Simulation version WBS element

Good morning,
We need to load for the 0WBS element,  the simulation version (PS
version , not CO version).
Could you help me?
Thank you

Hi,
check out this sap help...
http://help.sap.com/saphelp_nw04/helpdata/en/b4/60073c0057f057e10000000a114084/frameset.htm
CJ40 - Project Cost Planning By project and wbs

Similar Messages

  • CJV4, WBS simulation version cost in COSS and COSP by cost element

    Hi PS expert.  (-:
    IN PS When we freeze a simulation version with CJV4,  (operative data to version), sap will create new object number in table VSCAUFV_CN for each network and VSPRPS_CN for each Wbs element related to the simulation Version.
    In our environment, SAP will add record in COSS and COSP for the new object number for Network but NOT FOR THE WBS.
    Is it standard to NOT record the cost in COSS and COSP for the simulation cost of the WBS (against the new object number?)
    That mean we will able to see the simulation cost by cost element for network, but NOT FOR WBS element.
    For the WBS, we only record the cost in RPSCO by cost category.
    Is there a way to active (with an exit ..classu2026bapi) the recording of the cost of the WBS by simulation version in COSS and COSP
    Thanks you very much for your help
    Sophie

    hi sophie,
    create separate network for each wbs in project.  see if this can solve your issue.
    vengaiah chowdary

  • WBS element field to Depreciation Simulation Report  output display

    Hi SAP Experts,
    We need to Add the WBS element field to Depreciation Simulation Report  output display (S_ALR_87012936)
    Could please give your valuable inputs
    Thanks
    Hari Pothula

    HI Javed,
    We have capitalized with WBS element but not displaying in simulation report.
    All configurations done in in ACSET and activation Account assignment objects
    Thanks
    Hari

  • WBS Element Version Released Already Exists

    Dear All,
    When we create a Project by copying another Project, we get the error message " WBS Element Version Already Exists. Help.
    Regards,
    Shareeq

    Hi,
    When you are copying project from template then you need to select WBS triangle instead of green tick.
    You will enter in the screen wherein you need to replace std WBS with the one which is to be adopted. Then select check and include so that for every activity , WBS element you will find your given nomenclature.
    Try this and revert.
    Regards
    Keshav

  • Simulation version Error - Message no. C2323

    Dear Experts,
    I'm trying to create simulation version from operative project.
    I'm getting the following error even though I have maintained settlement rule.
    Settlement rule contains errors and has not been saved
    Message no. C2323
    Diagnosis
    You use a strategy and/or default rule to automatically determine settlement rules for orders/networks.
    The system has determined a settlement rule for NWA #46 according to the defined strategy and/or default rule. However, when checking this settlement rule, an error appeared.
    This error may occur, for example, when you want to create a settlement rule for the superior WBS element, because due to a user status on the WBS element, this is not allowed.
    System Response
    The settlement rule is not saved due to the error.
    Procedure
    Maintain the settlement rule manually for NWA #46, and check the strategy and/or default rule used.
    Please help.
    Regards,
    VINOD.V

    below is the settlement strategy parameter for network
    Manual maintenance of settlement rule
    1   Automatic generation of settlement rule
    2   Generate settlement to WBS element
    3   Copy settlement rule of the WBS element
    4   Copy settlement rule of the project definition
    5   No settlement rule
    then assign strategy to PSP/PS1
    assign network settlement profile to network type as zps1,2,3,4&5
    so just configure the strategy according to suitability then run simulation.
    Regards,
    Sanjeev

  • Creat simulation version

    Dear All
        when i try to creat sim version in cjv4 i get error massage (Results analysis key 000001 not intended for determining capitalization values) pl gave solution on this.
    Regards
    Prathamesh

    Try carrying out the settlement first (if you are using Investement profile - AUC settlement) and then create the simulation version.
    If not, delete the investment profile on the WBS elements and create the simulation version.
    Regards
    Sreenivas

  • Project Simulation Version

    Hi,
    Is there any Function Module or BAPI to extract all details of PRoject Definitions and WBS element and Network Activities for Project simulation Version/Version key.
    Thanks
    Ramesh

    Hi,
    Both options, as in DP81 we are able to select simulations versions.
    But onces the quotations has been created we can't know the source. we know the project as is informed in the account assignment but not the simulation version we have used.
    Has anybody faced this issue before?

  • PS report: wbs element relation with PO, Pur Req. and vendor

    Hello,
    I need to build a report on WBS element which also shows PO number, Pur. Requisition, vendor details along with budget, actual, committements.
    I found datasources that can provide informations except PO, Pur Req.
    Can anyone help in providing a soln to build a relation between wbs and vendor to bring the correct PO and pur req related to wbs.
    Thanks
    Anima

    Hi Sushil,
    Which version of BW are you using?
    If its BW 7, then look at the datasource 2LIS_02_ACC
    http://help.sap.com/saphelp_nw04s/helpdata/en/ed/62073c44564d59e10000000a114084/frameset.htm
    Hope this help you
    Anima

  • Planning on WBS elements without cost elements

    Hi all,
    we are trying to implement the planning solution where users will be able to plan on individual WBS elements monthly but without providing a breakdown on cost elements. Standard SAP planning profiles allow to post plan values on WBS elements in annual view without cost elements. But when you want a monthly view the system you need to click on primary cost elements planning first.
    Is there any way to plan monthly but at cost object (WBS) level only?
    Many thanks,
    Roman

