Hi gurus,
SCM 5.0
I am running SNP heuristics for a product and expecting planned orders for it.  It has corresponding production data structure and multimixed resource.  The resource has an assignd factory calendar and SNP bucket capacity.  The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays.  Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource.  APO does not schedule on holidays consistent with bucket capactiy.  This is true until...
We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday.  The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change.  However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday.  Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
Any ideas on this? looks like a bug.

Hi Edgar,
Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
Since this is a mutlimix  resource , it can also be checked if in PPDS planned order can be created on the day.
The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
regards
Datta

Similar Messages

  • SNP Planned order start and end dates are not calculated correctly

    Hello SNP Guru's
    The SNP planned orders generated after the Heuristics run, have a start and end date based on the Activity Duration (Fixed), while the resource consumption is based on the Bucket Consumption (Variable), which is correct.
    The Activity Duration (Fixed) is based on the BOM Base Quantity. So if the Activity Duration = 1 day, and if the order quantity is more than a day, the start and end dates, still shows as 1 day. So no matter what is the order quantity, the start and end dates is always = 1 day.
    Does anyone have any experience in implementing any code to change the start and end dates on SNP Planned Order?
    Seems like it should work as standard.
    Am i missing something?
    Thanks,
    Mangesh

    Dear Mangesh,
    SNP is a infinite planning tool. If you have defined fixed duration to be 1 DAY in the activity, no matter how many quantity you input for your planned order, the order will last for one day. If the resourced is overloaded, you then run capacity levelling to
    banlance the capacity. What your expected beahavior happens in PPDS planning.
    Claire

  • Creation of SNP planned order in Monthly Bucket though CTM plan

    Hi,
    Can anyone advise how to aggregate the SNP planned order generated after CTM run in Monthly bucket.
    Can it be done through customizing?
    Regards.
    Punit

    system switches over to external procurement in place of in house production only when you use optimizer.
    Heuristic will do this only if there is a SNP PPM/PDS and the resource calendar prevents timely production.
    Regards
    Nitin Thatte

  • Split SNP planned order to weekly buckets

    Hi all,
    does anyone knows a way to split SNP planned order to weekly buckets from monthly buckets?
    the planner enters his production forecast in SNP94 in monthly buckets, but for purchasing prefer to see the demand weekly, i need an automatic split of planned order (something like the split of forecast).

    to split the component will not help, the need is to distribute the finish goods through the month on weekly buckets, once the finish goods are on weekly bucket, i don't care if the all the components demand is at the beginning of the period.
    i need a macro or heuristic to split the quantity, see the example below, the planner has monthly view in which he had entered 55,000 PC for month 10.2014, before i transfer this quantity to the ECC i need to split it to weekly buckets:
    simple MRP run will not work, because the planner may plan to produce more than the total demand.

  • SNP planned order deleted in APO, but not in R/3.

    OK Guru's,
    We have a situation where during the weekend SNP planning runs, SNP Planned orders are deleted in APO, but the order is never deleted in R/3.  The change pointer is not in CPP and there are no failed queues.  Also, when you run CCR on planned orders, we will get an error on some orders saying "Not in APO" and the only option to reconcile that order is to "Send to APO".  The option that should exist is "delete in R/3" becuase the deletion never occured in R/3.
    If you send the order back to APO, the order will show in the "Production Confirmed" line of the Planning Book.  This is because APO is thinking that this order is an order that was created in R/3 when in fact is it really is a SNP planned order.
    Any clues to why this would happen?
    thanks,
    Brian

    How are you getting the SNP Planned Orders to R/3 in the first place.
    If you are transferring them using /SAPAPO/RRP7 then I guesss its a manual transfer and system does not consider SNP Planned Order deletion flag relevant for transfer to R/3.
    You will need to look into CIF enhancement to send the deletions to R/3.
    Normally SNP Planned Orders are not relevant for transfer to R/3 unless its replaced or converted to a PPDS planned order.
    Somnath

  • Creation of SNP Planned Orders using Optimizer

    Dear Experts .....
    I am facing some problems while creating SNP Planned orders using Optmizer ( Discret Optimization).....
    For eg.
    I am using 3 months horizon ... the first two months is daily buckets with 12 hours capacity each one and the last month is weekly buckets.
    The product minimun lot size exceed the daily capacity .... this way planned order have been created in the weekly buckets at the end of the horizon.
    I need the system to create orders in the correct date avoiding use of safety stock .....
    Regards
    Mauricio

    Those other 2 settings was already done .....
    It is still not working .... iI am receiving the following message ...
    Production process model/PDS 00000000000001011301001             S: Cannot be executed
    Message no. /SAPAPO/SNPOPT159
    Diagnosis
    Production process model 00000000000001011301001             S at location 0100 is intended for cross-period lot size planning. It can be started in bucket 20110404->20110404. However, it does not then end in the same bucket.
    Thanks for your effort trying to help me with this issue.

