   I have come across one authorization object namely "S_PROJ_AUTH.
What is the importance of this object?
In that object, field name, PROJAUTH, system asking me to enter project number. But i know only project name. From where i can the project number for my project name?
Even i can input only 3 digit value in "Project number" field.
Plz guide me
Thnaks
Senthil

Hi Ragu,
  Sorry..plz refer the following auth object:S_PRO_AUTH (New authorizations for projects) & field:PROJAUTH(Project number).
In Field "PROJAUTH"---I need to enter 3 digit project number. But i could not find project number for my projects. Even i am not possible to enter my name of the project, since system permits upto 3 digits.
Thanks
Senthil

Similar Messages

  • Solution Manager Project

    When creating a project in Solution Manager (solar_project_admin) I am receiving an error when creating the IMG View for the remote system. The message states that I am not authorized to display the project even though I have SAP_ALL and SAP_NEW authorizations in both systems. When reading the extended help for the error (SPROJECT322) it states that I need the value 03 for the field ACTVT in the authorization object S_PROJECT, but I have confirmed that this is already set.
    It begins the process of creating the IMG in the remote system but does not complete the link back to the Solution Manager project.
    Are there any other reasons why this type of behavior might occur?

    Prince Jose
    Thank you for your suggestion, but let me provide you with a little more information to see if this is still the correct action to take.
    I currently have SAP_ALL and SAP_NEW authorizations in Solution Manager along with many different role assignments.  In the satellite systems I have the IMG_CUS_ADMIN role for managing the projects when they are published to those systems.
    In my most recent work I created a project in Solution Manager using 4 different logical components (BI, ECC, SCM, and SRM) for the systems that this project would interact with.  With my current Solution Manager security and authorizations I was able to create the IMG view from Solution Manager to the BI, SCM, and SRM systems, but received my error message described above for the ECC system.
    Based on that do you think I would still look at my security in the Solution Manager system, or a configuration in the satellite system?

  • Links  to Documentation in a Solution Manager Project

    Solution Manager Project Documentation has a feature that allows you to "link" to differnet levels of your documentation. For instance, if I attach a documentation template at the Process level of a Project and there are 10 process steps under that process, I can create links at each process step that will link to the document that I attached at the process level.
    Is there a way to automatically build these links or must I create each link manually?
    Thx

    Hi Rod,
    at least until solman version 7.0 ehp1 i'm not aware of any automatic way to do that. Maybe in the 7.1 could be any other option, maybe importing from any external tool.
    I believe that the only things you can do in a node and replicate to the subnodes are the settings in the administration tab.
    Kind regards, Fabricius

  • Migrating Solution Manager Project ?

    Hello .. has anyone had success in migrating a Solution Manager project from one server to another ? If so, can you share the details. I am aware it can be done via template, but havent tried as of yet...
    weinux

    My worry is not migration process.
    That´s why you must have a certified migration consultant on-site to do the migration. If you do it on your own and you have problems after the migration you will loose support.
    But after migration will solution manager configuration remain intact?
    Yes - it will be identical.
    Will configuration done in SOLMAN before migration, affect due to migration.Any pros and cons?
    No - apart from a different OS and database configuration that must be taken care of during the migration.
    Also Can you please suggest rough ( approx ) estimate for migration? Solution manager version 7.0 , Solaris 5.9 , oracle 10g.
    It´s impossible to tell that.
    It depends on lots of factors (processor number/speed, speed of I/O subsystem, database configuration...). A migration is usually done three times at least to get the optimal number of R3load processes and database configuration during the migration process.
    Markus

  • Exporting a Solution Manager project

    Hello Solman experts,
    My prof. wants to know if it is possible to export a solution manager project to another Solution Manager. So experts, how to do an export of an project an how to import it in another one? If there is no possibilty please tell me also!!
    Thank you for answering!

    Hi Simon,
    It is true that the transport is easy if the connection for transport between the systems is created correctly.
    But the consequences are delicate.
    E.g. a project that is assigned to a released transport request cannot be deleted.
    And there are difficulties to change the projects in both systems back to be local. Any change to the origin project needs authority to add the change to the transport if the project is not defined to be local ($TMP in transport tab).
    To avoid this problem you can copy the project first by the transaction SOLAR_PROJECT_ADMIN and then transport the copy.
    Another point of view is: If the origin project was defined to be local ($TMP in transport tab) some assigned objects may got lost (e.g. links, assigned users, testers). On the other hand: if you define the transport request first before creating objects to the project you enhance effort for maintaining the project. Because any change has to be added to the transport request. And the users need the authorities to do so.
    I hope this additional information helps you too.
    Best regards,
    Adelbert
    Edited by: Adelbert Kaub on Aug 24, 2011 7:16 PM

  • Linking solution manager projects with CHARM implementation project

    Hi Guys,
    Currently i am working in CHARM implementation project, i have created one CHARM implementation project with urgent correction and i am able to create the Transport request and release the transport request succesfully and i am able to move it to quality system successfully. But my customer is asking to link the solution manager project to CHARM implementation project.
    Earlier before implementing CHARM they have implemented project managent in solution manager, during that project they have created so many projects which are currently running, now they want those projects to be linked CHARM implementation project.
    When ever they create a transport request through CHARM they want the TP to be saved under a respective project which they are using currently. but according to my knowledge the TP can be saved under CHARM implementation project only.
    Now i want to know whether the projects created in SOLAR_PROJECT_ADMIN can be linked to CHARM implementation project. Pls give ur valuable inputs as it is very urgent.
    Thanks&Regards
    Raju