    Hi Eli,
    thanks for your response. We will be using budget functionality for budget purposes but at the same time we will need to use planning on different versions. I believe there are no versions for budget.
    One of the idea to minimize cost element planning is to introduce like a planning cost element to use with all planning postings and then include this into the same cost element group with the rest of cost elements for plan/actuals comparison reports.
    If you have something in your mind I would appreciate your input.
    Thank you,
    Roman

  • Exchange rate diff. influencing the available cost of WBS-element

    Hi all,
    here is a intricate problem I need help to solve. I am not so very experienced withon CO/PS, my main competence is within PM. This issue involves PM/MM/PS and CO so I am not sure if this is the correct group to post to, but I give it a try..
    In PM (Plant Maintenance) workorders the u201DPlanned Costu201D is calculated.  Exchange rate type for the u201DPlanned costu201D is picked from the CO Cost Version u201D0u201D that uses exchange rate type u201DPu201D. This is a exchange rate type that have one yearly fixed exchange rate. The actual costs are posted with exchange rate type M, which is daily updated.
    The Planned cost in the workorder is a part of the u201DAssigned Costu201D that are influencing the available budget on the WBS-element. u201DRemaining/Residual order planu201D.
    In cases where the PRQ/PO are created in other currency than the Company code currency we have a problem:
    The difference in exchange rate are causing the u201DAvailable budgetu201D to be too low u2013 and the only workaround I have found is to decrease the planned cost in the WO to release the available cost for the Budget. (make the available cost higher )
    Does anyone have an idea how to solve this?
    - I have thought of setting the exchange rate type for the planned cost to be the same as for the actual costs u2013 but it is not recommended to change the exchange rate type in CO for cost version u201D0u201D and not a good ide to change the exchange rate type for actual cost eather. This will also not solve the problem of exchange rate difference caused by PRQ/PO beeing created for a whole year for varying exchange rates.
    - Is there a way to exclude the u201D Remaining/Residual order planu201D from the u201DAssigned Costu201D? And what consequences will this have? Only cost from PRQ/PO will appear? (Since internal material (reservations) and internal hours not triggers a PRQ/PO)? I see there is a transaction CJE5 where you can exclude the u201D Remaining/Residual order planu201D from the u201DAssigned costu201D u2013 but I think this will only exclude it from beeing shown in the report S_ALR_87013558?- not from the calculation of available cost at the WBS-element?  which is what I need. (see Note 668240)
    -Is there any u201DExchange rate differenceu201D setting in the customizing u2013 how exchange rate difference are treated for PM orders? And will this help my problem?
    Best regards
    Ellen

    Hi ,
    try this way...
    Go to T-code>CJE0>Enter CO Area-->and execute the report 12KST1A  ->in the selection screen -->
    go to menu -->system -->status check the program name and ...copy
    next go to se38 and copy yhe above program name and execute and use submit report with selections,,,,
    Prabhudsa

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • WBS elements deletion

    I deleted some of the WBS elements a week ago.
    Now I still see them under the search list,
    Is it because they are marked for deletion and not deleted actually,
    If yes what should I do to remove them.
    Please reply.

    Hi Ramesh,
    The scene is like this.
    End users created WBS elements starting with H.****
    Then after I assigned project code H for tht co.code.
    after applying project coding mask [OPSJ] those WBS elements automatically got deleted, I m not sure if they are deleted or not but when i go to CJ02 and enter that WBS it says it does not exists. but it still shows those WBS elements under ths search criteria.
    I reffered to OSS notes as per it they have corrected this problem in version I am using.
    Please guide if you have any idea.
    MIlind

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • Search help for WBS element on timesheet

    Hi,
    We are using EA-HR 6.00 (webdynpro)
    Is it possible to change the search help for the WBS Element field that appears on the Record Working Time timesheet?
    There appears to be a table called TCATS_SHLP_ITS, but is this not for the old ITS version and not the new webdynpro version?
    The client would like to use a different search help when they choose the dropdown on the timesheet but I can't seem to figure out if this is possible.
    Thanks.

    I guess I'll retract my question, as making change to table TCATS_SHLP_ITS is making a difference on my WBS element dropdown... just need to get it to work properly now.

Maybe you are looking for

  • Trackpad in bootcamp doesn't work all the time

    Hi, so I just bought a brand new MacBook Pro because out of my own stupidity, I destroyed my old one. I decided when I got the new one, that I would BootCamp it and run Windows 7 on a partition. I've been pretty happy with it so far, but occasionally

  • ADF Export to Excel functionality from multiple tables

    Hi, I am using jDeveloper 11.1.2.3.0. We have a ADF page which has three tables inside a panel group layout. How may I export the data from all tables into a single excel ? Do I need to use any specific layout types to achieve this ? Thanks, Ashwin

  • Flex builder sucks

    flex builder sucks big time. it take more than 250 mb ram even without any projects loaded and help open. in work mode it takes more than 450 mb. which is riduculus. also its auto complete doesnt work properly. it vanishes most of the time without re

  • Using your personal domain name in .Mac/iWeb?

    Hi people, just a question about using my personal domain name which I have from UKreg. Anyone know how to use this in iWeb? I have looked at a few sites explaining it, but looks like a hard task! Thanks : )

  • Enterprise Portal Implementation - Cost wise.

    Hi Experts, Had a few questions/doubts in my mind regarding the costing side of implementation of Enterprise portal. If i take an example that an Enterprise has SAP ECC 6.0 implemented, and would need to implement ESS/MSS packages !!! Can someone ple