SNP Resource available capacity variance

Hi friends,
need your help??
      I am using an SNP resource with capacity 500 min per day(Bucket). but after thew SNP run when i download the optimizer log data( Transaction:/SAPAPO/SNPOPLOG) the available capacity derived from the log is for the particular day is different than the actual capacity of the resource(i.e. it is less than the actual available capacity).
    How can be this issue resolved.??
please revert back urgently

Hi kiran ,
Check for the following possible reasons :
Try this resource in SNP Heuristic and check the capacity and do levelling.
Check the Time zone and the calenders for this resource and plant.
Check the overload % and min load % rounding & down times.
See oss note 510339.
Optimizer gives the results based on the settiing you have entered,and you will only be able to analyse it better .
Regds // Digs...

Similar Messages

  • SNP Planned order not following resource bucket capacity/factory calendar

    Hi gurus,
    SCM 5.0
    I am running SNP heuristics for a product and expecting planned orders for it.  It has corresponding production data structure and multimixed resource.  The resource has an assignd factory calendar and SNP bucket capacity.  The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays.  Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource.  APO does not schedule on holidays consistent with bucket capactiy.  This is true until...
    We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday.  The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change.  However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday.  Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
    Any ideas on this? looks like a bug.

    Hi Edgar,
    Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
    Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
    Since this is a mutlimix  resource , it can also be checked if in PPDS planned order can be created on the day.
    The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
    regards
    Datta

  • CIF resource: SNP Using resources with capacity expressed in EA

    Hi,
    My enviroment is APO-SNP SCM ver 5.0.
    Planning with SNP Heuristic and Capacity leveling in weekly buckets.
    I'm having requirement to express my resource capacity in bucket resource which is measured in EA (units).
    I.e. say that my machine is having capacity 100pcs a day.
    If I create it using Workcenter in R/3 and then CIF across the only options which I have are time-based capacities. I'm limited to create my resources via CIF, as we are going to use PDS generated by BOMs and Routing from R/3.
    Can you give me some advise how I can manage this. I looked arround for solution but with no success.
    Regards,
    Stan

    Regret to tell you that you can't.
    If you are CIF'ing over PDS's which require a resource be created in R/3; you can't use any unit of measure besides time.  That is a limitation of R/3. 
    our workaround was to create a multi-mixed resource with the number of hours available per day = capacity available in units.
    So the resource could be available 100 hrs/day.
    And each unit of production consumes 1 hr.
    Ken Snyder

  • CProjects - "Available Capacity" for resources

    Dear Experts,
    We are on cProjects 4.0, Support Pack 11.
    We have a requirement by which we use a four-day-per-week calendar. Also, this calendar is required to have some holidays which are specific to our business. And this works good in our calendar.
    However, we notice that the "Available Capacity" for resources (Under Resources > Staffing) does not caluclate the available hours based on this calendar. So to say, the available capacity for resources is calculated on the basis of some different calendar. We can make changes to the availability of a resource per day (from 8 to, say, 10 hours per day). But what we have not been able to do is to have the availablity calculated on the basis of the working days available in the project calendar.
    How can we do this?
    Summary
    How can we get the application to calculate "Available Capacity" for resources on the basis of a calendar of our liking and not the system's?
    Thanks in advance.
    Regards,
    Bittu

    Hi Vivek,
    This helped and you get 6 points!!
    I could make the settings as per your suggestion and see that the 'Available' capacity for resources is now governed by the 'factory calendar' and 'hours' per day that I specify.
    However, we have a requirement by which this 'Available Capapcity' may not be governed by the the same calendar for every resource. For e.g., resource R1 may have 'Available capacity' based on calendar C1 and Resource R2 may have an 'Available Capcity' based on calendar C2. How do I make allowance for this?
    What I mean is, the settings that I have done works good but the same rule applies to all the resources. Is there a way I can make one setting applicable to one resource and another setting applicable to another resource??
    Thanks in advance.
    Regards,
    Bittu.