    Hello,
    We have implemented this with two systems landscape where in we have in place a Solution Manager Dev system and Solution manager Production system both are SOLMAN 4.0 with SP12. So the path for us to move the changes is from Development Systems to Production system.
    We have ChaRM between the Dev and production. We reapplied the satellite system concept. For us the Solution manager Prod is a satellite systems all the changes that we move from Development system to Production systems is tracked with necessary documentation in the ChaRM process.
    Yes, I agree with you that this is not any big magic. Working with two SOLMAN implementation, I strongly feel that SAP needs to have well rounded ChaRm processes. We have robust Change Management Process, but when we moved to ChaRM we were limited functionality of the ChaRM processes.
    I had approached and did some research on how other companies are implementing the same process. Most of them have almost the same process for tracking SOLMAN changes. I am still look out for improved process to manage SOLMA changes.
    Hope this helps!!! Thanks
    Vish

  • How to export all documents of a Solution Manager Project?

    Hello,
    I am currently trying to export all documents that exist inside a Solution Manager project (which documents these are, I can see via SI80 -> select project). That means, I need to export between 300 and 7000 documents from SAP to a MS Windows directory.
    Is there any way to do this automatically?
    My approaches so far:
    1) Use the "Knowledge Workbench" tool to connect to the Knowledge Warehouse of the Solution Manager and "check out" all documents to the specific project.
    Problem: The resulting local folder structure is horrifying and all documents are not named by their titles as seen in SAP, but named after the template that was used to create them. So flattening the folder structure would result in many, many name collisions.
    2) Using SOLAR02 to get an overview over all documents via "Environment->Project Analysis->Assignments->Documentation", and selecting everything.
    Problem: I found no download option here, only some kind of overview over all documents.
    The forum threads:
    [Re: download all document in SOLAR01]
    [Mass download of documents from SM to PC;
    didn't help either.
    I would appreciate any help.
    Thanks!
    Edited by: Andreas Seemann on Mar 2, 2011 2:15 PM

    Hello Andreas,
    You might take a peak at this link
    Export of SOLMAN-project
    SOLAR_PROJECT_ADMIN can also copy documentation, plus there is more information on  SAP Knowledge Workbench.
    Using it for the first time is a bit cryptic so they recommend reading the SAP Notes 336968 , 196078 and 817529.
    erhaps worth a view?
    Regards,
    Paul

  • Difference between a Solution Manager project, and IMG project.

    Hello,
    We are in process of installing and thereby configuring scenarios for Solman 4.
    While reading about it on help.sap.com, I came across following:
    <b>
    "<i>The Change Tracking function of Change Request Management allows you to track everything that relates to changes within the context of a Solution Manager project, or an IMG project."</i></b>
    Please help me here by clarifying difference between two.
    regards, Shantanu

    Hi Shantanu,
    Let us assume you have captured everything w.r.to an SAP Implementation project in Solution Manager and this project has gone live. Here all details relating to an SAP Project are captured in a Solution Manager Project. Solution Manager project acts as a container to hold all the details relating to the SAP Project.
    Now when this SAP Project comes in the support/maintenance phase, whenever a small change needs to be done to this SAP Solution, it will be raised as a Change Request. This change request will be captured in Solution Manager (starting from the point when the request was raised from an end user as a support message, which eventually might have evolved as a Change Request). All details about this change request, its approval workflow, task control being transferred to different roles(people), movement of the request along the transport path, everything is captured and controlled in the Solution Manager Project.
    So, we are clear about Solution Manager Project now.
    What is an IMG Project?
    For each and every component involved in this SAP project, an IMG project will be created with the same name as the Solution Manager Project in the component systems. These IMG projects in the Satellite systems are the same as the normal Project IMGs which we use in any SAP Project to hold all details relating to an SAP Project w.r.to that component.
    In the context specified by you, it has been told that any changes w.r.to a Solution Manager project or an IMG project can be tracked in CHARM. It is because any change that is requested w.r.to any component(say SRM or ECC) will result in a change in the details captured in Solution Manager project about that SAP Project, and also will result in a change in the details captured in the appropriate Project IMG (say SRM or ECC).
    Hope it is clear.
    Dont forget to reward points for useful answers.
    best regds,
    Alagammai.

  • Solution Manager project views

    Dear friends,
       In Solution Manager, t.code SOLAR_PROJECT_ADMIN, i have created IMG project & Project views. Both(IMG projects & project views) are in green colour.
    Both the IMG projects & project views are now available in R/3.
    Under project view, i have selected some SPRO activities (for example Logistics execution i have selected ) from IMG screen & also assigned the project view to one R/3 user.
    Then in SOLAR02, under configuration tab, i am giving some t.code SPRO & executing the t.code. It is taking me to R/3 but i can view the entire IMG screen instead of what i selected in project view ( I have selected only logistics execution in project view).
    Now he can make configuration in all nodes rather than what he has been assigned in project view.
    Then what is the importance of assigning project views for users?
    Please give your input to restrict the IMG views for users.
    Thanks
    Senthil

    Hi,
    Additiion to the above, please check this blogs
    Best Practice: Business Process Monitoring for Order to Cash
    Best Practice: Business Process Monitoring for Procure to Pay
    Thanks
    Jansi

  • Linking Solution Manager Project Documentation - MS Sharepoint

    Hello,
    When working on a project in Solman we upload documents as needed in each phase or scenario. This is well known to all... But we already also, have an MS Sharepoint portal sometimes with documents already stored there.
    Is there a way to include the link to sharepoint ?
    In other words.. Is there a way to utilize the folder structure provided by sharepoint in solution manager without replicating documents ?

