SPAM is hangs  XPRA_EXECUTION Phase

Hi Gurus,
I have stucked in XPRA_EXECUTION phase. The TP
ended with return code 0008 while implementing the sapkb70012 patch for SAP_BASIS in ECC system.
SPAM is hangs  XPRA_EXECUTION Phase.I see in status of Support Package :The import was stopped, since an error occurred.
Error in phase - XPRA_EXECUTION
Reason for error - TP_STEP_FAILURE
Return code - 0008
Error message - OCS package SAPKB70012, tp step R, return code 0008.
Could please Advise the Solution for the issue.
Appretiate you help.
Thanks
Anils

Hi
See below is the log for error code 0008 in SAPRB70012.
3 EPU182 Post-processing for &2"ACGR" &3"SAP_XI_BPE_ADMINISTRATOR_ABAP" was already performed successfully earlier&1"R3TR"
3 EPU182 Post-processing for &2"ACGR" &3"SAP_XI_BPE_CONFIGURATOR_ABAP" was already performed successfully earlier&1"R3TR"
3 EPU182 Post-processing for &2"ACGR" &3"SAP_XI_BPE_MONITOR_ABAP" was already performed successfully earlier&1"R3TR"
3 EPU182 Post-processing for &2"ACGR" &3"SAP_XI_BPE_SERV_USER" was already performed successfully earlier&1"R3TR"
3 EPU182 Post-processing for &2"ACGR" &3"SAP_XI_BPE_SERV_USER_MAIN" was already performed successfully earlier&1"R3TR"
3 EPU123 Post-import method "PRGN_AFTER_IMP_ACTGROUP_ACGR" completed for "ACGR" "L", date and time: "20080206084243"
2 EPU122XPost-import method "RH_ACTIVATE_PDOBJECT_AFTER_IMP" started for "PDST_BASE" "T", date and time: "20080206084243"
3 EPU182 Post-processing for &2"TDAT" &3"PDST_BASE" was already performed successfully earlier&1"R3TR"
3 EPU123 Post-import method "RH_ACTIVATE_PDOBJECT_AFTER_IMP" completed for "PDST_BASE" "T", date and time: "20080206084243"
2 EPU122XPost-import method "SRT_REG_AFTER_IMPORT" started for "SRTD" "L", date and time: "20080206084243"
3 EPU182 Post-processing for &2"SRTD" &3"8A0A000A416FA34EBD449DF66C50649B" was already performed successfully earlier&1"R3TR"
3 EPU123 Post-import method "SRT_REG_AFTER_IMPORT" completed for "SRTD" "L", date and time: "20080206084243"
2 EPU122XPost-import method "SUSR_AFTER_IMP_PROFILE" started for "SUSPR" "T", date and time: "20080206084244"
3 EPU182 Post-processing for &2"TDAT" &3"SUSPR" was already performed successfully earlier&1"R3TR"
3 EPU123 Post-import method "SUSR_AFTER_IMP_PROFILE" completed for "SUSPR" "T", date and time: "20080206084244"
2 EPU127 Post-import methods of change/transport request "SAPKB70012" completed
2 EPU128      Start of subsequent processing ... "20080206084214"
2 EPU129      End of subsequent processing... "20080206084244"
2 EPU110XExecute reports for change/transport request: "SAPKB70012"
4 EPU111    on the application server: "DRIECCDEV"
3 ETP000
3 ETP000 **************************************************
3 ETP000
2 EPU117 Reports for change/transport request "SAPKB70012" have been executed
2 EPU118      Start of................ "20080206084244"
2 EPU119      End of.................. "20080206084244"
1 ETP162 EXECUTION OF REPORTS AFTER PUT
1 ETP110 end date and time   : "20080206084244"
1 ETP111 exit code           : "8"
1 ETP199 ######################################
Regards
Anilsai

Similar Messages

  • Spam is hanging in phase IMPORT_PROPER

    Hi!
    I am facing with hanging SPAM error in phase IMPORT_PROPER (patch of SAPKB70013 - SAPKB70016).
    The SPAM patch terminates after a few sec. in DDIC activation action.
    I have looked into log file and founded folllowing:
    The job RDDEXECL terminated with error.
    The reason seems to be sysntax error in program "CL_PROXY_SERVICE=======CP".
    Futhermore I could detect that table SI_WD_FIRST_MAIN_SCREEN cannot be activated.
    Can some one help me to solve this problem?
    Of great interest was the following:
    rescedule possibilities of job RDDEEXECL in order to contibue patch
    start of SPAM or tp-commando by ignoring this error
    Thank you very much!
    Thom

    Moved to NW Admin...

