Shortage of stock at subcontractor end

Hi all,
I have a scenario like, i have issued 100 pc to a sub-contractor vendor through 541, after count vendor said, he has only 95 pcs, my requirement is to remove that 5 qty from his stock. so what will be the entry.
Thks&Rgds,
Deepak

Hi,
You can use the TCode: MIGO_GS - Subcontracting (MIGO) for the same.
Regards
Mahesh

Similar Messages

  • Write off Stock at Subcontractor End

    Hi Experts,
    We want to write off the stock lying at stock subcontractor end in SAP thru Physical Inventory Adjustment.  No storage location is assigned to subcontractor stock in SAP. Therefore we are finding it difficult to do it thru MI01, MI04, MI07.
    Please guide how it is possible
    Regards
    ( Rajneesh Gulati )

    Why do Physical Inventory, presumably the SC is telling you, you aren't physically checking.  Why not just process a goods issue to destruction, Movement Type 551 etc., through MIGO for O stock category ?
    Cheers,
    Nick

  • How to Write Off Stock at Subcontractor's End

    Hi Friends,
    Few parts are shown at Subcontractors End in the System which has actually been consumed(returned). Now we want to remove those stock from Subcontractors stock. How can we write off those stock???
    These are very old stocks, is there any other method to consume those materials??
    Please help
    Thanks in Advance,
    Ritesh

    there are diffrent ways to reduce this stock
    either do it by mb1a move typoe 551 and spectiaop stock O
    or by physical inventory  cycle MIO1
    hope this helsp

  • STOCKS AT VENDOR END

    How to view stocks at vendor end for raw material considered under MRP process .Is it possible or if not what config needs to be

    Hi,
    For normal MRP process system will not consider the Stocks at the Vendor side.
    It will consider only the Plant stock only with all the str location.
    If you want to consider the vendor stock for MRP process then the only possiblity is through MRP Areas. You need to consider the subcontractor as MRP areas then when you run the MRP for MRP areas then system will consider the Stock at the vendor end & can be checked in the MRP reports.
    rgds
    gsc

  • Print out of Schedule Lines & Material reqt at subcontractor end.

    Hi experts,
    Presently we are using ME9E report for taking print out of scheduling agreement.  In scheduling agreement, material wise / date wise R.M requirement at Subcontractor end is displayed as well as schedule lines material wise / date wise is displayed. 
    We do not find it user friendly.  We are searching for following reports :
    1. Datewise / Material wise requirement of R.M at subcontractor end should be displayed separately.
    2. Schedule line qty date wise / material wise  should be displayed separately.
    Solutions / Suggestions will be highly appreciated.
    Regards,
    ( Rajneesh Gulati )

    hi,
    pl go with Y program

  • Transfer of material from sales order stock to subcontractor

    Iam having subcontracting operation in routing. But i am not able to transfer of material from sales order stock to subcontractor when i do 541 movement

    Dear Mayuresh,
    You cannot move Sales Order assigned material directly to Sub contracting Vendor stock.
    For doing so firstly unassign the Sales order stock by transaction MB1B & movement type 411E.
    After this you can provide the stock to the vendor by transaction MB1B & movement type 541O.
    Other way is to create account assigned Purchase Orders. Thereafter create virtual sub contractor storage location in your plant. Transfer your Sales Order assigned material to these Virtual locations so that you can see the stock provided to the vendor. Now during Goods Receipt of the finished goods you can consume the material by movement type 543E.
    Regards,
    Subha.

  • Referring Sales order no while issue stock to subcontractor

    Hi All,
    My client want to refer sales order while issuing stock to sub contractor.
    Scenario is like this, he procure all the materials based on the Sales order only.
    Now in sub contracting po he want to use Account assignment category C and item category L. And once the po is completed he want to provide stock to subcontractor using this sales order only.
    Please go thru the issue once and let me know the possiblities.
    Revert back in case not understand the issue.
    Reg,
    Ashok

    hi
    u can do this scenario
    u have to maintain combination of C& L
    then go to omjjj and in 541 movement in field selection (201),
    in additional acct assignment make sales order field mandatory ,so system will ask u for sales order in MB1A
    also in field selection enjoy add field KDAUF which is for sales order  ,so system will ask u for sales order in MIGO
    steps
    create po with C&L
    issue goods to sc (system will ask u for sales order ref
    and further normal subcon cycle
    just try it , i haven`t try it
    reward if helpful
    regrds
    kunal

