SNP PPM Generation error

Hi ,
I am facing an issue in SNP PPM generation from PPDS PPM and getting an error as /SAPAPO/PPM_GENERATE124-u2018Start date of the generation period is in the pastu2019.
I tried changing dates in field u2018Start of Gen. Periodu2019 to future in /SAPAPO/PPM_CONV_310 std TCode but still this error remains.
Please let me know the missing part here u2026
Regards,
Digambar

Hi Digambar,
Please check SAP notes 737991, 524601 and 1036685.
Whichever is relevant for you, implement it
Regards
R. Senthil Mareeswaran.

Similar Messages

  • SNP PPM generation

    Hi Guys,
    I have PPDS PPM have 3 operation , in first operation there are 6 modes ,all are SNP relevant and second operation there are one mode and third operation there are 2 modes. second and third operation resources are not SNP relevant, While generating SNP PPM system gives error maximum no of mode combination exceeds.
    The requirement is only 6 SNP PPM should be generated as there are 6 SNP relevant modes are there.
    Thanks and regards
    Thamizhchelvan G

    Hello,
    With my experience SNP PPM generation can be  a tricky business. Try this out...give the max number of PPMs possible as '99' and generate the PPMs. Then have a look at the number of PPMs generated and see what its doing. It should give you a fair amnt of idea wats going on.
    Let me know how it goes
    Abhi

  • PPDS to SNP PPM conversion error log

    Dear all,
    Iu2019m facing an issue in PPM conversion from PPDS to SNP.
    I have deleted the both PPDS & SNP PPM for a product/location combination & the corresponding PV has been made invalid.
    I have created a new PV for the product/location combination.
    When I execute CIF & conversion for the newly created PV, though system is generating both new PPDS & SNP PPMu2019s but at the same time it issuing error messages referring the deleted PPMu2019s in transaction /SAPAPO/PPM_CONV_LOG - SNP PPM Generation: Display Log.
    Please suggest how to resolve this issue. More over I would like to know is there any table where the deleted PPMu2019s data is stored which system is referring while generating new PPMu2019s?
    Thanks in advance.

    Hi Shaiz,
    I am surprised at the behavior of system. PV is invalid and still it is giving error message.
    Please try to CIF new PPM for newly created PV after making earlier PPM inactive.
    If the above said option does not work.
    I could suggest you to try this. Let's hope it works.
    1) Delete all SNP and PPDS PPM for this product location combination.
    Make sure PPMs are inactive and deleted.
    2) Delete the PV which is invalid and maintain only one valid PV.
    Now try to CIF it afresh.
    As far as your last question is concerned.
    all the plans can be accessed by table  /SAPAPO/PLAN
    You will get all the details about all PPMs in this table along with the status if PPM (Active/Inactive)
    Hope this helps. Let us know if it works.
    Regards,
    Abhay Kapase

  • SNP PPM Generation from PPDS PPM - Time less than 1 sec. in snp bucket con

    Dear All,
    Request immediate help .
    (a) My PPDS PPM have time elements less than 1 seconds towards processing time and there are operations without a set up time .
    (b) While converting such a PPM PPM into an SNP PPM I get an error of bucket consumption as SNP cannot convert less than 1 second into a daily bucket .
    (c) I have to maintain the base qty in BOM and Routing as 1 unit hence cannot increase the same .
    (d) Is there a way in which SNP PPM can be generated from a PPDS PPM wherein the PPDS PPM has only a processing time of 1 second and no set up time .
    (e) Infact I have tried to convert the PPDS PPM with a time of 1.5 seconds but now I have lot of products where the routing suggests a processing of less than 1second and no set up . This is leading to a PPDS PPM of time less than 1 second and SNP PPM is not getting generated as guess it cannot convert a PPDS PPM with less than 1.5 seconds in a day .
    Would appreciate a quick response .
    Thanks and Best Regards ,
    Prashant Kumar

    Hi
    Firstly, can I ask why the base unit has to be 1, this seems a strange restriction?
    If it has to be, then two possible solutions:
    1) In the CIF enhancement CIFPPM01 you could multiply all values by, for example, 100 to give you larger values in the PP/DS PPM in APO and hence of a size that SNP conversion can cope with.
    2) In one of the BADI's /sapapo/ppm_calc or /sapapo/ppm_gen you can do the same conversion factor if the PP/DS PPM has to also be 1 unit.
    Hope this helps
    Ian