    Hello,
    I think we found a way... Just during uploading a file to Solman, choose the option "web link", then your documentation tile will jump to the sharepoint folders.
    Thanks,,
    Edited by: Khalid Al-Tayaran on Nov 11, 2009 8:18 AM

  • Solution Manager Project Title

    Is anyone aware of a method to get the project name in the title of the screen when an associate runs Solution Manager? If you look at the standard screen it displays a generic title like "Maintenance Cycle M000000010" or "Implementation Project I000000054".
    Is anyone aware of a way (other than modifying SAP code) to get the screen to display the project title. Yes, I realize the project name is displayed in the body of the screen. We have a request to see if there's a way to make the project title more pronounced.

    Hi,
    Additiion to the above, please check this blogs
    Best Practice: Business Process Monitoring for Order to Cash
    Best Practice: Business Process Monitoring for Procure to Pay
    Thanks
    Jansi

  • Solution Manager project export / import

    Hi,
    is there any possibility to export the project files from Solution Manager, change some data in an other program and then import them back to solution manager? This whole import/export process should work automatically.
    The entire thing is to avoid that the users have to work with the Solution Manager instead of their usual and well known programs for project management.
    Regards

    Hi Andreas,
    Currently there is no possibility to perform this.
    kind regards,
    Fabricius

  • Solution Manager project - no roadmap available for CRM 7.0 EhP3

    Hi all,
    I'm setting up a new project in solution manager for an upgrade.
    However, in my roadmap selection tab, there's no roadmap for CRM 7.0 EhP3 (or even EhP2).
    Is this just not available or can/should I update this list?
    Many thanks and with kind regards,
    Yee-Tee

    Hello,
    There are two possibilities I see here.
    1-Your roadmap list is not up-to-date.
    2-There is no roadmaps for these specific product/version delivered for the solman.
    I would recommend you to first check the ST-ICO package SP level. The whole documentation content (Roadmaps, BPR, templates,...) are delivered by this component, so in order to have the complete and must up-to-date list, you'll need the latest SP-level.
    further info: Implement SAP | SAP Support Portal
    I hope this helps.
    best regards,
    Fabricius

  • SAP Solution Manager - authorizations

    Hello!
    Is there any functionality in Solution Manager for
    1. Adjust user rights per project
    - example:
    User1 has access in Project1 but no access to Project2 in same Solution Manager client
    2. Adjust user rights per part of project structure
    - example:
    User1 has access in Business scenario1 of Project1 but no access to Business scenario2 of Project1
    3. Adjust user rights per document belonging into project
    - example:
    User1 has access in Document1 of Process step1 of Project1 but no access to Document2 of Process step1 of Project1

    Thanks for the tip!
    What I was searching for was not in Change Request Management but more like Project Administration. It was found from the Solution Manager library help in Assign Authorization for Documents: 
    "You can control the access rights to documents in the project by assigning authorizations for groups of documents, e.g. you can specify that only the project management can change documentation templates. The system saves Solution Manager project documents in Knowledge Warehouse folders. Access to Knowledge Warehouse folders is controlled by the authorization object S_IWB, which is in the roles SAP_SOL_KW_ALL and SAP_SOL_KW_DIS, and in the Solution Manager Composite Rolles.
    You have role (transaction PFCG) and user maintenance authorization..."
    So, thanks for the guidance .

  • Difference between Solution manager and ASAP

    Hi All,
    Can anyone tell me what's the difference between SAP solution manager and ASAP?
    Regards
    Saroj