  • Resource Availability - for next Shift only when required

    Hi Gurus,
    How the Resources can be made available for the 2nd/3rd shift, only during a certain period. Resource should be made available for 2nd/3rd Shift as and when required period
    Since the requirement for the shift is not sure during the Master Data(Resource) creation or at the Planning phase, It can only be decided upon during the shop floor execution based on the load and the urgency of the production compeletion. Is there a way to select/extend the Shift for 2nd/3rd shifts to make the resource available, ONLY as and when required
    Appreciate your help in advance
    Regards,
    TamNen

    TamNem,
    1. How this Resource availability - Extension will get accounted in CRP
    I am not sure why you even care.  This is execution, not planning (predicting the future).  In effect, you are declaring, either upon execution or very near to the actual execution date,  that the existing plan was unworkable.  You declared a new cap plan, based on the reality of the capacity situation.  Many companies don't even bother with such niceties.
    Anyhow, these additional hours will show as available in CRP.  If you schedule your existing orders to utilize these hours, then the additional hours will be consumed, by any orders that are scheduled to consume them.
    When the Shop floor user decides in the mid-of-the day and plans to run the 2nd shift for the production completion for only one day to achieve the target, should the same procedure Master data change be done(each a day - when required)
    Who even cares?  You will confirm orders during execution, based on what actually happened, and these confirmations will consume existing capacity requirements.  Once you have confirmed your orders. why do you need to change your old Cap plan to match the consumption actuality that happened during execution?  It is all a moot point, since it has already happened.   Planning is important only to predict the future.  What is the point of changing the old (inaccurate) plan to match the reality of what actually happened?
    3. Since the production department has many number of machines(15 Machines) and all...
    what are you talking about? I definitely don't understand the question.
    Capacity plan lets you plan what you are going to do in the future.  Execution tells you what actually happened.  Who cares what machines you actually used/didn't use?  You either executed the cap plan, or you didn't.  Execution will seldom match the plan.  The only thing a planner is interested in is "how much available capacity do I  have now, and how much remaining load is there on the capacity, as of right now.  No other questions are relevant.   Previous plans are irrelevant.  Comsumption variances are irrelevant (except to help you fine-tune existing future plans).
    I don't believe there is much benefit to 'fiddling' with the previously created plan so as to make it match reality. Just execute.  If manufacturing has to work additional shifts, let them do so.  I don't believe It is really necessary to change the old plan to reflect the fact that manufacturing decided they needed to work additional shifts to meet the requirements of the cap plan..
    Rgds,
    DB49

  • Project server 2010. Troubles with resource availability

    A problem occurred while checking resource usage using PWA. 
    Using the PS 2010 
    the total number of projects about 2000, about 1600 resources (for 5 years) 
    We have a project - project1 and resource involved in it - res1 
    In the project, each week for the resource specified work (20 - 30 hours), the project is saved and published. (When publishing a project there are no errors.) 
    In MS Project and PWA in Project center values ​ per weeks are the same. Go to the resource center, choose res1 and check its work in resource availability and see that for some weeks value of work is 0, at some 1.75. some 0.462 etc. 
    For other projects work of this resource displayed normally. Moreover, for all other resources is displayed correctly in this project. 
    When re-saving project data and republishing it the situation is same. 
    This issue takes place to be for some other projects. 
    questions: 
    1 - what database of PS take the data for plotting in resource availability? 
    2 - than similar behavior can be caused? 
    3 - how possible to solve this problem? 
    Thanks for help!

    Hi,
    The resource availability in PWA-resource center is based on the Published DB data.
    In order to trouble shoot, can you check in the data grid under the resource availability graph the capacity of the resource? Indeed the availability is calculated based on work versus capacity. The capacity might vary with calendar exceptions (holidays)
    and non-working administrative time in the resource timesheet. I'd suggest that you check in detail the periods where you have this unexpected behavior and see the resource calendar and timesheets.
    Also what you can do is to open a blank project plan (be sure to check the option "load summary resources assignments when starting MS Project Pro), insert the resource, go to the resource usage and add the remaining availability and work availability.
    Then you could confirm if the data are correct or not.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Resource availability during Non-Working Hours and Weekends

