Please help me understand system behavior for a single cycle count plan.
Say I have it set up with an annual estimate of 52,000 and PM to be done weekly, ie a count of every 1000. Shift factors set to 100% and call horizon 0%. I initialize my counter at 100,000. When I schedule my first order, it is set a week out for 6/5 for projected counter reading 101,000. So far so good.
Now technician decides to do the PM work a week early. He confirms the work order today (5/29), and a counter reading of 100,500 is entered. The system responds by scheduling a new order for 6/2 and keeps next projected counter reading at 101,000.
Questions:
1) Why is the next counter reading kept at 101,000 instead of 101,500? Say a bicycle chain needs to be greased every 1000 revolutions of the chain. If I grease the chain after only 500 revolutions, why would the system not schedule the next greasing 1000 revolutions out? (And is there a setting to enable this?!)
2) Why did system pull in the next work order a few days early to 6/2? If I have consumed my 52,000 annual estimate at an accelerated rate, shouldn't all subsequent orders be stretched out (still 52 weeks, divided by 51,500)? (
Thanks,
Vlad

687 comes by summing up current reading (123) with Cycle frequency (564).
From Current reading 123 to reach 687, it will take 7 days (564 / 80), System considers the date of 16/06/2014 to calculate 23/06/2014.
Whenever you change the Maintenance Plan scheduling parameters or Cycle frequency, Maintenance plan should be restarted to generate the new schedule lines.
And, by changing some data in existing plan & based on system response, we can't predict the system calculation. We can give you the suggestions on how all the parameters should be maintained in Maintenance plan & Measuring Point (in case of Performance based plan) to generate the order in specific way.
As we can't make replica exactly what you made, it will be never possible to give proper advice on system behavior.
If you want to see the calculation behind date calculation, select the particular row in IP10 & click "Calculator" button. There you can see the calculation.
Measurement document should be created while doing TECO of PM order. In TECO pop up, you can find the button as "Create Measurement document".
Refer this blog which has been created by considering your scenario.
Behavior of Performance Based Plan in SAP Plant Maintenance

Similar Messages

  • Cycle Count Scheduling in 11.5.9

    Running a cycle count by period. Cycle count was established to start on 27-Aug-07. Created the Perform full cycle count (Report Set) which runs every month...however in September the auto schedule in the cycle count form has the next date as 24-Sep-07 yet the report set which is set to run monthly will run on the 27-Sep-07...and this disconnect will continue month after month. Did I miss something obvious in set up or is there no way to have the report set in synch with auto schedule on the cycle count?
    Thanks in advance.

    You are not connected to the user that started the database. Please verify the owner of the database processes. You can use the ipcs utility if on linux/unix to verify the owner. Please also verify the owner and permissions of the 'oracle' binary under the RDBMS Oracle Home bin directory to verify that it has the proper owner and permissions. This file should have the suid bit set in its permissions and must be owned by the proper group as well. It should appear something similar to this:
    -rwsr-s--x 1 orahelp dba 96735691 Jun 17 2009 oracle
    You can find the proper group by examining the 'config.c' file under the RDBMS Oracle Home rdbms/lib directory. It should look as follows:
    /* $Header: config_ux.c 115.1 2004/03/27 07:17:12 hfux ship $ */
    /* SS_DBA_GRP defines the UNIX group ID for sqldba adminstrative access. */
    /* Refer to the Installation and User's Guide for further information. */
    #define SS_DBA_GRP "dba"
    #define SS_OPER_GRP "dba"
    char *ss_dba_grp[] = {SS_DBA_GRP, SS_OPER_GRP};

  • Perform Full Cycle Count - No Data Found

    I am trying to initialize a full cycle count for all items in a subinventory. I have a recent ABC compile set and a new cycle count setup. A, B, C and D classes are all set to count 1x per year. I have verified that all items from the compile are no in the cycle count. I submitted a "Cycle Count Scheduler" request and ensured that it completed. I then set all the parameters in the "Perform Full Cycle Count" request and set to save to file. After it completes and I view the output, the file says "No data found". My only recourse is to dump all items from Material workbench and use Data Load to enter them in ( a bit tedious for 900+ items). Is there anything I need to be doing different?

