SL not getting generated via MRP

Hi,
Unable to generate schedule lines via MRP.
Settings:
Mat master - External proc , no spl proc
OA - Maintained
Source list - Maintained MRP Relevant - Indicator 2
Quota arrangement- Exist with only 1 vendor(same as of OA) 100%
MD03 - Planning data - Create PR (indicator-1), Create Sl(indicator 3)
Please let me know whether there is anything else which influence SL generation.

Resolved

Similar Messages

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Schedule lines are not getting generated through MRP

    Hello Experts,
    While running MRP, we observed that the system is creating PR instead of schedule lines, although all the necessary prerequistes to generate schedule lines through MRP are maintained. For e.g.
    1. MRP Schedule line relevant indicator '2' is maintained in the Source List.
    2. Sch. Agreement dates and Source List validity dates are same.etc...
    Further after some analysis, we observed that if we change the source list validity from date to some back date then system is creating correct schedule lines.
    Example: Material M1; Planned delivery time 7 days; GR processing time 5 days; MRP Type PD; Lot Size WB;
    SA validity dates - 07.09.2011 to 31.12.2011
    Source List validity dates - 07.09.2011 to 31.12.2011
    If MRP run on 12.09.2011 and source list dates are retain same as mentioned above, system creates the PR.
    If MRP run on 12.09.2011 and source list dates changes to 05.09.2011 to 31.12.2011, system creates the schedule lines.
    Could you please let us know, why the system behave like this?

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Demand not getting generated on MRP run.

    Hi All ,
    We have an trouble ticket. For a particular sales order , the user has run the MRP , but no planned order is generated . So she cannot convert the planned order to production order .
    When she tries to create a production order with T-code CO01 , She gets the error message ," Sales order does not allow Make to Order production"
    Diagnosis :- Sales order entered is not to be included in Make to Order Production.
    System response:- Account assignment can only be carried out with sales order created with requirement type for Make to Order production.
    Please note :- We have many other production orders running for the same material in the same plants for different sales order . There is no problem with them except this sales order.
    Following are the details for the material :-
    Planning strategy:- 25
    Procurement type :- E
    Kindly advise  . Thanking you.
    Kind Regards
    Ayaz A Khan

    Dear,
    Are you getting Message no. 61155?
    In particular, the above-mentioned error messages are displayed  if a planned order is not  assigned to a sales order but the sales order number or the sales order item is not yet known when the account assignment data of the planned order is checked.
    Check the requirement type in sale order and account assigment.
    Create a production order with T-code CO08 with reference to sales order.
    Then please refer this link,
    Sales order does not allow make-to-order production

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • PR,s not getting generated after MRP run

    Dear All,
    I'm running MRP through MD51 for WBS element where RM's are attached to WBS.
    It is MTO scenario where no stocks of RM's are maintained. I have checked all relevant settings of Masters.
    After running MRP through MD51, system is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    Please suggest & help.
    Thanks in Advance.
    Shaiz

    Little confused on your statement
    System is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    I would like to Know, whether the FG is attached with WBS or RM?

  • Proposals are not getting generated for BOM items in MD50

    Hi Gurus,
    I have maintained strategy 50 in MRP for header material , Item category gp as LUMF & maintained consumption parameters in material master .
    For dependent requirements i have maintained BOM for production & sales usage, Strategy is blank as it is customer specific component , Item category gp is NORM , individual requirements i.e 1 in MRP 4 view.
    MRP type is PD in both materials.
    When i run a MRP thru' MD50 after getting customer order.
    it is not planning my dependent requirements i.e. proposals are not getting generated for dependent requirements (BOM materials).
    Please let me know the solution.
    Thanx in advance
    Regards,
    Nagraj Vasmate

    try to use strategy 20

  • Planned order not getting generated for FG

    Dear Experts,
    Planned orders not getting generated for the Finished Goods - X which is having MRP Type M0 - MPS fixing type strategy group 20 which is copied fron another FG - Y , its a new product and production plan has been updated through MC88 - Rough cut planning but the planned orders are not getting generated.
    And for the material valid production version exists with selection method 3 and individullcollective as 1.
    Please let me know what might be the possibalities and what all the key fields i need to check.
    Thanks & Regards,
    Sampath
    Edited by: sampath s on Jul 13, 2011 11:31 AM