  • SNP planned order availability date difference between APO and ECC

    Hi,
    I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
    I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
    Example:
    I am using PDS as a source of supply.
    Fixed production activity in SNP PDS is 1 day.
    GR processing time: 3 day
    After running optimizer planned order is created with dates explained below.
    Start date/time: 09.05.2011 00:00:00
    End date/time: 12.05.2011 23:59:59
    Availability date: 16.05.2011 00:00:00
    Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
    After publishing this planned order to ECC dates on the planned order is as follows.
    Start date: 09.05.2011
    End date: 09.05.2011
    Availability date: 12.05.2011
    I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
    Regards,
    Venkat

    Hi Venkadesh,
    What's "state stamp"? Do you mean different time zone?
    note : 645597  mentioned by Nandha is very helpful:
    In standard, CCR will use duedate - "the available date of the output product".
    Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
    end date of the last activity of the order, the receipt date
    always identifies this as inconsistent. You cannot rectify
    inconsistencies of this type by using CCR."
    I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
    Please CIF the PDS or PPM again.
    If you really want to apply a note, please use note 815509 as you're using planned order,
    and system will use order end  date in CCR instead.
    GR time is always considered. BR/Tiemin

  • To build query related to SNP: Planned Order

    Hi,
    System: SCM 5.0
    Scenario: SO received at plant and planning creates PR against SO at plant and accordingly SNP:Planned Order at Vendor location. If SO is cancelled/deleted (manually), sometime only the PR gets cancelled/deleted (automatically during planning run) but corresponding SNP:Planned Orders still remains at vendor location and so the dependent requirements. PR and Planned Orders are pegged to SO so one-to-one relation is maintained.
    I could not find any reason why system is not deleting Planned Order at vendor location despite SO and PR is deleted at plant location. So I am planning to build query where SNP:Planned Orders are not pegged to any PR or SO.
    Can anyone help with list of SNP:Planned Order tables so that I can build query around it to identify ghost Planned Orders.
    Hope I was clear with my query but let me know if any further information is require.
    Thanks and regards,
    Devang

    HI Marius,
    Sorry for delay reply.
    I was working on on some other more critical issues to business.
    Finally we decided to built report to identify obsolete Planned Orders for which PR is not available in ordering plant. I have listed below logic for that report:
    Get Location ID from table /SAPAPO/LOC based on Location entered in selection screen
    Get PEGIDs from FM /SAPAPO/DM_MATLOC_GET_PEGIDS based on IV_SIMID as 000 and location id from step 1
    In FM /SAPAPO/OM_PEG_CAT_GET_ORDERS, use SIMVERSION as 000 and in Import Para IS_GEN_PARAMS insert all PEGIDs from step 2.
    From Export Para ET_PEG_INPNODE take From_OrderID and store in internal table.
    Execute T.Code /SAPAPO/RRP4 with following selection (Use Selection Variant: OBSOLETE PR and add Location as entered in Selection Screen)
    Planning Version: 000
    From: Current date – 60 days
    To: Current date +180 days
    Location: 0000201328
    Product: *
    Order Type: 1F
        6. Compare output of step 4 and step 5 and display result.
    From FM /SAPAPO/DM_MATLOC_GET_PEGIDS the output (step 4) will be Order ID (22 characters) while step 5 (T.Code /SAPAPO/RRP4) will give Planned Order number (8 character). I am not sure how to compare Internal Order ID (22 characters) for corresponding Planned Order Nos. (8 characters).
    I have not marked your post as correct answer as still need to find answer of above query.
    Thank you in advance for your guidance.
    Regards,
    Devang Shah

  • How to Change Component on a SNP Planned Order ( Just 1 time )

    Hello,
    We are trying to change a component on a SNP Planned Order just 1 time.
    So we do not want to change the PDS since this is one time change only.
    We tried changing it in R/3. Once we do that, R/3 shows new component but APO still shows dependant demand on old component ( May be because APO SNP Planned order is still connected with the PDS ) .
    Then we went to APO and tried to change the component in /sapapo/rrp3. Here you can delete the old component but doesn't let me add new component.
    Next thing we tried was to convert it to PPDS Order. Once converted, we went to change mode and tried to remove old component and add new component. It lets me do this. Only issue with this route is that, it puts correct start and end dates on the order dependning on the order quantity and so order moves the dates which we do not like.
    Is there any other better way to fix this issue ?.
    Thanks.
    Ketan Doshi.