    ASAP stands For Accelerated SAP........its a SAP implementation methodology. It consists of Five phases---
    1. Project Preparation
    2. Business Blueprint
    3. Realization phase
    4. Final preparation phase
    5. Go live and Support
    For Solution manager u can follow this link:
    http://www.sap.com/services/pdf/BWP_SB_SAP_Solution_Manager.pdf
    ASAP and Solution Manager are tools used for managing SAP implementation and roll out project. Both supports sevral stages of the project as mention by Raj.
    The main Difference between three tools (ASAP, VSAP and Solution Manager) are as follow:
    ASAP:
    - Offline CD set with tools, content and a methodology for component-based implementation projects
    VSAP:
    - Offline CD set with tools, content and methodologies for Evaluation, Implementation and Continuous Business Improvement
    - ASAP CD set is used as a tool platform. ASAP content is included to cover the implementation phase
    Solution Manager:
    - Onsite platform to support key implementation actitivities
    - Including key ASAP concepts and tool features
    - Enhanced concepts to encompass the specifics of mySAP.com implementations
    - Integrated platform to support Implementation and operation of mySAP.com
    - Solution Manager is server based tool.
    More informaiton you can find from the following links:
    ValueSAP : https://www.service.sap.com/valuesapupdates
    Solution Manager: http://service.sap.com/solutionmanager
    some documents what is the duty of asap and solution manager i think with u can understand the difference.
    asap means,
    ASAP
    ASAP stands for Accelerated SAP. Its purpose is to help design SAP implementation in the most efficient
    manner possible. Its goal is to effectively optimize time, people, quality and other resources, using a proven
    methodology to implementation.
    ASAP focuses on tools and training, wrapped up in a five-phase process oriented roadmap for guiding
    implementation.
    The road map is composed of five well-known consecutive phases:
    • Phase 1 Project Preparation
    • Phase 2 Business Blueprint
    • Phase 3 Realization
    • Phase 4 Final Preparation
    • Phase 5 Go-Live and support
    In today's post we will discuss the first phase.
    Phase 1 : Project Preparation
    Phase 1 initiates with a retrieval of information and resources. It is an important time to assemble the
    necessary components for the implementation. Some important milestones that need to be accomplished
    for phase 1 include
    • Obtaining senior-level management/stakeholder support
    • identifying clear project objectives
    • architecting an efficient decision-making process
    • creating an environment suitable for change and re-engineering
    • building a qualified and capable project team.
    Senior level management support:
    One of the most important milestones with phase 1 of ASAP is the full agreement and cooperation of the
    important company decision-makers - key stakeholders and others. Their backing and support is crucial for a
    successful implementation.
    Clear project objectives:
    be concise in defining what your objectives and expectations are for this venture. Vague or unclear notions of
    what you hope to obtain with SAP will handicap the implementation process. Also make sure that your
    expectations are reasonable considering your company's resources. It is essential to have clearly defined
    ideas, goals and project plans devised before moving forward.
    An efficient decision making process:
    One obstacle that often stalls implementation is a poorly constructed decision-making process. Before
    embarking on this venture, individuals need to be clearly identified. Decide now who is responsible for
    different decisions along the way. From day one, the implementation decision makers and project leaders
    from each area must be aware of the onus placed on them to return good decisions quickly.
    Environment suitable for change and re engineering:
    Your team must be willing to accept that, along with new SAP software, things are going to change, the
    business will change, and information technology enabling the business will change as well. By
    implementing SAP, you will essentially redesign your current practices to model more efficient or predefined
    best business practices as espoused by SAP. Resistance to this change will impede the progress of your
    implementation.
    Building a qualified project team:
    Probably the most important milestone early in assembling a project team for the implementation. If you are
    implementing the materials management and plant maintenance modules, you need to include people from
    both of these departments. The team should also represent management as well as non management or
    "functional" personnel. Sometimes management is less aware of the day-to-day functions of an organization,
    including how implementing SAP will tactically influence those function
    ASAP- Second Phase- Business Blueprint
    SAP has defined a business blueprint phase to help extract pertinent information about your company that is
    necessary for implementation. These blueprints are in the form of questionnaires that are designed to probe
    for information that uncovers how your company does business. As such, they also serve to document the
    implementation. Each business blueprint document essentially outlines your future business processes and
    business requirements. The kinds of questions asked are germane to the particular business function, as
    seen in the following sample questions:
    1) What information do you capture on a purchase order?
    2) What information is required to complete a purchase order?
    Accelerated SAP question and answer database:
    The question and answer database (QADB) is a simple although aging tool designed to facilitate the creation
    and maintenance of your business blueprint. This database stores the questions and the answers and
    serves as the heart of your blue print. Customers are provided with a customer input template for each
    application that collects the data. The question and answer format is standard across applications to
    facilitate easier use by the project team.
    Issues database:
    Another tool used in the blueprinting phase is the issues database. This database stores any open concerns
    and pending issues that relate to the implementation. Centrally storing this information assists in gathering
    and then managing issues to resolution, so that important matters do not fall through the cracks. You can
    then track the issues in database, assign them to team members, and update the database accordingly.
    ASAP Phase- 3 - Realization:
    With the completion of the business in phase 2, "functional" experts are now ready to begin configuring SAP.
    The Realization phase is broken in to two parts.