    Hi Gurus,
    Aim: Make the Resource available during Non-Working Hours and Weekends
    Requirement: CRP functionality enabling
    In CRC2 I have selected capacity tab and in capacity header under 'Change Interval and Shifts' button. I have Inserted a new Interval period and given the validity from/to dates(Non-Working day - Saturday) and Saved.
    When i execute the Capacity Planning CM01, there is no change. The Resource availability still shows as "0"hrs for this particular date and for rest of the days it shows as 8hrs.
    I have checked the same even after executing the MRP, No change in Capacity Planning Overview - Still the available Capacity Showas as 0
    Please guide me, how can i use my resource during the holidays. Means make the system understand that the defined day is a working day though it is holiday as per factory calendar
    Please correct me whether am i missing any settings or i should follow some other logic
    Regards,
    Tam

    Hi Partha,
    In workdays i dont have any such option "2"
    As per standard list I could see only 3 entries in the possible values(F4) popup
    "Blank" - Working days according to factory calendar
    "0" - Non-Working days(Overrides factory Calendar)
    "1" - orking days(Overrides factory Calendar)
    I have even tried with option "0" and "1" its still the same, when i enter the period From and To date the fields for the entries Shift start and end date, workday, Shift Seq, Length of the shift, No.of shifts.........are jumping to the next line item.
    Because of which i understand that the entered values is not corresponds to the newly defined period
    Pls guide me to how to make the resource available during non working days
    Regards,
    TamNen

  • Fields for Available capacity in SAP

    We are trying to generate Z report on Availabile capacity
    Under normal transaction : by going in CR03 we can have Start time / Finish Time based on which we get operating time in hours, we need to capture the Avaialble capacity we are not getting this field in any SAP table
    Max we go in KAKO by capacity ID of resource and get Start time, Finish Time , Breaktime in Seconds & % utilization  how do i convert this in Hours,i have tried various combinations but it does not matches in CR03
    Can anyone suggest how to convert this seconds or any other table from which i can get Availability Capacity in hrs

    Dear Bhavesh,
    Check this logic,
    Available Capacity = From table KAKO take the fields BEGZT(shift start), ENDZT(shift end) and PAUSE(break time),divide this
    value by 3600 and you will get it hours.
    For example if BEGZT - 25200,then 25200/3600 = 07:00:00 start time.
    ENDZT - 54000,then 54000/3600 = 15:00:00 end time.
    Check this logic a.capacity = {(BEGZT - ENDZT) - PAUSE}NGRADAGNOR /100
    Regards
    Mangalraj.S

  • Resource Availability in Portfoio Analysis (Strategy) 2010 is Always 0

    Hi,
    I am workig with PWA 2010 and we want to use the Strategy feature.
    When I create an analysis, reach the last phase (Analyze Resource) and click on
    Requirment Details on the ribbon, I can see in the bottom window (Project Requirements) the demand that my projects generate. However, in the top pane (Resource Availability) I see 0 for all the roles for every month. Also, the coloring in
    the bottom pane is done as if I have no resources available (everythig is red) 
    I do have resources with these roles, some are named, some are generic, some have max units of 300%, 500% or 1000%.
    What is my problem?

    Hi Barak,
    Some question to verify:
    Let Project Server recalculate the Resource Capacity
    Have you modified the resource roles after you have created the Portfolio Analyses? => Recreate the Portfolio Analyses
    Make sure the 'Resource Capacity Settings' under 'Additional Server Settings' and the 'Planning Horizon and Granularity' settings for the portfolio analyses overlap.
    Could it be that all resource roles are fully allocated in all timeperiods? The Resource Availability part shows the 'remaining availability'.
    I hope this helps you to find a solution.
    Regards,
    Hans
    My EPM blog: Projectopolis

  • Available capacity in APO

    Hi,
    I have a resource for which the PLANNED DOWNTIME has been maintained as 12 hrs a day for next few months
    On top of it, the FACTORY  SHUT DOWN (this has been picked from the fact cal) has been maintained in the CAPACITY PROFILE in APO
    Logically speaking I should now see AVILABLE CAPACITY as 12 hrs  in the capacity profile in the Resource
    But I see sometimes as 12 hrs and some times as 3 hrs in the capacity profile in the Resource
    and in the planning book I am seing the available capacity as '0'
    Kindly share your interpratation , how do I look into this issue to fix
    Thanks,
    SS
    Edited by: SAPSriman on Dec 7, 2010 8:40 AM