    This being a very unique requirement, I would use one-off approaches usually not followed. You may need to explore the use of BAPI BAPI_MOSRVAPS_CREATESNPORDER. This will help you point the source of planned order to a PPM or a PDS that you may want to create in APO system on a one-off basis. PPMs can be maintained in APO, however PDS are usually CIFed from R3. You can try to create PDS (based on the new component) in APO system only using backend tables. Try do some little research on /sapapo/curto tables to create the PDS in APO. Then use the BAPI to point the source to this new PDS. (better you also try the PPM approach since there are no issues keeping the PPM in APO)

  • SNP Planned Order

    Hello Experts,
    Scenario: we plan finished goods in SNP & for component level we run MRP in ECC.
    I need to understand how MRP does planning in ECC based on SNP Planned order. Why MRP run does detailed scheduling on Finished goods planned order which released from SNP?
    I am not getting why MRP in ECC considers material which has X0 MRP type & it does detailed scheduling on finished good planned order & it changes start date & time of planned order which push back or forward sometime in SNP.
    Can anyone explain why MRP does detailed scheduling on finished good planned order? And after sheduling why it changes start Date & Time?
    Thanks in Advance
    Regards
    Sujay Joshi

    Dear manimaran
    I am going through the same scenario as joshi....component planning is done by MRP and planning for final product is done by SNP and PP/DS......say i have planned order from SNP and PP/DS
    1. can i subject those planned orders to MRP run again by bringing back to ECC
    2.If its is possible how do i see what is the screen wherein i will see that planned orders from SCM has arrived to ECC
    3.what tcode do i use to subject those scm planned orders to MRP run
    I have detailed a implentation procedure i would be happy if you can say if it is logically correct,if it is not correct then which is the correct logic.
    Planning will be divided into two parts ,Plant level planning and supply chain planning, for Plant level planning traditional MRP run is mandatory to determine the requirements at the plant level.
    DMS (Distributor management system ) to be used by all customers
    Capture the demand from all the market segment  into DMS and upload the demand in SCM
    Create a demand plan in APO and release it in SAP R/3 Demand management after confirming the demand.
    Maintain material master for all the materials on demand.
    Maintain relevant production version in C223
    Run traditional MRP
    Calculate exact  quantities by creating production order in R/3.
    Transfer the quantities  required for specific time period alone to APO,for example if you want to allocate capacity to run 4 shifts transfer the approximate value of quantity alone to APO, the time period may be for 7 shifts or 1 month ,which is industry specific. 
    Perform simultaneous capacity and material planning in PP/DS  (or)
    After rough cut planning in APO, SNP perform simultaneous planning in APO , PP/DS ,using any one of standard heuristic like PP_001 or MRP_001 or PP_002
    Adopt planning procedure =3
    Confirm the production order in R/3
    thanks
    Saravanan

  • SNP Planned order error

    Hi,
    During the immediate transfer of the SNP planned orders after the planning run, some orders are not moved immediately, they went to R3 during the next snp run in the background.
    do you know any reason for this?
    Thanks,
    Dhanush

    Hi Dhanush
    To answer your query in block size, the block size can be maintained in customizing settings. You can navigate with the following navigation path
    SPRO --> Integration visa APO Core INterface --> Basic Settings for data transfer --> Publication --> Manitain Object Specific Settings
    You can define an optimum block size for both external procurement and In house Production. But before you do that I would request first check if there any queue blcoks exisitng which are preventng the smooth flow of data from APO to ECC. You check this through /sapapo/cq transaction. Depending upon how you have queue set up (inbound/outbound), you can select the apprpriate drill down and see if any queue blcoks exist. If you can afford to delete the queue blocks, then please delete them and then run heursitcs again.
    Also in your intial part of the query you have mentioned that the planned orders are not getting transferred. However in the latter part you are refering to purchase requistions. Are you facing problem with both the types of transaction data?
    Rgds, Sandeep

  • Creation of SNP planned order based on PDS

    Hi,
    I'm a APO developer and I have the following problem:
    I would like to create a SNP planned order based on a PDS (like e. g. in the planning book when you input a number into a cell in the "Production (Planned)" line).
    Up to now I've only managed to create such an order without using the PDS.
    Can you name me a function module which allowes me to do that?
    Thanks in advance.