    1) Your SAP consulting team helps you configure your baseline system, called the baseline configuration.
    2) Your implementation project team fine-tunes that system to meet all your business and process
    requirements as part of the fine tuning configuration.
    The initial configuration completed during the base line configuration is based on the information that you
    provided in your blueprint document. The remaining approximately 20% of your configuration that was not
    tackled during the baseline configuration is completed during the fine tuning configuration. Fine tuning
    usually deals with the exceptions that are not covered in baseline configuration. This final bit of tweaking
    represents the work necessary to fit your special needs.
    Configuration Testing:
    With the help of your SAP consulting team, you segregate your business processes into cycles of related
    business flows. The cycles serve as independent units that enable you to test specific parts of the business
    process. You can also work through configuring the SAP implementation guide (IMG). A tool used to assist
    you in configuring your SAP system in a step-by-step manner.
    Knowledge Transfer:
    As the configuration phase comes to a close, it becomes necessary for the Project team to be self-sufficient
    in their knowledge of the configuration of your SAP system. Knowledge transfer to the configuration team
    tasked with system maintenance (that is, maintenance of the business processes after Go-live) needs to be
    completed at this time.
    In addition, the end users tasked with actually using the system for day-to-day business purposes must be
    trained.
    ASAP Methodology - Phase 4 - Final Preparation:
    As phase 3 merges into phase 4, you should find yourselves not only in the midst of SAP
    training, but also in the midst of rigorous functional and stress testing. Phase 4 also
    concentrates on the fine tuning of your configuration before Go-live and more importantly, the
    migration of data from your old system or systems to SAP.
    Workload testing (including peak volume, daily load, and other forms of stress testing), and
    integration or functional testing are conducted to ensure the accuracy of your data and the
    stability of your SAP system. Because you should have begun testing back in phase 2, you do
    not have too far to go until Go-live. Now is an important time to perform preventative
    maintenance checks to ensure optimal performance at your SAP system.
    At the conclusion of phase 4, take time to plan and document a Go-live strategy. Preparation for
    Go-live means preparing for your end-users questions as they start actively working on the new
    SAP system.
    ASAP - Phase 5 - Go-live and Support:
    The Go-live milestone is itself is easy to achieve; a smooth and uneventful Go-live is another
    matter altogether. Preparation is the key, including attention to what-if scenarios related not only
    to the individual business processes deployed but also to the functioning of technology
    underpinning these business processes and preparation for ongoing support, including
    maintenance contracts and documented processes and procedures are essential
    solutionmanager means,
    SAP Solution Manager
    Purpose
    The SAP Solution Manager supports you throughout the entire lifecycle of your solutions, from the Business Blueprint thru configuration to production operation. It provides central access to tools methods and preconfigured content, that you can use during the evaluation, implementation, and productive operation of your systems.
    Features
    Implementation of the mySAP Business Suite
    • All phases of the implementation project (Business Blueprint, Configuration) are performed centrally in the Solution-Manager system.
    • Central project documentation repository in the Solution Manager
    • Integrated Project Administration allows you to manage planning schedules, human resources and other project data.
    Customizing Synchronization
    • The Customizing Scout, with which you can compare customizing in various SAP components, e.g. an ERP system with SAP MDM
    • The Customizing Distribution, with which you can synchronize customizing in various SAP components.
    Test
    • You can use the Test Workbench to organize and perform tests at the end of a project phase.
    • Reuse of the project structure for process-oriented tests
    Global rollout
    Integrated authoring environment, with which customers and partners can create their own templates, which they can reuse in subsidiaries, e.g. in a global rollout
    E-Learning management
    Creation of training material and learning maps (computer-supported self-tuition courses) to train end users after the implementation of new functions
    Solution Monitoring
    • Central system administration
    • Analyze your system landscape with Service Level Reporting
    • System monitoring in real time
    • Business Process Monitoring
    Services
    Access to programs and Services, which help you to monitor and optimize the performance and availability of your system landscapes, and minimize your operational system risks
    Service Desk
    Solution support with workflow to create and handle problem messages
    Change Management
    Management of change requests, with workflow for the monitoring and audit of changes and transports in your system landscape, with the Change Request Management.
    See also:
    • Projects
    • Solution Monitoring
    SAP Solution Manager Roles
    Authorization Concept
    • Project Authorizations
    The following composite roles contain the authorizations required for the tasks to be performed in a project:
    &#9675; Project Leader
    &#9675; Application Consultant
    &#9675; Development Consultant
    &#9675; Technical Consultant
    There are individual roles for Roadmap administration.
    • Production Authorizations
    Production authorizations are in individual roles for the functions:
    &#9675; Solution Directory
    &#9675; Solution Monitoring
    &#9675; Service Data Control Center
    &#9675; Service Desk
    &#9675; Corporate Functionality
    &#9675; Solution Manager Diagnostics
    &#9675; Solution Reporting
    Use
    Adjust the SAP Solution Manager roles to your requirements.
    Overview of Roles in Solution Manager
    If you use trusting-trusted RFC connections, assign the authorization profile S_RFCACL to the user, as well.
    Scenario Role
    Implementation and Distribution SAP_SOL_PM_COMP
    SAP_SOL_AC_COMP
    SAP_SOL_BC_COMP
    SAP_SOL_TC_COMP
    SAP_SOL_RO_COMP
    SAP_SOL_RE_COMP
    SAP_SOL_LEARNING_MAP_DIS
    SAP_DMDDEF_DIS
    Implementation and Distribution (Roadmaps) SAP_RMDEF_RMAUTH_EXE
    SAP_RMDEF_RMAUTH_DIS
    Implementation and Distribution (E-Learning Management) SAP_SOL_TRAINING_EDIT
    Service Desk (Service Desk) SAP_SUPPDESK_ADMIN
    SAP_SUPPDESK_PROCESS
    SAP_SUPPDESK_CREATE
    SAP_SUPPDESK_DISPLAY
    Service Desk (Corporate Functionality) SAP_SUPPCF_ADMIN
