Simoultaneous planned delivery time (MRP)

Dear Experts,
I would like to set my MRP for material purchases in order that I can have 2 different lead times, depending on the route (air/sea)
For instance, if MRP can supply enough material with 1kg or less, then it should take a shorter lead time for it would be air freight than if the minimum necessary was more than 1 kg. (Actual freight lead times= air 60 days, sea 90 days)
Best regards
Marco Aramini

Hello Marco
It is possible to have different lead times for different vendors on MRP.
On the customizing transaction OPPQ, choose the option "external procurement" and make sure that the flag "scheduling: info rec agreement" is set.
With this setting, the planned delivery time is read from the info record or from the scheduling agreement.
After that, you should create a quota arrangement for both vendors (see note 1508647 for details).
On the quota arrangement, you can use the minimum and maximum size to define that the source will only be selected if the lot size is higher than 1KG or smaller than 1 kg.
If have a more complex logic to select the vendor, you can use BAdI MD_MODIFY_SOURCE.
BR
Caetano

Similar Messages

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • MRP - Planned Delivery Time as 'Number of workdays' - How ?

    Hi All,
    We want to use 'Planned Delivery Time'(PDT) as 'Number of workdays' rather than 'Number of calendar days' while running MRP (Single item, multi level) from MD02 AND eventually that would be reflected in 'Availability date' in MD04. Can we achieve this by config or we need to search a proper user exit / BADI / enhancement spot for this ? Any suggestion on this is most welcome.
    Note - Factory Calendar ID has been maintained properly with Mon - Fri as working days.
    Thanks,
    Ashok

    Hi Csaba,
    Thanks for your input. The link you have provided does give information on how to assign the factory calender at plant level. However it doesn't answer to my question of how to use 'Planned Delivery Time' as 'Number of workdays'  rather than 'Number of Calender days' .
    My concern is 'Is it possible achieving this ? If YES, How ? By using config OR by any enhancement spots / User exits ?'
    Any suggestion is welcome.
    Thanks,
    Ashok

  • Consider planned delivery time field in MRP Areas

    Hi,
    I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
    Regards,
    Chester

    Hello Chester
    If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
    Also, the report RMMDDIBE can be used for mass processing of MRP areas.
    BR
    Caetano

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned delivery time issue

    Hello Experts,
    We have below requirement.
    Created sales order for a particular material. Planned delivery time is picked from info record for that material and PR has been created.
    We are converting PR into PO and the planned delivery time is fine. Now we are updating the ASN from vendor with some prior dates. In MD04, the same got updated. However the sales order still shows the old planned delivery time only. How to get the new planned delivery time  in the sales order based on the ASN updated in PO.
    Example:
    Material: A
    Planned delivery time is 10 in info record
    Created sales order. Planned delivery time in the sales order is 10. PR created with fixed vendor and planned delivery time is 10 days from the date of creation.
    Converted PO.
    Now we received the ASN from Vendor that the vendor will deliver this material in five days. So accordingly we are updating the ASN in PO with delivery date.
    In MD04, we could the new planned delivery time based on the ASN. However sales order delivery still shows the previouls delivery date only.
    How to get the new delivery date in the sales order based on the ASN update?
    Regards
    Bala

    This is not standard SAP logic. Required delivery date on the original line item stays as it was when you issued the order. Then you create a confirmation (ASN) that is relevant to MRP with the updated delivery date. Planning sees the new date and acts accordingly, and also in the order you can see both "old" and "new" (in the confirmation tab).

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • Planned delivery time & GR Processing time

    Hi all,
      I would require a clarification on this one,
    Scenario - After an MRP run, the Purchase Requisitions for materials are generated & the order release date is being calculated by subtracting only the planned delivery time from the requirement date. But to the best of my knowledge
    "Purchase Order release date = Requirement date - (Planned delivery date + GR Processing time)"
    Solution required - Is my understanding correct & if so, where should i make the changes to include the GR processing time for the computation of order release date. Is there any other field which i need to add to my PO release date computation. An early response in this regard would be highly appreciated.
    Regards,
    Vivek

    Hi,
    The order release date simply takes the requirement date and subtracts the planned delivery period (as you have indicated).
    But this has ALREADY taken the GRP time into account and so you don't nedd to (and shouldn't) add it in again.
    For example,
    Material A has a Planned delivery period of 10 days and a GRP time of 3 Days. The date that the production order is to be started is 30 July.
    The MRP run sees the requirement date as 30 July but it also sees the 3 days GRP and so it asks for the item to be delivered 3 days prior to this date (27th July).
    The planned delivery period is 10 days and so the PO will need to be created by the 17th July. 
    So the dates are correct and do not need any further changes.
    If you were to take the GRP time off again this would be wrong.
    Steve B

  • Regarding planned delivery time for Subcontracting process

    1.Factory calender is maintained  and assigned to the plant,SUNDAY is
    not working day for Client,so the system is not planning any internal
    activities for SUNDAY,up to here it is fine.
    2.One semi finished material is produced by vendor.i.e.Sub contracting
    process, it takes 2 days to complete.For vendor SUNDAY is not a
    working day.
    3.Planned delivery time is maintained as 2 days ,so that if PO is
    release on MONDAY ,the delivery date on WEDNESDAY.
    4.If  requirement is on MONDAY ,In MRP Run System is generating the
    release date on SATURDAY and delivery date on MONDAY,here system is
    taking the calender days not the factory calender days,Client is
    asking for correct delivery date.
    5.Is there any way to tell the system that SUNDAY is not working day
    for vendor,so that system will generate the release date on FRIDAY
    and delivery date on MONDAY.
    Please give your valuable inputs.

    Hi
    the following link might help you in setting the planned delivery time in your defined calendar, rather than the general calendar days.
    SAP ERP Manufacturing - Production Planning (SAP PP)

  • Planned delivery time field in sale order

    Dear All,
    During creation of  STO at item level under delivery TAB "planned delivery time" field is showing with edit mode, I want to activate this field for sale order creation / change also. Plz advice how I can do this.
    regards,
    sps.

    Dear SP
    This field is laready there in the MRP-2 of the material master. This is used to calculate the no. of days to procure a material/service externally. Why do you want to activate this in sales order.
    Thanks
    Shuktiz