    Hi,
    I've now managed to create this kind of order.
    I set a breakpoint at the function module /SAPAPO/DM_PROD_ORDER_CHANGE and checked how it was filled in the planning book.
    For those who want to know:
      INCLUDE /sapapo/constants_om.
      CONSTANTS:
        lc_order_type_1f        TYPE /sapapo/om_order_type VALUE '1F'.
      DATA:
        ls_prod               TYPE /sapapo/msnp_prod,
        lt_prod               TYPE /sapapo/msnp_prod_tab,
        ls_sources            TYPE /sapapo/sources,
        lt_sources            TYPE /sapapo/sources_tab,
        lv_matid              TYPE /sapapo/matid,
        lv_locid              TYPE /sapapo/locid,
        lv_vrsioid            TYPE /sapapo/vrsioid,
        lv_tstfr              TYPE /sapapo/timestamp,
        lv_tstto              TYPE /sapapo/timestamp,
        lv_simsession         TYPE /sapapo/om_simsession.
    lv_vrsioid = '000'.
    * Create SimSession
    CALL FUNCTION '/SAPAPO/TSIM_SIMULATION_CONTRL'
        EXPORTING
          iv_simversion              = lv_vrsioid
          iv_simsession             = lv_simsession
          iv_simsession_method = 'N'
          iv_perform_commit       = space
        EXCEPTIONS
          lc_connect_failed        = 1
          lc_com_error             = 2
          lc_appl_error            = 3
          multi_tasim_registration = 4.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
    * Get PDS
      CALL FUNCTION '/SAPAPO/MSDP_SNP_PPM_VALIDITY'
        EXPORTING
          iv_vrsioid      = lv_vrsioid
          iv_matid        = lv_matid
          iv_locid        = lv_locid
          iv_tstfr        = lv_tstfr
          iv_tstto        = lv_tstto
          iv_planstart    = lv_tstfr
          iv_planend      = lv_tstto
        CHANGING
          ct_sources      = lt_sources
        EXCEPTIONS
          wrong_interface = 1
          error_occured   = 2
          OTHERS          = 3.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
      READ TABLE lt_sources INTO ls_sources INDEX 1.
      ls_prod-version       = lv_vrsioid.
      ls_prod-matid         = lv_matid.
      ls_prod-locid         = lv_locid.
      ls_prod-plobid        = '9AMALO'.
      ls_prod-tstmp         = lv_tstfr.
      ls_prod-catgr         = 'PP1'.
      ls_prod-categ         = 'EE'.
      ls_prod-categ_prku    = 'EE'.
      ls_prod-categ_prse    = 'EL'.
      ls_prod-kz_prod       = '9APPROD'.
      ls_prod-kz_prku       = '9APPROD'.
      ls_prod-kz_prse       = '9ADMDSE'.
      ls_prod-produ         = '1000'.
      ls_prod-proid         = ls_sources-trpid.
      ls_prod-mosta         = gc_new.
      ls_prod-order_type    = lc_order_type_1f.
      ls_prod-is_fixed      = 'X'.
      ls_prod-snp_is_header = 'X'.
      APPEND ls_prod TO lt_prod.
      CALL FUNCTION '/SAPAPO/DM_PROD_ORDER_CHANGE'
        EXPORTING
          ic_database           = 'LC'
          ic_application        = '4'
          iv_simsession         = lv_simsession
          it_prod               = lt_prod
          iv_netch              = 'X'
        EXCEPTIONS
          material_not_supplied = 1
          location_not_supplied = 2
          OTHERS                = 3.
    * Merge simulation version (to commit order changes)
      CALL FUNCTION '/SAPAPO/TSIM_SIMULATION_CONTRL'
        EXPORTING
          iv_simversion                = lv_vrsioid
          iv_simsession                = lv_simsession
          iv_simsession_method         = 'M'
        EXCEPTIONS
          lc_connect_failed            = 1
          lc_com_error                 = 2
          lc_appl_error                = 3
          multi_tasim_registration     = 4
          target_deleted_saveas_failed = 5
          OTHERS                       = 6.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.