  • SNP PPM Generation after the delta change in PPDS PPM

    Dear Colleagues,
    In oss note 1172838 SAP AG states that there is no auto link to
    generate SNP PPMs from PPDS PPMs,when PPDS PPMs are changed from R/3
    and recommends the customers to do that manually.
    Yes, that is possible if the company uses not more that 50-100 PPMs,
    but that is not the case in our business.
    We have ~10000 SNP PPMs and it is impossible to track the changes and
    update the PPMs manually.
    What we need (when there is a change in PPDS PPM) is a report which will:
    1. Delete SNP PPM with invalid mode combination and the Production
    (Planned) orders which use that PPM. The old SNP PPM must be deleted as
    the existing name of SNP PPM is required.
    2. Create a new mode combination taking into account the changes in the
    PPDS PPM.
    Then we will run transaction /SAPAPO/PPM_CONV_310 and generate the new
    SNP PPMs.
    Task in point 1 can be done with transaction /SAPAPO/PPM_DEL,
    but it does NOT give us the possibility to select only SNP PPMs
    with invalid/obsolete mode combinations. Besides that it can not be run in
    background, but in foreground.
    Would you share you experience if you have faced the same/similar problem.
    Best Regards,
    Alper Myumyun

    Hi Senthil,
    The problem is that the mentioned check does not work. I have even opened an oss message where I have got the following answer:
    First you have to re-generate the SNP PPM (invalidity of the old mode combination will be generated) and then the
    check will warn you about the invalidity.
    This is so because at the first stage there is no issue of it being obsolete until a new one is created.
    At the point that you Generate SNP PPM is when the mode invalidity is generated and not before. So its not possible for the warning to have come when there is no invalidity.
    /SAPAPO/SAPLSCC_CPIT2 looks scary. There are tons of includes in it. Would you specify which one is used for the mentioned check? INCLUDE /SAPAPO/LSCC_CPIT2F09?
    Thanks for your help.

  • Error In SNP PPM Creation . . .

    Hi All,
    I am getting following error message while converting PPDS PPM to SNP PPM. . .
    " SNP-relevant and non-snp relevant modes exist in operation "
    Please can someone let me know the solution on this. .
    Thanks in advance.
    Regards,
    PP.

    Hi,
    Please  check if any  single or multi-mixed resource has "Not SNP Rel. indicator" has  been set on the Planning Parameters tab page is in the PPDS ppm.
    Regards
    Datta

  • Getting error while trying to generate SNP PPM

    Hi Experts,
    I am getting error, while trying to generate SNP PPM fron PP/DS PPM. It says Set up matrix for resource in planning version is not define. But I checked that i havea set up matrix as well as setup group.
    Any help will be appreciated. Thanks In advance.
    Sani

    Hi Sani,
    Try running resource & ppds ppm consistency check against
    their respective transactions (/sapapo/res01 & /sapapo/scc_03)
    and check any inconsistencies found.
    Regards
    R. Senthil Mareeswaran.

  • APOLoader PPM Plan Error

    Hello,
       We are upgrading from APO 3.1 to 5.0 and I am trying the new ApoLoader to load some PPM's.  I keep getting the following error:
    E/SAPAPO/PPM_TRANSFER 119
    Message: Unable to find suitable logical component for PPM
    I'm able to Get Data successfully, and I get the same error above if I try to Put the data just received.
    Points will be rewarded.
    Thank you,
    Jerry

    Hi
    There was a similar issue in the standard versions of SCM 400 and 410 which was fixed by the below OSS Note:
    [Note 715935 - BUS10003: Error when modifying Component data in DP/SNP-PPM|https://websmp208.sap-ag.de/~form/handler?_APP=01100107900000000342&_EVENT=REDIR&_NNUM=715935&_NLANG=E]
    It may give you some help as to what is occuring in the APO Loader itself which may have the same issue.
    Regards
    Ian

  • Switch between SNP-PPM and SNP-PDS

    Hi,
    In APO I have both SNP-PPM and SNP-PDS, but right now I am having some trouble with the bucket time from the PDS so I am trying to temporarly change my PDS to PPM.
    My query is:
    - Is there a way in APO to make the SNP-PPM the default production model over theSNP- PDS?
    I was searching for some kind of documentation on this topic and I found that I should change the priority for the PDS throught the PDS_MAINT transaccion in ECC, is this the only way to do it?
    Thank you in advance,
    Fernando

    Hi ,
    SNP heuristics  planning source determination gives first preference to Quota arrangement.
    You may include PDS as a source of supply in the inbound quota arrangement of the product.
    There is a BADI  BAdI /SAPAPO/PWB_SOS to modify the content and the sequence of the sources of supply in the ranking list.
    The normal ranking list for SNP source determonation  is as below:
    Quota arrangements
    Procurement priority
    Procurement costs
    Procurement type
    There are two other BADIs releveant as below:
    u2022        /SAPAPO/CURTO_SNP ) Enhancements When Creating an SNP PDS (R/3) (Generation)
    u2022        /SAPAPO/CULLRTOSNP ) Change SNP/CTM Production Data Structure Data (Generation)
    Hope this gives some options.
    Regards
    Datta

  • SNP PPM can't be activated

    Hi ,
    I am working in SCM 5.1 , I wanted to test the dependent demand flow in SNP heuristic run and for the same I have tried to create PPM. I have created resource bucket  & single mixed both. But when I am trying to activate the SNP PPM it gives me error "No linked PP/DS plan exists for SNP plan". IS it necessary to have PP/DS plan for SNP ppm ? Is anybody else faced the same problem in SCM 5.1 ?
    Thanks for your support.
    Best Regards,
    M