    Hi,
    First check if the same resource in APO is maintained as external capacity or not.If the same is activated then check the resource capacity in ECC.Check the intervals and shifts.
    If the same is not true then check the capacity profiles and the avalable capacity versions maintained in resource master in APO.
    Since from factory calender resource blocking is only possible for at least a day so any availble hours is basically for resource blocking.
    Check the shift sequence.If your shift sequence is cross period the 3 hours can be coming from previous period.
    Hope the points can help you.
    regards,
    kaushik

  • Available Capacity in LTP

    Hi,
    During creation of a planning scenario during LTP, we have a facility of assigning the Available capacity versions.  Imagine, that a few versions have been defined with '01' as the active version and some Simulative what if scenrio versions.  This active version has been maintained in the relevant WC/Resource. 
    Now during the creation, I would like to assing one of the what if scenario available capacity version. But I am really not sure how the system is supposed to behave since this version is not attached to any capacities in the work centres.
    Now in case i would need to analyse the what if scenario capacities, what is it that needs to be done.
    I have tried digging in some of the SAP material but came up with nothing.
    Any pointers on how to use the Available capacity versions  and what settings needs to be done will be much appreciated.
    Regards
    Kiki

    1. SAP has given this facitliy so that we can do a simulation based on different capacities.
    2. For this first you have to maintain different version of capcity in the workcentre level
    3. in the workcentre in the capacity tab you can see version , so can create different version of capacity here .
    4. Later when you create a planning scenario then you can plan with different version and do simulation.
    kindly let me know if this resolves,else will explain in detail.
    reg

  • ECC Plan Resource Availability is Considered before Component is Available.

    Hi All,
    We have an issue with GOP and ASCP Resource Availability.
    We are using ECC plan with 'Calculate Resource Requirement' option enabled. Current version is R12.1.1
    Issue:
    Component and Resource together are required to make a subassembly.
    Component is available on 31st August. For example, resource will be used only after 31st of August as component is not available before that. GOP/CTP is considering resource availability before 31st of August (before the component is available). Resource availability is being calculated from plan run date.
    What we expect:
    Since component is available on 31st of August, resource (which is available 8 hours per day, 6 days a week) should be used from 31st of August and thus should give us completion date somewhere in first week of October (for 207.816 hours requirement of resource: 26 working days, after 31st of August) for subassembly.
    But the resource capacity availability is being considered from current date and since there is no other demand, the resource availability from today is being considred. We want the capacity to be considered from the component availability date.
    Did anyone encounter this problem before or this is an intended functionality?
    Your help is highly appreciated.
    Thanks.
    Vijay
    Edited by: user10836534 on Jun 1, 2010 5:50 PM
    Edited by: user10836534 on Jun 1, 2010 5:51 PM

    Hi Partha,
    Thanks for the reply. The resource availability is not just visible but also used by ASCP in calculations.
    For example in our case we have resource availability of 8 hours per day and inverse usage is 100 items per hour for a subassembly, there is no other demand, no supply. Subassembly lead time is 1 day. The component for the subassembly is available 12 days from today. For ATP inquiry of 8000 qty of the subassembly, the available date should be 23 days from today (Component available on 12th Day, and starts processing 800 qty per day for the next 10 days for a total qty of 8000 + subassembly lead time of 1 day).
    The ATP inquiry is suggesting availability of subassembly as 13th Day from today. Pegging shows resource requirement of 80 hours and this is shown available 10 days from today. Component is available on 12th day and it takes 1 day for the subassembly completion.
    ASCP is using resource availability from current date even if this resource cannot be used until the component is available.
    Any thoughts on this?
    Thanks.
    Vijay

  • Help about available capacity

    Hi Experts,
    I want to know the entire available capacity of my plant and also maximum how much quantity I can produce by using this available capacity, Is there any T-code or any reports?
    Please help.
    Regards,
    Imran

    Dear,
    It is possible through Rough cut planning
    Here we check the capacity for our bottel neck work center. So you have to define time for your material requried to manufacture certain quantity on this work center . Ex-enter the time to produce 1 pc
    Create Rough cut planning profile - MC35. Enter material and plant nd execute. Enter status = 4, usage = 1. Enter a resource name and double clik on that line, choose example work centre: Enter work center name, plant and unit = H.
    Enter the times required in Hours in the time buckets and save
    Create SOP plan - MC87. Enter material and plant. Execute. Enter sales and prod qty. Go to views>Capacity situation>Rough cut planning>show.
    Or in MC82, go to views->capacity situation->show
    You could display the capacity requirements at the bottom of the screen.
    Please refer this link also,
    http://help.sap.com/saphelp_46c/helpdata/en/8a/a5905c4adc11d189740000e8322d00/frameset.htm
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Project Server - Projects does not show up in the detail section of the resource availability view!!!

