a 802.11n (pre-N) wireless router recently?
    802.11n effectively increases capacity by doubling the number of Wi-Fi radios and increasing the number of antennas used to push signals out of those radios. 802.11n splits a data frame into multiple pieces. It then transmits these pieces in parallel using multiple radios that are attached to multiple antennas. These antennas blast out signals from virtually the same vantage point – scattering the signals everywhere.
    You may find the following ZDNet article interesting: http://blogs.zdnet.com/Ou/?p=247
    Even if he did not, and you are on good terms, you might want to ask if he can temporarily turn off his wireless, or, at least, reduce the signal strength to see if that will help in your situation.

  • Object directory entry R3TR EVEN EVEN_BEY5RHD67LRF9UT6G9LXEZUK6 does not exist

    Hi BW Experts,
    I´m facing a Problem while releasing a Transport from Dev to Quality System. The consisty check shows the following objekt as not available:
    Object directory entry R3TR EVEN EVEN_BEY5RHD67LRF9UT6G9LXEZUK6 does not exist
    A check for the Object: R3TR EVEN showed that it is a Event Collector which seems to be missing. The transport consists a process chain which listens to an event. Is this the mentioned Object or is it related to some different topic? The process chain is correct and activated.
    Thanks in advance for your help.
    Best regards
    Christian

    Hi Abdullah,
    I followed your advice and did a check if the object was writen to my transport. The object was missing on the transport. But also searching in transport connection did not help.
    So I had a look into the table TADIR and also here I could not find the mentioned object which was realy strange to me, as the process chain was active and correct.
    I than deleted the event collector(AND) object in the process chain and created a new one. A check in the table TADIR now showed the before invisible EVEN_BEY5RHD67LRF9UT6G9LXEZUK6 and also the new one created. The new EVEN Object(and also the old deleted one) was written to the transport. Importing it into Quality System worked without any problems.
    I´m not 100% sure about this behaviour but maybe its linked to the fact that the process chain was a result from the Dataflow migration wizzard. Maybe while migrating that dataflow something went wrong.
    Anyway, thanks to all of you for your help!
    Best regards
    Christian

Maybe you are looking for

  • LPX-00601: Invalid token in: err while trying to read data from xml

    Hey , While trying to read data from xml i got err: LPX-00601: Invalid token in: 'path' the proc. i'm using to read data from the xml is: procedure read_xml_file_test (in_filename in varchar2) is my_dir  varchar2(20) := 'XML_DIR;   cur_emp2 number:=0

  • Goods Receipt  of Asset

    Dear All, In case of Asset Goods Receipt (MIGO),  I am facing following problem- 1) Capital Goods PO created . 2) At the time of MIGO, system is saving the GR, but no accounting document is generated. Here the Asset Clearing Account should get credit

  • PORT_ACCESS Configuration to accecpt inbound mail from 1 IP address

    I have a inbound mail proxy that relays imbound mail to my final destination iMS5.2 mail server, for this reason I want to block all un-autheticated inbound connections to my iMS5.2 server except for the IP address of the mail proxy(s). It seems the

  • Hnadling unit

    Hi Experts , I want to know the Handling unit cycle. Where packing proposal is created with T code. how to create handling unit. what is the importance of packing station ? is this need to be created ?? How to do GR in HU against production order. Ho

  • Thumbnails Gone

    Thumbnails have disappeared in my timeline? Any ideas what has happened?