  • Bapi for sfg dependent dem,snp planned order qty, and ppds planned orde qty

    Hi Gurus,
    I am not much familiar with APO, so please help me,
    Input details:
    Field                         Value     
    Planning Version     000     
    Source Location *     1001     Single/Multi Value
    Product *                          1000061     Single/Multi Value
    Production Planner *     PRC     Single/Multi Value
    Start Date *          
    End Date *          
    o/p:
    Source Location     Date     Semi-Finished Material     Material Description     SFG Dependent Demand     SNP Planned Orders qty     PPDS Planned order Qty     Total SFG Variance due to Lot size     Total SFG Variance reference to dependent demand
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT     340     412     420     8     80
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT                         
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT                         
    Is there any bapi to fetch the data as shown in o/p.
    Thanks

    Hi Phani,
    Tryout the below BAPIs
    IF10503 (object)
    BUS10503
    Regards
    R. Senthil Mareeswaran.

  • Unable to convert SNP planned order to PP/DS planned order in RRP3

    Hi,
    This is an in-house production scenario. SNP planned order are created based on forecast, now i want to convert those SNP planned orders to PP/DS planned orders in product view. While converting i am getting the following error message.
    Conversion canceled with error
    Message no. /SAPAPO/RRP707
    I have checked the SNP, PP/DS PDS, it looks good.
    Regards,
    LV

    Hi Lingaiah,
    Conversion SNP -> PP/DS SAP002 is scheduling heuristic
    Heuristic for Conversion SNP->PP/DS  as SAP_SNP_SNGL used for order conversion.
    Regards,
    R.Brahmankar

  • Issue in Deployment of SNP Planned orders

    Hi Experts,
    I am trying to deploy SNP Planned orders and I have made relevant settings in SNP2 i.e. ATP category in ATD Receipt.
    When I run deployment, it creats deployment stock transfer (DEP: PReq / DEP:ConRl) based on available stock first. When I run deployment second time, then it creats deployment stock transfer( DEP: PReq / DEP:ConRl)  for SNP Planned order with the same quantity of stock & not for entire quantity of SNP Planned order. Please refer below example to make it clear
    Total Demand at destination location = 600
    Stock at supply location = 100
    After planning run, Purchase requsition of 600 is generated at destination location.
    At supply location, SNP Planned order of 500 is generated considering 100 stock is available against PReqRel of 600.
    When I run Deployment first time, it forms DEP: PReq / DEP:ConRl  of 100 based on available quantity of 100.
    After running Deployment second time it forms again DEP: PReq / DEP:ConRl  of 100 and it continues to create deployment stock transfer till it completes the quantity of SNP planned order.
    So all together it creates 6 deployment stock transfers instead of forming one deployment stock transfer (stock+ SNP Planned order).
    There is no lot size setting for product master.
    Can anyone suggest whether I need to do some settings to get one deployment order instead of 6.
    Thanks & Regards,
    Chetan
    Edited by: Chetan Patil on Nov 10, 2010 4:45 PM

    Hi Chetan,
    It looks the SNP planned order is not being considered in the receipts quantities  to be available for deploying against requirements.
    Please check SNP order  ATP type( it  is normally EE)  is included in the appropriate Categroy group
    IMG >> APO > Supply Chain Planning  > SNP > Basic Settings > Maintain Category Groups
    Example :  ATD Receipts:   ATR
    Typical values :    AI, AJ, BF, CC,EE,EF, EI
    Secondly, in the transaction /SAPAPO/MSDP_ADMIN, in the Key Figure detailed  tab, ATD Receipts should have assigned the Category Group(say  ATR).
    Regards
    Datta

Maybe you are looking for

  • CS6 Premiere Pro Workflow

    In the limited time I have, I am attempting to learn Premiere Pro and have working through the CS6 tutorials that creativecow.com have to offer. However, it would be a great help if I had a better idea on the workflow (in simple terms) such as: Set p

  • Multiple address book sync

    I have two phones blackberry(business) & iPhone (personal). I want to sync the contacts with address book but keep it separate. Is there a way where I can have two address books one for business and one for personal and sync my phones? TIA Raj

  • Adobe Reader-PDF-window without tools-column

    When displaying a PDF-document, can I set the display so that the tools-column at the right sight is not shown thereby making the view of the document larger? If yes, how? Thanks in advance, Hans M.

  • HDMI connected to work flatscreen not displaying, but detected

    Hi all. I'm having an HDMI output problem on a MacBook pro retina, just got it a couple days ago. When I connect to the flatscreen in the conference room (Toshiba) via HDMI, the mac screen does it's resolution-switching blue flicker, and I get, in th

  • HT5457 how do i get facebook on my iphone 3 GS?

    is it possible to download facebook on i phone 3 g ,or 3 gs?