    Hi,
    are you getting some more error? like 'bucket consumption is not defined'. then you have to define the 'bucket consumption' in the resource. go to 'mode' of the 'ppm' and check resource consumption is properly defined or not.
    thanks,
    Satyajit

  • Generation error in TSTR_PERIODS_FACTORY CALENDER while doing capacity leve

    Please help to resolve the issue,
    i am getting error Generation error in TSTR_PERIODS_FACTORY CALENDER while doing capacity leveling,i am observing it is getting error for specific location,i have checked the resource ,ppm valididy, valididy of factory calender in resource  looking fine to me,please help to get resolve the issue

    Hi,
    Check the location master for the Time streams & related calendars.
    Try to re-activate the planning area & run consistency check.
    Hope this helps.
    Regards,
    Nawanit

  • SAP System Message: Syntx error or generation error in a screen

    dear sap basis gurus,
    i am currently having problems signing on to our DEV server. i get this error message:
    <SID>: SAP System Message
    Syntx error or generation error in a screen.
    it won't let me log on.
    there were no changes made on the server (i.e., profile parameters) lately. it was working really fine after our support package level upgrade about 5 months ago.
    have you encountered this problem before? please help me as there we have two imminent go-lives.
    thank you very much in advance.
    best regards,
    albert

    hello nick, ashok,
    thank you very much for your responses.
    i have already resolved this issue by just freeing up some space from our disks. not one of them was full though.
    i hope i would no longer encounter the error message.
    again, thank you.
    best regards,
    albert

  • Report Painter GR214 generation error - Short dump 4.6C

    While generating a report with more than twenty sections, the system short dumps with the error message GR214 pointing to  "MESSAGE_TYPE_X"                                          
    "%_T01JR0 " or "########################################" 
    "INSERT_ROW_FORMULA_NEW"                                  
    Any leads to fix this?
    The generation error happens only when I include a last line formula in the last section, Till then it is working fine.

    Hi,
    The error you are receiving could be caused by a large number of row blocks in your report definition, (you can check the report definition with report RGRRDC00). A report should not contain too many row and column blocks. It is not possible to give an upper bound for the number of row blocks (since the length of the coding depends on other parts of the report as well). However, even a complicated Report Writer or Report Painter report should not contain more than 50 row blocks, and reports with more than 100 row blocks should not be defined.
    In this case the report(s) have to be redefined. Please also refer to the note 387916 for further information regarding this issue.
    When there are more than 30 variables in a report, please have a look at the note 332091.
    Please reduce the number of row blocks in the report by using the function 'Edit' -> 'Rows' -> 'Explode' in the Report Painter
    definition. This function enables several rows to be created for one row block (in the Report Painter definition one row block is just one row). Report Painter (and Report Writer) are designed to display hierarchical reports where the rows in the few row blocks are built up using the 'Explode' function.
    regards
    Waman

  • Smartform report generation error

    Hi,
    I have a problem with a report calling a smartform. The report works perfectly on the 1 system but on the other system there is a generation error. I found that the problem lies with the following declaration:
    data: otf_info type SSFCRESCL. 
    I compared the structures on the different systems and they are identical. The only difference is the Support Package levels. The error occurs on the system with the higher support package - SAPKB64015 (basis and aba) whereas the other system is still at level 12 (SAPKB64012).
    Any ideas what is causing the generation error and what could be done to fix it?
    Regards
    Liza-Marie

    Hi ,
    I think there may be some errors in function group errors.
    Try the following :
    T/Code : SMARTFORMSEnter the name of the form> Test--> This will leads to function module --> Utilities(Menubar)-=-> Repair function group --> Repair.
    After repairing the function group --> Save and Activate.
    Then transport the Smartform to other system .
    Regards,
    Lanka

  • SID generation error

    Hi All,
    I am loading data for Sales Item for this i have enhanced the DataSource. Now while i am loading the data to DSO it is giving error while activating the DSO--SID generation error as it found some hex. values.
    To overcome this i tried with TOUPPER formula for that field but still it is giving error. So i have removed unchecked the check box 'SID generation upon activation' as i am not going to use this DSO for reporting.
    But i am transferring data to InfoCube where again it is giving the same error.
    Kindly help me out to overcome this error.

    Hi
    Always Load Master Data before Transaction data to get rid of SID Generation Error.
    And Hex Values FM -- CHAR_HEX_CONVERSION.
    http://help.sap.com/saphelp_nw70/helpdata/EN/48/b4e431c0ca11d2a97100a0c9449261/frameset.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/25/73725c700511d3aa40006094b92fad/frameset.htm
    Re: How-to convert a character to its hex value?
    Hope it helps

Maybe you are looking for