  • Spam error in xpra_execution phase

    hello experts,
             I am applying SAP BASIS PATCH (SAPKB70011) , I got stuck in EPRA_EXECUTION phase.
             It is going on running for more then 10 hours.
             i had restarted the import but still it is showing the same status.
             it is not writing any logs, I checked in SM50 it shows ON HOLD reason RFC, report SAPLSTPA.
             when i checked in SM66 it says CPIC STOPPED.
            I had even tried importing the patch in FOREGROUND, but in status bar it shows "TP BUFFER PREPARED OK " and going on running.
            unable to resolve the issue.
    any suggestions
    thanks and regards
    kavitha

    Hi,
    Best thing is to raise an oss messasge to SAP,while applying support packages you should not play around.
    I think you are applying on a windows system on you would be on oracle 10g or higher version,some of my friend faced the same probelm SAP has suggested to change some memory parameters which i am not very sure.
    Regards,
    Vamshi.

  • Error in XPRA_EXECUTION PHASE on SAINT transacction installing BPC 7.5

    Hi 
    I am installing Bussines Planning & Consolidation 7.5 on an Netweaver 7.01 with EHP1 (enhacement package 1) system but when I used SAINT transacction to install the ADDON for this ABAP component . First I received a message about some "conficts" between some ADDOns so I had to applied an CRT (confict resolution transport) support package to resolve the issue
    But the saint transacction stopped on the XPRA_EXECUTION phase and the log message talk about some "BC-SRV-NUM" (number Range Managment) in some table values conteined invalid key number range object values
    I found the 1467470 note to fix the issue , I tried to use SNOTE to implemented it but can not be implemented.
    Can someone help  give me some advices to this issue?
    Thanks a lot for your time
    Regards

    Hi Salman
    I understand your issue because the installation guide is not enough clear.
    Look
    1) Once you installed the ADD-ON CPMBPC on ABAP and follow the installation guide
    You have to create on ABAP tier 3 communications data users (user,admin, sysadmin)  like guide says and at the end of it , you have to run UJA3_WRITE_SYS_USERS program on se38 and write:
    domain windows or local group windows\bpc_user  -->  for example  GGBIDBPC\bpc_user
    domain windows or local group windows\ bpc_admin  -->  GGBIDBPC\bpc_admin
    domain windows or local group windows\bpc_sysadmin  --> GGBIDBPC\bpc_sysadmin
    you should use Domain windows to ensure security environment about users like password or expiration rules
    2) On .NET tier when your are installing the BPC Server you have to entry at first time  just one user (sysadmin) using the same format:
    Domain or local group windows\bpc_sysadmin -->  GGBIDBPC\bpc_sysadmin
    later you will prompt on next screens enter the System Administrator, Administrator, and User (user IDs), together with their passwords that were created on step 1.
    The reality is just sysadmin user is used to BPC configuration on ABAP and .NET tiers
    I hope this information be useful
    Regards
    Luis Antonio Aguirre

  • Error in XPRA_EXECUTION phase in instalation BI_CONT 3.53

    Hello,
    After installing SAP Netweaver 04 as ABAP i am Installing Add-on
    BI_CONT Rel.353 : Import of the queue -
    via SAINT Tcode.
    Now it is in error in XPRA_EXECUTION Phase of pkg
    SAPKIBIFQ4 BI_CONT 353: patch 0014.
    Error is in Method Execution step:
    InfoObject 0GRC_CSEOWR, version D being deleted, (basic char. not
    found)
    Start of the after-import method for object type R3TR DTMP ( )
    Errors occurred during post-handling RS_AFTER_IMPORT_D for DUPD L
    RS_AFTER_IMPORT_D belongs to package RS
    The errors affect the following components:
    BW-WHM (Warehouse Management)
    Post-import method RS_AFTER_IMPORT_D completed for DUPD L, date and
    time: 20080103122305
    Pls help me ASAP to resolve this error.
    Regards,
    Ankita

    Hi,
    I solved this problem after implementing
    Note 1083886 - Method IF_FDT_EXPRESSION~IS_GENERATING is not implemented.
    is thsi dosent work try restarting the queue again.
    Kind regards,
    Vamsi

  • Error in XPRA_EXECUTION phase while upgrading patch in solman 7.0.

    Hi all,
    I was upgrading solman system( 7.0 ) from patch level 10 to patch level 13 , while upgrading it throwed error in XPRA_EXECUTION phase. Error is in SAPK-40003INCPRXRPM and SAPK-40004INCPRXRPM.
    Error log is as given below :
    Post-import method SWO_OBJTYPE_AFTER_IMPORT started for SOBJ L, date and time: 20090415070141
    Object type 'BUS2178' generated successfully
    Object type 'BUS2177' generated successfully
    Object type 'BUS2176' generated successfully
    Object type 'BUS2175' could not be generated
    The type 'DPR_SCHEDULING' is unknown.
    Object type 'BUS2174' could not be generated
    The type 'DPR_SCHEDULING' is unknown.
    Object type 'BUS2173' could not be generated
    The type 'DPR_SCHEDULING' is unknown.
    Object type 'BUS2172' could not be generated
    Please help me out as i am stuck.