    You mention that you have done the ABC setups.
    But in Cycle count setups, have you defined a cycle count schedule?
    And more importantly, in cycle count classes, have you entered the frequency at which each class should be counted?
    Last but not the least, what is the last count date (on the serial and schedule tab)?
    If it is today, you will have to wait till tomorrow.
    Hope this helps,
    Sandeep Gandhi

  • Duplicate Items in Cycle Count

    Hello -
    I am new to setting up Cycle Counts.
    We have a count that is weekly and it is generating the same count for week 2 as it did for week 1 for all subinventories.
    It is setup with a yearly calendar defining the weeks.
    It is setup for the Org on the 1st of the month.
    It is setup on a scheduler as weekly.
    Once it is setup - we run the Cycle Count Scheduler and then run the Generate Count Requests.
    Generally the team at the subinventory location will run the weekly counts a few days prior to the due date In this case. run the count for 4/1-4/7 for their subinventory location and then do the count and enter by the 8th.
    When they ran their counts on 4/9 and and 4/10 for 4/8-4/14 - the same items (new tag numbers) printed for each subinventory location.
    We did find that someone in another location reran the Generate Count Requests on 4/8.
    Did this maybe cause the count to restart and duplicate week 1 data as week 2 data?
    Thanks for any suggestions or assistance.
    SC

    How do I ask a question on the forums?
    SQL and PL/SQL FAQ

  • Single cycle plan with counter in plant maintenance

    Dear Experts,
    I am creating single cycle plant with performance based with couter reading.
    1 I have crated a measuring point with counter in running hrs
    2 Created a single cycle plan and given the couter no. there
    3 Since i hv given 4000 hrs in plan, as soon as i update the document there should be a notification but it is not happening
    Can any one clarify the issue
    Thanks&Regards
    N.Chandrasekhar

    Dear thyagarajan,
    1 I hv created meas point with counter with specified equip
    2 made document for that of 10 hrs
    3 Created a  single cycle plan giving reference same equip Cycly given 250 hrs, Entered the counter no there, call horizon 100, schedule 365 days.... while saving given no to save.....while scheduling IP10,
    taken the counter ducument which i 1st saved 10 hrs... thn called 1st call and released and saved.
    4. here with out entering that 250 hrs in ducument i am getting the notification............?
    5. I have to get the notification after entering 250 only..
    Why is happening like that
    Hope you have under the issue
    Regards
    N.Chandraasekhar

  • Cycle Counts - Manually schedule by From and To Locator

    We run Cycle Counts for a range of stock locators. However, when manually scheduling a Cycle Count, the only option is to enter locators one by one. So, if one subinventory has 300 stock locators and we'd like to count only 200 of them, we'd have to enter each locator. We are finding this very impractical. Hoping someone has come across this and thought of something innovative - as we can only think of using Dataload to load the locators.

    Hi,
    I think the solution for your question can be solved using the ABC compiles, ABC assignment groups. Just check the topics once.
    Regards,
    veeraiah chowdary.B

  • Manually schedulled cycle count items are not coming in cycle count listing

    We had scheduled some items for manual cycle counting for particular date. But those are not getting generated in cycle count listing report or not avialble for counting.
    Checkpoints done: 1. Items are cycle count enabled
    2. Those items are avialable in that Cycle count  Name
    3. Onhand is avialbe for those items in particular subinventory
    4. Cycle count scope is specific to Subinventory and that sub inv is included in the list
    Can anyone give some thoughts why those manually schedulelled items are still not getting in cycle count listing report?
    Thanks in Advance
    Avinash

    Hi Avinash,
    Can you please let us know, are you using the CC with ABC analysis?
    Thanks
    NS

  • Start in the current cycle in scheduling ip10

    Dear Experts,
           when i create a single cycle or strategy(ip41,ip42) maintenance plan and i put start date in the past(2010) and when i go to ip10 to make the scheduling dates it  start from 2010 but start counting for calls from 2014

    Greetings Mohamed,
    The Scheduling Period is the period the Call Dates are calculated in advance from today, and not the validity period of the Maintenance Plan. So in 2010 the dates are calculated up till 2015, but if you run IP10 or IP30 in 2014, the dates are calculated till 2019.
    If you want to make sure the plan stops running after the first five years, which is how I understand your point, then you should use a Strategy-based Plan without Cycles, but rather use Offsets.
    For no Cycle, but specified Offsets, the particular maintenance is only performed one at a given Offset. No offset after 5Y means no more maintenance is scheduled.
    Your Strategy should look something like the one below: (Assign all the Packages to your Task List)
    See a similar requirement here Performance based maintenance

  • Single cycle plan

    Hi experts,
    Plz tell me What is meant by single cycle plan ?how it works?
    Thanks in advance.