    SAP_SUPPCF_CREATE
    SAP_SUPPCF_PROCESS
    Service Desk (Issue Tracking) SAP_SV_SOLUTION_MANAGER
    SAP_SV_SOLUTION_MANAGER_DISP
    SAP_SUPPDESK_ADMIN
    SAP_SUPPDESK_PROCESS
    SAP_SUPPDESK_DISPLAY
    Change Request Management (Schedule Manager; Service Desk, cProjects)
    SAP_CM_CHANGE_MANAGER
    SAP_CM_DEVELOPER_COMP
    SAP_CM_TESTER_COMP
    SAP_CM_OPERATOR_COMP
    SAP_CM_PRODUCTIONMANAGER_COMP
    SAP_SOCM_REQUESTER
    SAP_CM_ADMINISTRATOR_COMP
    Solution Monitoring
    (Service Data Control
    Center)
    SAP_SDCCN_ALL
    SAP_SDCCN_DIS
    SAP_SDCCN_EXE
    Solution Monitoring
    (Solution Directory)
    SAP_SOLMAN_DIRECTORY_ADMIN
    SAP_SOLMAN_DIRECTORY_EDIT
    SAP_SOLMAN_DIRECTORY_DISPLAY
    Solution Monitoring
    (Operations)
    SAP_SV_SOLUTION_MANAGER
    SAP_SV_SOLUTION_MANAGER_DISP
    SAP_SETUP_DSWP
    SAP_SETUP_DSWP_SLR
    SAP_SETUP_DSWP_SM
    SAP_SETUP_DSWP_BPM
    SAP_SETUP_DSWP_CSA
    SAP_OP_DSWP
    SAP_OP_DSWP_SLR
    SAP_OP_DSWP_SM
    SAP_OP_DSWP_EWA
    SAP_OP_DSWP_BPM
    SAP_OP_DSWP_CSA
    Solution Reporting SAP_SOL_REP_ADMIN
    SAP_SOL_REP_DISP
    Solution Manager Diagnostics SAP_SMDIAG_WIZARD
    SAP_SMDIAG_TEMPLATE
    Cf.:
    &#9679; Overview of Roles and Profiles in Satellite Systems
    &#9679; SAP Solution Manager 4.0 configuration guide
    &#9679; SAP note 834534
    &#9679; SAP note 803142
    Overview of Roles and Profiles in the Satellite Systems
    Use the profiles below for SAP R/3 Release before SAP Web Application Server 6.10. Use the profiles below from SAP R/3 Release SAP Web Application Server 6.10.
    If you use a trusting-trusted RFC connection, assign the authorization profile S_RFCACL to the user, as well.
    Scenario Roles (Release > 6.10) Profile ( SAP_S_CUS_CMP S_CUS_CMP Data read access
    SAP_S_CMSREG S_CMSREG Central system repository data
    SAP_S_BDLSM_READ S_BDLSM_READ SDCCN data
    Adjust Roles and Profiles
    Before you assign SAP standard roles and profiles to users, copy and specify them.
    SAP delivers roles and profiles with default values. If they are missing, you must set the values in the authorization objects yourself. Proceed as follows:
    1. Load the roles/profiles from client 000 into your target client. You can:
    &#9675; Transport client 000 into your target client (roles and profiles)
    &#9675; Upload und Download (for roles in transaction PFCG)
    &#9675; RFC connection in transaction PFCG (for roles; menu path: MENU ® READ FROM OTHER SYSTEM WITH RFC). In this case, you must have set-up the RFC connection (transaction SM59).
    2. Copy the roles/profiles into your namespace.
    a. Choose Role Maintenance (transaction PFCG).
    b. Enter a role name and choose Copy Role.
    c. Enter the name of the new role in the To Role field.
    d. Choose Copy All.
    e. Save.
    3. Complete missing values in the authorization objects.
    a. Choose the Authorizations tab.
    b. Choose ChangeAuthorization Data.
    c. Enter your own values for the authorization objects, or double-click on the yellow traffic light.
    The authorization objects appear with a green traffic light.
    d.
    When you double-click on the yellow traffic light, the value “*” appears. This grants full authorization for this field of the authorization object.
    e. Save.
    f. Generate the authorization profile.
    4. Assign the role to users.
    a. Choose the Users tab.
    b. Enter the user names.
    c. Choose User Adjustment.
    d. Save.
    You can also assign the roles to the users, in the user maintenance (transaction SU01).
    e.
    Project Authorization
    Roles
    The roles in the SAP Solution Manager are composite roles, which contain individual roles, which in turn contain authorizations for individual functions, e.g. for the Business Blueprint.
    The following composite roles contain the central authorizations which they require for projects, and can be tailored to suit individual projects:
    &#9679; Project leaders are responsible for organizing and planning the project, and monitoring costs and deadlines.
    &#9679; Application consultants consultants are responsible for business content and the documentation of operational activities. This composite role has limited authorization and is intended for project members who need to be adjusted individually.
    &#9679; Development consultants are responsible for the development of customer-specific programs and authorizations.
    &#9679; Technical consultants are responsible for installing systems and providing technical support to users.
    &#9679; Display user/Read only : contains SAP Solution Manager display/read only authorization.
    &#9679; Read authorization depending on status in Document Management : only contains read authorization per status in Knowledge Warehouse Document Management
    See also:
    &#9679; Solution Manager Roles Overview
    &#9679; Overview of Roles and Profiles in Satellite Systems
    &#9679; SAP Solution Manager 4.0 configuration guide
    &#9679; SAP note 834534 (Roles in the Solution Manager)
    &#9679; SAP note 803142 (Roles in Satellite Systems)
    Project Manager
    Technical name: SAP_SOL_PM_COMP
    Tasks
    Project managers are responsible for the realization of the desired project results and the daily management of the project. They anticipate deviations from the project direction and carry out the necessary corrective measures immediately. Project managers should also understand the integration of the business processes within the enterprise.
    Project managers are also members of the steering committee. They have decision-making authority in matters concerning the program and budget. He forwards strategic questions to the sponsor in order to make joint decisions.
    Activities in SAP Solution Manager
    The main responsibilities of the project manager include:
    • Organizing the entire project
    • Developing strategies and procedures for an efficient SAP implementation
    • Developing and maintaining the time schedule for the implementation project
    • Finalizing and managing the project scope, budget and deadlines in accordance with the approved plans
    • Assigning and managing resources
    • Monitoring project progress on a weekly basis
    • Carrying out evaluations and analyses
    • Carrying out a formal review at the end of each phase
    • Clarifying open issues in good time
    • Reporting regularly to the review committee on the progress and status of the project
    • Representing the project internally and externally
    • Giving status updates to the whole project team
    Project managers can also copy content from a ValueSAP Edition 2 project into an SAP Solution Manager project. See the migration tool documentation.
    Notes on Tailoring
    If you require additional authorization, you can use the role SAP_BC_CUS_ADMIN: It contains authorization for the administration of customizing projects in the component systems.