    Hi,
    I click resource center in PWA 2010 and select a resource; then click resource assignments and a list of projects along with the task which the selected resource is assign is listed. I then click on resource availability and set the date
    option and units for the selected resource and the resource availability and capacity is visible in the details section but not the list of projects that the resource is assign.
    How can I get the list of projects to show up in the details section under the resource name?   
    A. Williams

    Hi A. Williams,
    Could you post a screenshot of BOTH upper (graph) and lower (detailed grid) parts of our resource availability page?
    It would be very weird that you can see workload in the upper part but not in the detailed grid. This is what we need to know to help you:
    Are you not seeing at all the assignments in both graph and detail grid of the resource availability page? In this case the issue comes from your assignment, not from the resource availability page.
    Are you seeing the assignment in the graph but not in the detail grid?
    In case this is an assignment issue, some reasons could be:
    you're not looking at the right period
    date range selection has not been applied clicking on the button "apply"
    the assignments are proposed (versus committed)
    the assignment has not been publish (column publish to "yes" in MS Project Pro)
    the assignment owner is not the resource
    Here is (sorry, it is in french) my upper part (graph) with 1 resource selected, 3 weeks and a 7hrs assignment on the 2nd week (note that you have to apply the date range once selected) :
    Then the lower part (detailed grid) where is have exactly the same information (same assignments, same resources, same date range):
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Rough cut planning & available capacity

    I need one clarification, in the rough cut planning, the existing load
    is not considering for available capacity.It is considering only from
    the resource capacity.
    E.g : Avaialble capacity of for Resource A (today) is 24 hr
          One Order is created and released for 4 hr with Resource A
          As per that now my available capacity of the resource is only 20 hr
          In SOP planning view, it showing as 24 hrs.
          And If i am running the SOP today at 1400hrs for calculating the
    resource capacity. Practically my avaialble capacity is 10hrs. But
    in the system it showing as 24hrs.
    How to capture the above both requirements?
    2. Through roughcut planning we can able calcualte the cost, material and
    PRT availability also. But it is not coming the the SOP screen.
    Is it any configuration i missed out? Help me out
    Regards,
    sakthivel
    <Title of the thread has been changed. Please use meaningful title.>
    Edited by: Csaba Szommer on Nov 15, 2010 9:52 PM
    Edited by: Csaba Szommer on Nov 15, 2010 9:58 PM

    Hi!
    Available capacity means the total capacity available for use in production. Presence of an requirement will not reduce the available capacity.
    Regarding SOP. Check for the starting time of the order or requirement. See if you can schedule from the current time instead of start of the day.
    Regards,
    S.Satish Kumar

Maybe you are looking for

  • Refresh rate isn't preserved

    Hello there, I am using a 120hz monitor with a nvidia card, and I am trying to keep my refresh rate settings. I've launched nvidia-settings as root and saved the settings (which work fine for the session after setting the proper settings and pressing

  • New System Autentication

    Hi All, If connected my SAP ERP Development system to Business Objects. In SM59 the connection test is OK, and in /CRYSTAL/RPTADMIN also OK. Now the problem is that I want to connect the Productive system, that is locates in other server, diferent fr

  • How to install Distiller for FM7

    WinXP Pro SP3 FrameMaker 7.0p578 At one time, we did not want writers to have Distiller; we had a couple of people who were set up with Acrobat Pro and TimeSavers and they took care of the FM-to-PDF process. We asked the LAN team to install FM withou

  • Access, by all users,  to alocally installed applet.

    Hi, A seemingly simple question that I can't find the answer to.... How can I make it possible for all users (windows) to access a cached applet. Due to security issues, the applets need to be installed offline (into the cache)...this has been done,

  • WLC tcp port 80 access only

    Hi, One of the SSIDs in WLC 5500 (SV:7.2.103.0) is configured in web authentication mode. After authentication (local database) users can access http sites and can't access, for example, https sites. TIA