    Dear,
    In general MPS is run for High value items ( if you use like Gold , Platimum or A class items. ).
    Always only single level is used for Explosion and planning. then only you can analyse the requirements at each stage before procurement.
    Otherwise if you run MPS to multi level, Bottom most high value will be procured without any notice to authorities. Even you may cancel the process in mid way. At that time what will happen to the procured high value material.
    So for that purpose only single item single level MPS concept is evolved.
    Fo that you run MPS at single level so that only for the first level MPS will be carried out.
    Check and revert back.\
    Regards,
    Alok Tiwari

  • PR not getting generated in MD50

    hello,
    anybody please help me.
    My scenario is make to order for FG & SFG. make to stock for RM & Packing material.
    MRP TYPE : PD
    For FG & SFG: Individual Requirement
    For RM & Packing material: collective requirement.
    RM & Packing materil Stratergy group : 10
    Avilability Check : 02 (individual check)
    My problem is when i doing MRP run by using MD50, Purchase request are not getting generated for RM & Packing material when there is not stock, no po & No PR. in MD04 it showing dependent requirement. again when i am doing MRP run with MD02 pr getting generated. please suggest how to resolve this issue.
    my client is asking to generate PR at MD 50 only.
    Thanks & Regards
    bhakta

    MD50 is for sale order planning, system will plan with respect to sale order only -  you are considered the RM and packaging as a MTS scenario, then how the system will plan for RM and Packaging in MD50
    are you procuring raw material with respect to sale order means
    then for RM and packaging,  remove the strategy group  and maintain individual indicator, then run MRP in MD50, system will plan for RM and pacakaging material also

  • Proforma invoice is not getting generated

    Proforma invoice not getting generated against replenishment delivery though configured relevance for proforma invoice & Pricing standard in the item category.
    Copy control are maintained absolutely  for Delivery document to Billing document.
    The system generating message the item is not relevant for billing.
    Can any one attend this on priority.

    Hi Rao,
    Check the item category configuration via VOV7 for the item category being used in the delivery. The billing relevance should be set to A.
    It should help you
    Regards,
    Pls Reward points if it helps

  • Planned order not getting generated at plant level

    Hi experts,
          When i run MRP for a particular plant in T- code (MD01) Planned order is not getting generated but when MRP is done against a material in T - code (MD02) in the same plant planned order gets generated... Is there any customizing  to generate planned order in plant level.....
    Regards,
    Joseph.
    Edited by: joseph5885 on Aug 12, 2010 9:23 AM

    Dear Joseph,
    No it is not recommended. only in emergance cases this will be done
    Usually in MDRE and MDAB will be scheduled before MRP run at background for inconistancies in planning file enries
    So the above said t-codes will take care of the same
    Added
    Refer this link
    [Planning file entry;
    Regards
    Madhu
    Edited by: K.Madhu Kumar on Aug 12, 2010 6:53 AM

  • Prs being generated via mrp need to be in ZI doc type

    hi,
    we ve just started using MRP to generate prs. these prs are of doc type nb. when i try to use this pr to create sto in me21n.
    i get thiss error saying doc type nb cant be converted into U (sto doc type).
    earlier we used to create pr in doc type ZI (monthly indent)..using which we were able to create sto as well as local procurement order.
    so how do i set PRs generated via MRP to document type zi.
    plzz help.
    regards
    rahul

    Hi,
    In SAP IIMG the order types of the procurement proposal through MRP run are configured.
    Please study the following configuration:
    IMG >> MRP >> Procurement Proposals >> Deifne order Profile
    Object type     2 Purchase requisition
    Order profile   UL
    Order type           NB   Standard purchase order
    Procurement type     F    External procurement
    Special procurement  U    Stock transfer
    Acct Assignment Cat.
    Here I think you need ZI type document.
    regards
    Datta

  • Spool not getting generated in OO ALV report

    Hi,
    I developed a report in which we are giving output in same selection screen through OO ALV.
    But,when we are scheduling that report in background,spool is not getting generated.
    Waiting for your reply.
    BR,
    Praveen