    The SAP Solution Manager configuration guide contains further information about authorizations in the component systems.
    Integration
    The project manager defines the content and the time frame of an implementation project, manages resources and monitors project progress. The application consultant reports to him and supports him in an administrative function.
    Application Consultant
    Technical name: SAP_SOL_AC_COMP
    Tasks
    Application consultants are responsible for making sure that the Business Blueprint and software configuration are tailored to the business processes and that analysis and report requirements are fulfilled. They use their knowledge of proven business procedures to support them in these tasks. Application consultants also function as advisers and work closely with the rest of the project team.
    They also work in close cooperation with legacy system experts, when extraction of legacy data is necessary.
    Activities in SAP Solution Manager
    The main responsibilities of the application consultant include:
    • Supporting definition and modeling of business processes
    • Checking how the business model works with the SAP products
    • Configuring the software to suit the required business processes and to meet analysis and report requirements
    • Determining the global and local standardization requirements
    • Determining requirements for organizational change in the enterprise
    • Supporting knowledge transfer to other project team members
    • Supporting organization and performance of tests
    • Defining requirements for authorization profiles and access authorizations
    • Analyzing statistical performance and passing on recommendations for improvement to support
    • Creating and developing data solutions and strategies to meet the requirements of the corresponding SAP component (for example, APO, BW, CRM)
    • Creating end user training materials for the new functions
    The application consultant is not responsible for:
    • The technical implementation of the solution
    • The programming of interfaces and other developments
    • Recurring problems with the quality of data (problems with data quality should be passed on to the project manager)
    Notes on Tailoring
    This role only contains basic functions. The following roles are available for additional authorizations:
    • SAP_BC_CUS_CUSTOMIZER contains authorizations for working with IMG activities.
    The following role is useful for the application components:
    • SAP_BC_CUS_CUSTOMIZER
    Integration
    Application consultants are responsible for the development of business content and the documentation of operative activities in accordance with the appropriate standards. The development consultant develops customer-specific programs and their authorizations.
    Development Consultant
    Technical name: SAP_SOL_BC_COMP
    Tasks
    Development consultants work with the project manager and the application consultant on the planning and organization of the authorization concept. They also perform developmental tasks and customer-specific developments.
    Activities in SAP Solution Manager
    The main responsibilities of the development consultant include:
    • Organizing authorizations
    • Developing ABAP programs, for example, interfaces, forms, or modifications
    • Working with the ABAP Workbench
    Notes on Tailoring
    The following roles are available for additional authorizations:
    • SAP_BC_DWB_ABAPDEVELOPER contains authorization for implementing new applications and enhancements and for changing and modifying standard applications using the tools and services provided in the ABAP Workbench.
    • SAP_BC_TRANSPORT_ADMINISTRATOR contains all authorizations for the Change and Transport System
    Integration
    Development consultants work for the project manager and the application consultant and carry out programming tasks, in contrast to technical consultants who act as system administrators and are responsible for installing systems and providing technical support to users.
    Technical Consultant
    Technical name: SAP_SOL_TC_COMP
    Tasks
    Technical consultants plan the technical requirements for a project with the project manager and the manager of the technical team and then carry out the required technical tasks in the system.
    Depending on the scope and complexity of the implementation, technical consultants may work in several areas, for example, system administration, database administration, network administration, operating system administration, development of cross-application components, or ABAP development.
    For international projects, technical consultants also manage consultancy in the following areas:
    Country-specific business requirements and country-specific SAP software requirements
    Language-specific or codepage-specific requirements
    Time-zone issues
    Activities in SAP Solution Manager
    The main responsibilities of the technical consultant include:
    Setting up and installing the system landscape
    Managing the system landscape and the corresponding transport landscape
    Providing support and advice in all technical questions during an implementation project
    Giving daily updates on the technical direction of the project including communicating deviations in the project
    Developing and realizing the Cutover Plan before going live
    Communicating effectively with the business process team
    Transferring knowledge effectively to employees in system administration
    In order to be able to carry out these tasks, the technical consultant should meet the following requirements:
    A sound knowledge in the areas of databases, networks, programming and Internet technology
    A sound knowledge of the SAP solutions
    Notes on Tailoring
    The following roles are available for additional authorizations:
    SAP_BC_RRR_SAA_ADMIN provides the authorization for executing all the tasks in the System Administration Assistant.
    Integration
    The technical consultant acts as a system administrator and is responsible for installing systems and providing technical support to users, in contrast to the basis consultant who works under the instruction of the project manager and the application consultant and carries out programming tasks.
    Read Authorization by Document Status
    Technical name:
    Use the specified individual role to:
    &#9679; display business process scenarios, business processes steps, etc. of your solution, in the Solution Directory.
    Integration
    Use the Solution Monitoring role SAP_SV_SOLUTION_MONITORING_DISP to display the Solution Directory and sessions in Solution Monitoring.
    Adjustment
    Adjust Roles and Profiles
    Solution Monitoring Roles
    Tasks
    Authorizations specified for the Solution Monitoring in the SAP Solution Manager:
    for the Solution Monitorin sessions, classified by the areas Operations Setup and Operations
    general individual role to display all sessions