  • Transfer Stock to subcontractor with reference of Sales order

    Hi,
    Scenario:
    MTO strategy
    We have one operation is subcontracting. When we take MRP run all PurReq. & PLOrd are reference to sales order. But  when we want to transfer material to subcontractor through TCode MB1B Mvt type 541 that time system issue the following message.
    Deficit of SL Unrestricted-use 3,150 KG : 119 1002 RM
    Then we have to transfer stock reserved against sale order to unrestricted.
    Requirement:
    Can we transfer stock to subcontractor with reference to sales order.
    Pl tell me how I resolved this issue.
    Thanks & Regards
    Dhamane

    Hello....
    You can not transfer material from Sales order Stock by movement type 541 as both stocks are Special stocks &  has not recommend to transfer between two special stocks.
    For this Solution ,  Transfer posting to transfer the provided components to a new storage location (for example, 9999) by using movement type 311. This enables you to obtain an overview of those stocks that are physically located at the subcontractor. This information is particularly important when you carry out a physical inventory of the sales order stocks.
    Rajiv

  • Withdraw material from blocked stock at subcontractor

    Hi
    We have Third Party Order process where in materials are directly received to subcontracting vendor stock, when Goods receipt is posted in receving plant.
    Due to some error, few stocks have been posted to Blocked stock at Subcontractor.
    We would like to transfer the stock to unrestricted stock / scrap the stock from Subcontractor blocked stock.
    Kindly let me know your opinion to make transfer posting.
    Thanks and Regards
    Rajkumar

    Dear Yadav,
    1.
    Firste you wrote:
    Due to some error, few stocks have been posted to Blocked stock at Subcontractor.
    After that you stated this
    It is about restricted stock at subcontractor.
    2.
    And materials are not subjected to batch management. So we cannot use MSC2N.
    So, your first statement was that the material is in "blocked" stock, after that you stated that it is in restricted-use stock. But you also stated that the material is not batch managed.
    "Restricted-use" is the status of the batch, so your material should be batch managed if its status is restricted-use.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/a5/63396b43a211d189410000e829fbbd/frameset.htm
    As I wrote you can use MB1A +553O if your material is in QI stock, if it is in restricted use you can't. If it is in restricted-use, please use MSC2N to change its status to unrestricted and after that comes MB1A + 551O.
    What is the real stock type the stock you are speaking? Who "posted" it to that stock type and how?
    Please give EXACT information.
    Thanks,
    Csaba
    Edited by: Csaba Szommer on Feb 10, 2009 10:50 AM

  • Removal of stock from subcontractor place

    Dear Team,
    I have issued the excess child material quantity to subcontractor. Now the job is completed. GRN is done.
    Now i want to remove this excess stock from subcontractor place and put it in my stock.
    Whta are all the steps required.
    Thanks & reagards,
    R.Saravanan

    hi,
    You can do the consumption posting using 542 mvt type from MIGO...
    You post the GR form 101...
    and later pay to vendor for this consumption...
    Regards
    Priyanka.P

  • Transferring stock at subcontractor location to APO

    Hi ,
    We have a subcontracting scenario in R/3 . The component material is supplied to the subcontractor who manufactures the FG and sends it back to our plant . The component material is SNP planned. We want the stock of the component at subcontracting vendor(MatSub) also to be taken into consideration when the the component is planned in SNP. We have enabled the option stock at subcontractor location (forgot the exact description ) in R/3. But the stock is not getting transferred. we are currently running CCR in aPO to pust the subcontractor location stock to APO.
    Am i missing some setting . Kindly help .