    Hi
    If you want to create plan for a single criteria single cycle plan should be used
    For ex:
    If you want to the maintenance for every 6 months
    then create plan in IP41
    Select maintenance order or Notification
    enter
    Maintenance plan cycle tab  Enter 6 in Cycle/ unit    &   Mon   in adjacent
    Maintain offset as 0
    fill the order needed and save
    go to IP10 schedule it
    If you want to creare plan for every 6000 hours
    Then create a separate measuring point and document
    Enter the measuring point no in counter
    M.Alagesan

  • Cycle Counts in 11.5.9

    Running a cycle count by period. Cycle count was established to start on 27-Aug-07. Created the Perform full cycle count (Report Set) which runs every month...however in September the auto schedule in the cycle count form has the next date as 24-Sep-07 yet the report set which is set to run monthly will run on the 27-Sep-07...and this disconnect will continue month after month. Did I miss something obvious in set up or is there no way to have the report set in synch with auto schedule on the cycle count?
    Thanks in advance.

    You are not connected to the user that started the database. Please verify the owner of the database processes. You can use the ipcs utility if on linux/unix to verify the owner. Please also verify the owner and permissions of the 'oracle' binary under the RDBMS Oracle Home bin directory to verify that it has the proper owner and permissions. This file should have the suid bit set in its permissions and must be owned by the proper group as well. It should appear something similar to this:
    -rwsr-s--x 1 orahelp dba 96735691 Jun 17 2009 oracle
    You can find the proper group by examining the 'config.c' file under the RDBMS Oracle Home rdbms/lib directory. It should look as follows:
    /* $Header: config_ux.c 115.1 2004/03/27 07:17:12 hfux ship $ */
    /* SS_DBA_GRP defines the UNIX group ID for sqldba adminstrative access. */
    /* Refer to the Installation and User's Guide for further information. */
    #define SS_DBA_GRP "dba"
    #define SS_OPER_GRP "dba"
    char *ss_dba_grp[] = {SS_DBA_GRP, SS_OPER_GRP};

  • What is the Significance of Late Days in Cycle Counting

    Hi All,
    I would appreciate if you could someone please let me know the significance of "Late Days" under Scope and Control tab in cycle counts form while defining.
    We are using 12.1.3 version.
    Regards,
    John

    Late Days tells when a scheduled count should be considered late.
    So if you make late days = 5 and if you schedule a cycle count today. After 5 days, it will be considered late.
    AFAIK, this field is not used in Oracle. But you can use it in reports.
    Sandeep Gandhi

  • Load Cycle Count over 7500 in just 5 days on new DV4 series notebook

    Hi,
      I'm really concerned about my new laptop i bought just a week ago (dv4-4172); it happens that the disk is making a lot of noise just like the infamous 'clicking sound of death' and reporting up to now, more than 7500 load cycles in just 5 days of operation and also, 2 errors in the CRC of the UDMA. Since my hard disk (Hitachi HTS547564A9E384 640.1 GB) was behaving like that i ran several test on the disk (HP's BIOS run-tests, HDD Tune, smartctl (short and the long one), etc.) but i'm not getting a single read-write error, that is, the system hasn't any functional/operational problem, yet. Furthermore, my disk's lifespan is 600000 load cycles and i'm getting about 1500 in just a day, you don't even need a calculator to realize the harddisk won't last more than 1.5 years. The constant clicking of the disk is also getting on my nerves too .
      The question here is, is it normal for this hard disk to have an average count of 1500 load/unload in a day (i.e. 1 cycle every minute) or is my disk the only one with suicidal attitudes?. My last notebook's harddisk (Seagate) didn't get more than 100k cycles in 2 years of operation, that's why i'm concerned...
      Naturally, hdparm solves the issue, but (partially or permanently) disabling my harddisk's APM is even more suicidal than my disk's actual attitude, and by the way, you need some technical skillset to change those values (I'm a linux sysadmin, so i knew how to solve that specific issue), why is the default configuration set as this? or is HP expecting every single user to know how to modify the APM or, if you don't, to have a seat while watching your hard disk self destruction take place.
    Thanks in advance.
    - melvin
    FYI, the problem is agnostic of which operating system i use, even in the POST stage the harddisk starts with that annoying clicking (and its corresponding cycle count increased), and yeah, i've updated all my drivers and followed every suggestion hp support assistant gave to me, like the nice guy i am.
    This question was solved.
    View Solution.