    HI,
    Did u check is there any dependencies of Solman support packages with other support pakckages.
    Object type 'BUS2174' could not be generated it seems there is a issues with dependencies only.
    Please check the stack guide once then u will come to know all the dependencies.
    -Srini

  • SPAM-Patch (SAPKB70014) is hanging in phase Import_Proper

    Hi experts!
    I have problems to patch the SAP-Basis component (SAPKB70014) for SAP ERP 2005.
    The problem is that the patch is hanging in the phase Import_Proper.
    I read suitable SAP Note 822379 and changed the kernel to Patch 133 or 146, but it does not help.
    The system is installed via heterogeneous system copy.
    I have also other problems, e.g. Dump u201CITAB_DUPLICATE_KEYu201D by accessing into the tcodes DB13, DBACOCKPIT.
    Enclosed the last lines of the log file ULOG08_2
    Any helpful information is very appreciated and will be awarded with points.
    APServiceVHT 20080526133153 RFC: tp IMPORT all VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dclientcascade=yes -Dstoponerror=8 -Drepeatonerror=8 -Dsourcesystems= -Dbuffreset=yes -Dmainimp_proc=1 -Ddictimp_proc=1 -Dbatch_proc=1 -Dstopimmediately=1 -Dactivatemerged=yes -Dcheckmasterlang=no tag=spam -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133221 RFC: tp COUNT AUS pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133221 RFC: tp COUNT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133224 RFC: tp COUNT AUS pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133224 RFC: tp COUNT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133246 RFC: tp COUNT AUS pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133246 RFC: tp COUNT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133248 RFC: tp COUNT AUS pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526133248 RFC: tp COUNT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526151612 RFC: tp SHOWPARAMS VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526151612 RFC: tp CONNECT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526151614 RFC: tp IMPORT all VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dclientcascade=yes -Dstoponerror=8 -Drepeatonerror=8 -Dsourcesystems= -Dbuffreset=yes -Dmainimp_proc=1 -Ddictimp_proc=1 -Dbatch_proc=1 -Dstopimmediately=1 -Dactivatemerged=yes -Dcheckmasterlang=no tag=spam -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526151807 RFC: tp COUNT AUS pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526151807 RFC: tp COUNT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526161807 RFC: tp SHOWPARAMS VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526161807 RFC: tp CONNECT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526161810 RFC: tp IMPORT all VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dclientcascade=yes -Dstoponerror=8 -Drepeatonerror=8 -Dsourcesystems= -Dbuffreset=yes -Dmainimp_proc=1 -Ddictimp_proc=1 -Dbatch_proc=1 -Dstopimmediately=1 -Dactivatemerged=yes -Dcheckmasterlang=no tag=spam -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165518 RFC: tp SHOWPARAMS VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165518 RFC: tp CONNECT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165520 RFC: tp IMPORT all VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dclientcascade=yes -Dstoponerror=8 -Drepeatonerror=8 -Dsourcesystems= -Dbuffreset=yes -Dmainimp_proc=1 -Ddictimp_proc=1 -Dbatch_proc=1 -Dstopimmediately=1 -Dactivatemerged=yes -Dcheckmasterlang=no tag=spam -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165743 RFC: tp SHOWPARAMS VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165743 RFC: tp CONNECT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165744 RFC: tp SHOWPARAMS VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165744 RFC: tp CONNECT VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dtransdir=
    vzhl9000\sapmnt\trans
    APServiceVHT 20080526165744 RFC: tp IMPORT all VHT pf=
    vzhl9000\sapmnt\trans\bin\TP_DOMAIN_VHT.PFL -Dclientcascade=yes -Dstoponerror=8 -Drepeatonerror=8 -Dsourcesystems= -Dbuffreset=yes -Dmainimp_proc=1 -Ddictimp_proc=1 -Dbatch_proc=1 -Dstopimmediately=1 -Dactivatemerged=yes -Dcheckmasterlang=no tag=spam -Dtransdir=
    vzhl9000\sapmnt\trans
    Regards
    Thom

    Hi,
    I have similiar problem with patching SPS from 9 to 14 level on NetWeaver2004s.
    One background process is working second day, but it has status - STOP.
    When I'm logging into system a have "Status 0020 of the user interface SAPMSYST missing" message.
    Thom did you resolve your problem?
    Regards
    Michal Sarna