    When the "vendor spec stock" option is enabled in the stock IM the stock at subcontractor location does get transferred to APO. In my test system i think there was some other data issue. But it worked in production
    Thanks
    Saradha

  • Stock Pegging Report for Vendor Stock in Subcontractor scenario

    Hello all,
    As we know, CTM pegs the component inventory available with subcontractor when the parent FG demand drops in. Now, my requirement is can we extract a report that can give the details of all demands that are pegged to the stock?
    1. This report should be run in batch after CTM such that it extracts a snapshot of all demands pegged to inventory of components under "vendor stock".
    2. This report will give a clear picture to the supply planners about the inventory that is not pegged any demands and can take appropriate action as necessary if there are demands directly for the components.
    3. The report should be available in a tabular form listing each of the coomponent materail and the quantity that is pegged and quantity that is not pegged.
    If any of you have worked on generating such report earlier or have any ideas to extract such a report, it will be highly appreciated. If my question is not clear and needs further explanation, please let me know. I can describe with examples and numbers.
    Thanks,
    Chandra

    Hi Chandra,
    The closest report in terms of various building blocks (table, structure, FMs etc.) is /SAPAPO/DM_PEGKEY_REORG.
    The inspiration can be taken from this report and a new report with ALV Grid can be bulit.
    Thanks and Best Regards, Manoj

  • Opening stock with subcontractors

    Hello Experts,
    I am doing a report on Opening and closing stock with the subcontractors...
    My report's requirement is..
    Mat. No.   -   ekpo-matnr
    Part No.   -    resb-matnr
    Opeining stock (for Resb-matnr)     -         ( movement type 541542543+544 from Mseg)
    Please advice me how to calculate opening stock for the Parts as  ekpo-matnr is linked to ekbe-budat
    and I have to take the opening stock by linking mkpf-budat. And for single material (ekpo-matnr)
    there will be multiple part no (resb-matnr) and I want the openinig stock for each part no.
    Please advice...your help would be highly appreciable.
    Thanks
    R.Karthik.
    Edited by: Karthik R on Feb 17, 2009 4:38 AM
    Edited by: Karthik R on Feb 17, 2009 4:39 AM

    Hi,
    I want to multiply finished good menge with raw material menge , both the menge are from different
    tables.
    eg - A pen is finished good and  its raw materials are top , refill etc.
    Matnr  (finished goods)  =  Pen  ,  Menge =  2 and its corresponding raw materials are:
    Raw mat1 - its Menge is  5
    Raw mat2 - its Menge is  3
    Raw mat3 - its Menge is  2.
    Now I have to multiply these whole raw mat menge with finished goods menge ie 2.
    But when I tried only the first line ie Raw mat1 is getting caluclated.
    Please advice.

  • Negative stock at vendor end location

    Hi all,
        Today I found a material showing negative stock in a vendor end location.
       Negative stock indicator flag is not  set for that material and negative stock setting also haven't made.
    The movement that led to negative stock is 543 O.
    I dont know how to solve this problem.
    Kindly advise me in this regard.
    Regards,
    Viswanath babu

    Apparently negetive stock is allowed at this location. It is a setting in config. If you know the material document that caused it(use MB51), reverse that document using MIGO or MBST. As far as the setting is concerned, you need someone to change the setting if it should not be allowed.
    Srinivas

  • HELP - MRP and Stock in subcontractor!

    Hello SAP gurus,
    I have a little problem with MRP and the stock in the subcontractor.
    This is the scenario:
    PLANT..........MRP ELEMENT..........QUANTITY
    2100.............Free Stock..................500UN
    2100.............Reser..........................700UN
    2100.............PurRqs........................200UN
    And I the stock in the subcontractor for the same material is 300UN...
    Why is MRP creating a PurRqs instead of a stock transfer from subcontractor.
    The Scope of check is considering subcontractor stock...
    Can you please help me?
    Thanks in advance,
    Adelmo Silva

    Hi,
    As i Know MRP will  not Consider , the Stock Available at Subcontractor. During the Net requirement calculation it will consider teh stock available at Plant. That is why it would have created PR.
    During material Availabilty check it will consider as per settings at Scope of the Check.
    One more Option is MRP area for the subcontractor , for More details please refer below SAP help.
    [MRP area for the subcontractor |http://help.sap.com/saphelp_47x200/helpdata/en/2f/690bc4068811d2a6c80000e83235d4/content.htm]