    Hello uncle_sam,
    You’re having a problem with the hard drive.
    The drive is not supposed to be making any noise.
    Since the unit is still new I’d call HP and have them send you a new HDD.
    Here is a link to the phone number.
    Clicking the White Kudos star on the left is a way to say Thanks!
    Let me know how everything goes.
    Have a good day.

  • Regarding Cycle Count Entries

    Dear All,
    I am doing cycle counting in which I have 10 Items in my subinventory. I have completed ABC Analysis and classified first 2 items as A and next 3 item as B and remain 4 items as C. Even I have performed Cycle Count as well.
    In Cycle count entries i am not able to enter count quantity for my entire 10 items instead it is showing only 6 items only. Why I was not able to see remaining 4 items and how do I enter count quantity for those missed 4 items?
    What would be the solution if i want to see all my 10 items in in cycle count entries form?
    Edited by: SaroR on Jan 20, 2010 6:58 AM

    Can you check mtl_cceoi_action_pub.import_CountRequest api?
    Please make sure you carry out the following before calling the API.
    1. Create a Cycle Count
    2. Enter a Manual Cycle Count Entry.
    3. Run program "Perform Complete Cycle Count" to generate generate cycle count request
    4. Post the count Entries using the by calling the API using your Script.
    Check the following MOS notes.
    Cycle Count Request Import (MTL_CCEOI_ACTION_PUB API) Fails When Using Serial Number Multiple Per Request [ID 1468453.1
    Cycle Count Api Not Working For Scheduled Counts [ID 786497.1]
    The Cycle Count Open Interface Is Not Working For The Stock In Api [ID 818977.1]
    Cheers,
    ND
    Use the "helpful" or "correct" buttons to award points to replies / Mark the thread as answered, if your question is answered.

  • Cycle count listing Report not generating out put

    Hi Team ,
    We are into 11.5.10.2 , We have set Auto schedule to weekly in cycle counts and cycle count is not generating output for cycle count listing in Production.
    But, we are able to generate report output in Test instance and unable to generate in Production . We tried testing with same login in Production and Test Instance .
    Please advice
    Thanks
    Kiran

    Also please confirm that the CC calendar and other CC related setups are exactly same from the PROD and TEST instances.
    Also make sure that you are running the report for the same INV org.. as there is no Input parameter for the Org in the report input but it picks from the MFG_ORG_ID profile value, which gets assigned when you loginto the responsibility.. You can confirm the selection by Chane Instance Org and select the Inv org and then run the report..

  • Inventory - Cycle count history

    Hi,
    I wanted to know is there a form/report, which can show the details of the historical cycle count Runs?
    i.e. if we schedule to the cycle count eg. every week, is it possible to see what all items are counted 3weeks back run?
    Rgds,
    -Kamal

    Sorry I never responded.  It's really just a matter of what you need to report on.  ISEG has all the basic information you need like plant, material, sloc, etc... so the other tables invovled is really a case by case type of thing.  I can't think of much else you would really need for generic cycle count reporting.
    Also, the previous post is a good method depending on your needs.  If showing difference postings and whatnot is suitable, then go with the movement type.  But if you need to dig deeper into it by showing system/counted quantities as well as the difference, then the custom extractor would be the way to go.  For me, I did inventory accuracy/cycle counting type of reporting that needed to consider the actual quantities, as a difference of 2 units on an inventory of 100,000 units is a lot different that 2 units difference on a balance of 100 units.  But that was just my case is all.
    Hope this helps.
    Thanks

Maybe you are looking for

  • Error in Database Instance

    Hi , we are installing ECC 5, after starting the  Database Instance it's giving this error Oracle instance termnated ,SQL statement or script failed. DIAGNOSIS: Error message: ORA-01092: ORACLE instance terminated. Disconnection forced Disconnected f

  • Still no fix for aspect ratio problems

    I was hoping this new version would fix the aspect ratio problems with importing clips other than in the DV codec, but alas, it was not to be. My problem is that if I import a clip that is 720x486 (non-square pixels, uncompressed), iDVD doesn't inter

  • Shared memory - free_instance method doesn't work

    I am using shared memory to store data, set the data in a program and then read in an update task.  My write and read both work, but I would like to "delete" the shared memory instance after the read in the update task.  I am using the free_instance

  • I have bought a full TV series, but says error when i  try and continue download?

    I bought a whole television series but the last 7 episodes wont download, help?

  • Performance tuning of a report.

    hello all,           I have been assigned a report to improve the performance.Initially after studying the report i found that all the data was fetched by using select * from... query,hence i changed the query by selectin the particular feilds from t