    Display all Sessions
    general individual role to edit all sessions
    Edit all Sessions
    Activities
    Authorizations are assigned to the roles. Specify user access to the session. There are the following authorizations:
    A The user with the role has full authorization for the transaction or session.
    D The user with the role can call the transaction or session in display mode.
    N The user with the role has no authorization for the transaction or session.
    Operations Setup session authorizations
    Individual role Service Level Reporting System Monitoring Central Administration Business Process Monitoring
    SAP_SETUP_DSWP A A A A
    SAP_SETUP_DSWP_SLR A N N N
    SAP_SETUP_DSWP_SM N A N N
    SAP_SETUP_DSWP_CSA N N A N
    SAP_SETUP_DSWP_BPM N N N A
    Operations session authorizations
    Individual role Early Watch Alert Service Level Reporting System Monitoring Central Administration Business Process Monitoring
    SAP_OP_DSWP A A A A A
    SAP_OP_DSWP_EWA A N N N N
    SAP_OP_DSWP_SLR D A N N N
    SAP_OP_DSWP_SM N N A (1) N N
    SAP_OP_DSWP_CSA N N N A (1) N
    SAP_OP_DSWP_BPM N N N N A
    SAP_SV_SOLUTION_MANAGER_DISP session authorization
    Individual role Early Watch Alert Service Level Reporting System Monitoring Central Administration Business Process Monitoring
    SAP_SV_SOLUTION_ MANAGER_DISP D D D D D
    SAP_SV_SOLUTION_MANAGER session authorization
    Individual role Early Watch Alert Service Level Reporting System Monitoring Central Administration Business Process Monitoring
    SAP_SV_SOLUTION_ MANAGER A A A A A
    (1) – from Release 3.20 SP02
    Cf.:
    Overview of Roles and Profiles
    SAP Solution Manager 3.2configuration guide
    SAP note 625773
    Notes on Tailoring
    You can use and combine the individual Solution Monitoring roles individually, according to your requirements.
    Special authorizations for specific checks in individual sessions, are described in the online documentation of the sessions:
    See also:
    Set-Up Central System Administration
    Using business process monitoring
    Integration
    If you need authorization for specific areas in the SAP Solution Manager, in addition to the authorizations for Solution Monitoring, use the associated individual roles with the specific authorizations:
    Change Request Management
    Service Desk
    Service Data Control Centre
    Solution Directory
    General Administration and Display Authorization
    Technical name: SAP_SV_SOLUTION_MANAGER
    Technical name: SAP_SV_SOLUTION_MANAGER_DISP
    Tasks
    Authorizations are assigned to the roles. Specify user access to the session. The following authorizations are available for your project:
    A The user with the role has full authorization for the transaction or session.
    D The user with the role can call the transaction or session in display mode.
    N The user with the role has no authorization for the transaction or session.
    Activities in
    Both individual roles have full authorization for the sessions in their areas.
    If you only assign one of the roles to a user, the system only offers the user this area in the system interface.
    They have display authorization for other transactions, according to the requirements of the session types:
    &#9632; SDCCN (Service Data Control Centre) for SAP EarlyWatch Alert and Service Level Reporting
    &#9632; SOLMAN_DIRECTORY (Solution Directory) for business process monitoring
    Special authorization objects
    Authorization Object Activity Meaning
    D_SOL_VIEW 20 (Operations) Determines which area can be processed and displayed in the SAP Solution Manager.
    D_SOLMANBU A (Bundle ID) Restricts processing by sessions.
    &#9632; SDCCN (Service Data Control Centre) for Service Level Reporting
    &#9632; SOLMAN DIRECTORY (Solution Directory) for business process monitoring
    Special authorization objects
    Authorization Object Activity Meaning
    D_SOL_VIEW 10 (Operations Setup) Determines which area can be processed and displayed in the SAP Solution Manager.
    D_SOLMANBU A Restricts processing by sessions.
    Activities in the session type roles
    &#9679;
    Functional roles
    Role Technical name Bundle ID Further explanation
    Operations Setup
    Service Level Reporting SAP_SETUP_DSWP_SLR EWA_CUST Additional display authorization for the transaction SDCCN (Service Data Control Centre)
    System monitoring SAP_ SETUP DSWPSM SOL_MON Additional authorization to call the Solution Manager Diagnostics wizard
    Central System Administration SAP_ SETUP_DSWP_CSA SOL_CSA Authorization object S_SAA_ADMI controls authorizations for customizing
    checks.
    Business process monitoring SAP_SETUP_DSWP_BPM BPM_JOBM
    CP_BPM
    CP_BPM_R
    SOL_BPMO
    Additional display authorization for the Solution Directory
    Operations
    SAP EarlyWatch Alert SAP_OP_DSWP_EWA EW_ALERT Additional full authorization for the transaction SDCCN (Service Data Control Centre)
    Service Level Reporting SAP_OP_DSWP_SLR EW_CONS Additional display authorization for the transaction SDCCN (Service Data Control Centre)
    Central system
    administration
    SAP_OP_DSWP_CSA SOL_CSA
    System
    monitoring
    SAP_OP_DSWP_SM SOL_MON Additional authorization to call the Solution Manager Diagnostics wizard
    Business process
    monitoring
    SAP_OP_DSWP_BPM BPM_JOBM
    CP_BPM_R
    SOL_BPMO
    Additional display authorization for the Solution Directory
    &#9632;
    Adjustment
    You can adjust the roles to your requirements.
    If you also need authorization to display the Business Process MONITORING session, as well as the functional role for Service Level reporting in Operations , to check the business processes for the Service Level report, you can:
    i. copy the authorization object D_SOLMANBU into the role and adjust it to your requirements (activity: 1; bundle ID: BPM_JOBM; CP_BPM_R; SOL_BPMO)
    ii. give the user the role and adjust the authorization object D_SOLMANBU to your requirements (activity 1).
    Integration
    You can combine the functional roles with other roles in the area:
    &#9679; Service Desk
    &#9679; Change Management
    &#9679;
    If you want to create a Service Desk message from a Business Process MONITORING session, you need the role for the user in a message system , as well as the functional role for business process monitoring .
    The online documentation for the sessions describes the scenarios in more detail.
    Solution Reporting Roles
    Technical name: SAP_SOL_REP_ADMIN
    Technical name: SAP_SOL_REP_DISP
    Tasks
    The individual roles administer and display Solution Reporting.
    Activities in
    Tasks
    The specified role sets up service connections to SAP.
    Adjustment
    Adjust Roles and Profiles
    Simple way to differentiate is ASAP is a methodology for SAP Project Implementation where as Solution Manager is a document repository to store the documentation that u will create during all phases of the project.