    Hi Aparna,
    I tried NEW-PAGE PRINT ON.
    I am pasting source code extract below:
       IMPORT DATA = ME->IT_FINAL2 FROM MEMORY ID SY-CPROG.
        FREE MEMORY ID SY-CPROG.
        CHECK ME->IT_FINAL2 IS NOT INITIAL.
        CHECK LO_DOCK IS INITIAL.
        CREATE OBJECT LO_DOCK
          EXPORTING
            REPID = SY-REPID
            DYNNR = SY-DYNNR
            RATIO = 70
            SIDE  = CL_GUI_DOCKING_CONTAINER=>DOCK_AT_BOTTOM
            NAME  = 'DOCK_CONT'.
        IF SY-SUBRC NE 0.
          MESSAGE 'Error in Docking Control' TYPE 'S'.
        ENDIF.
        IF LO_ALV IS INITIAL.
          TRY.
              LO_CONT ?= LO_DOCK.
              CALL METHOD CL_SALV_TABLE=>FACTORY
                EXPORTING
                  LIST_DISPLAY   = IF_SALV_C_BOOL_SAP=>FALSE
                  R_CONTAINER    = LO_CONT
                  CONTAINER_NAME = 'DOCK_CONT'
                IMPORTING
                  R_SALV_TABLE   = LO_ALV
                CHANGING
                  T_TABLE        = ME->IT_FINAL2.
            CATCH CX_SALV_MSG.
          ENDTRY.
      CLEAR LR_COLUMN.
          TRY.
              LR_COLUMNS = LO_ALV->GET_COLUMNS( ).
              LR_COLUMN = LR_COLUMNS->GET_COLUMN( 'KSCHL' ).
              LR_COLUMN->SET_LONG_TEXT( 'Cond.Type' ).
    CATCH CX_SALV_NOT_FOUND.
          ENDTRY.
    NEW-PAGE PRINT ON.
            LO_ALV->DISPLAY( ).
            NEW-PAGE PRINT OFF.
    I am not getting spool list while executing it in background.
    BR,
    Praveen

  • MC.9 - spool is not getting generated

    Hi Experts,
    When i execute MC.9 transaction in foreground i am able to view the report output. but when i execute it in background spool is not getting generated.
    Please provide me any solution for this issue.
    Thanks
    Pallavi

    Hi
    I have checked list of versions in the 'select version' button.  But my question is when i select 'execute in background', it is not generated spool. Is there any relation between spool and version. If there is, please explain me what it mean and how it relates.
    As i am new to this module i wanted to know it, in brief detailed.
    Thanks
    Pallavi

  • Transportation lane KEY not getting generated in the table

    Transportation lane KEY not getting generated in the table
    Hi folks,
    The issue is like this :
    We have a weekly workorders upload program from legacy systems to SAP-APO. The legacy planners send a .CSV file containing material-wise workroders. A customised zee program picks these quantities & writes them in Prod.planned keyfigures in SNP planning book. This process is done for the manufacturing locations only.
    Lately workorders for two particular material M1 & M2 had failed to get upload. It gives the error 'NO VALID SOURCE OF SUPPLY COULD BE FOUND' in its Job log. We did some debugging & found that for successful materials the  TRPID is getting generated in the table /SAPAPO/V_TRPROD  whereas this TRPID is missing for M1 & M2. Why this is happening is our main concern. We tried deleting the PPM & creating this again, assuming that the PPMID is the precursor for generating this TRPID, but this yielded no results.
    ____ for successful upload______________
    se16 --> /SAPAPO/V_TRPROD
    Version = 000
    LOCTO = LOCID KEY for manufacturing location
    MATID = MATID KEY of successfully loaded workorder
    Enter
    This gives the following results
    TRPID = TRPID KEY
    LOCFR = LOCID KEY for manufacturing location
    LOCTO = LOCID KEY for manufacturing location
    MATID = MATID KEY for successfully loaded workorder
    ( This seems a self-lane, i.e both TO & FROM location are same)
    ____ for unsuccessful upload________
    se16 --> /SAPAPO/V_TRPROD
    Version = 000
    LOCTO = LOCID KEY for manufacturing location
    MATID = MATID KEY for unsuccessfully loaded workorder
    Enter
    This gives the following results
    Error = No Table entries found for specified KEYS
    We are perplexed why this TRPID is not getting generated for these two particular material M1 & M2?
    We have deleted their PPM & re-created them to cross-check if the PPMID KEY is the trigger for generating the TRPID key. This didn't work!
    Please let us know in case someone faced a similar issue.
    Many Thanks.
    Kumar
    Edited by: Blue Lotus on Jun 9, 2011 2:44 PM

    Yes Anand.
    We deleted the PPM & created it again, which didn't work.
    Later on we deleted the product itself from APO & re-CIFed it from R3 & then re-created the PPM.
    The PPMID which was missing earlier is now getting created! However no luck with the TRPID.
    Why this TRPID is not getting generated in our only concern
    Regards
    Kumar

Maybe you are looking for