  • Xpra_execution phase error execution of report return code 12

    Hi,
    i am installing BI_CONT add on my ides system. 
    At phase xpra_execution its giving error "Execution of reports after put finished returncode 12". I have tried continuing 3 times.
    Program terminated (job: RDDEXECL, no.: 00174500
    See job log
    Execution of programs after import (XPRA)
    End date and time : 20081017002051
    job entries for RDDEXCEL:-
    Job started
    Step 001 started (program RDDEXECL, variant , user ID DDIC)
    All DB buffers of application server idesminda were synchronized
    Error Building the ENH TreeObject Type:XHObject Name:/POSDW/COND_TRANSBAL
    Function module CMMATGRP_O_WRITE_DOCUMENT deleted
    Saved
    ABAP/4 processor: CALL_FUNCTION_PARM_MISSING
    Job cancelled
    Along with that , it also giving an dump
    An exception occurred that is explained in detail below.
    The exception, which is assigned to class 'CX_SY_DYN_CALL_PARAM_MISSING', was
    not caught in
    procedure "OSOA_UPLOAD" "(FORM)", nor was it propagated by a RAISING clause.
    Since the caller of the procedure could not have anticipated that the
    exception would occur, the current program is terminated.
    The reason for the exception is:
    When calling the function module "RSA1_DSOURCE_ALL_D_GET", one of the
    parameters
    needed according to the interface description was not specified.
    This parameter was "E_T_OHIECOM".
    Kindly provide the solution
    Regards
    Vikas

    Hi
    XPRA_EXECUTION terminates due to the following reasons:
    ○       TP_INTERFACE_FAILURE: The tp interface could not be called.
    ○       TP_FAILURE: The tp program could not be executed. For more information, read the SLOG or ALOG log files.
    ○       TP_STEP_FAILURE: tp step XPRA_EXECUTION could not be performed successfully. To find the cause of the error, read the method execution log. To view the cause of the error in the log, choose Goto ® Log ® Queue.
    ○       CANNOT_READ_BUFFER: The tp program could not open the corresponding buffer file. For more information, read the SLOG log file.
    ○       CANNOT_MODIFY_BUFFER: The tp program could not change the corresponding buffer file. For more information, read the SLOG log file.
    For more details on this,please refer to the link :
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/7e/c6c2ad98a711d2b429006094b9ea64/frameset.htm
    Alternately, you have to follow the following steps:
    unlock the shadow instance (cd /usr/sap/put/bin && ./SAPup unlockshd)
    logon as DDIC
    copy DDIC to a different user
    logon with the other user
    start transaction SE06 and make the system "changable"
    start transaction OSS1 -> Technical settings - Change - Save
    use SNOTE
    Apply SAP Note 1153235.
    Regards
    Chen

  • SPAM update in IMPORT_PROPER phase

    Dear All,
    I have installed SAP Web Neweaver 04s as ABAP on MSSQL database windows
    OS and upgraded kernel 640 patch 175.
    But now when i go to import SPAM /SAINT from level 17 to 23 ie.
    SAPKD64023 then its running in IMPORT_PROPER Phase since last 5-6 hrs.
    PLEASE SUGGEST how to speed up my process??
    Log is as below:
    Log Overview for SAPKD64023
    SAPKD64023 SPAM/SAINT Update - Version 640/0023
    BPW System BPW
    Generate Transport Information File 02.01.2008 13:41:45 (0)
    Successfully Completed
    Test Import 02.01.2008 13:41:46 (0) Successfully Completed
    Import Request Piece List 02.01.2008 13:41:47 (4) Ended with Warning
    Import ABAP Dictionary Objects 02.01.2008 13:41:52 (4) Ended with
    Warning
    02.01.2008 10:54:46 (4) Ended with Warning
    02.01.2008 13:41:52 (4) Ended with Warning
    ABAP Dictionary Activation 02.01.2008 14:13:28 (4) Ended with Warning
    Import steps not specific to transport request
    ABAP Dictionary Distribution 02.01.2008 14:23:31 (4) Ended with Warning
    pls help me ASAP.
    Regards & Thanks,
    Ankita.

    Hi Ankita,
    I advice you to leave it for the moment and wait until it finishe that particular stage and check for the workporcess overview which report its executing at the back.Dont stop the process forcefully as it might cause inconsistency.
    Regards,
    Iqbal

  • SPAM update during prepare phase

    Hi all,
    I am doing an upgrade from 40B to 4.7 and finished my preparation before Prepare phase.
    Initialization phase is also completed successfully during prepare phase.
    Unfortunately i forgot to upgrade my SPAM to the latest and now i am unable to continue with Prepare
    phase because it is asking me to upgrade SPAm.
    And when i am performing SPAM update , it is giving warning and unable to continue further
    as " Caution: Upgrade is still running. Patches may be lost.
    Message no. TN 153 "
    Please let me know the way out , as i have also restarted my SAP and database but same warning still appear.
    Regards,
    RR

    I suggest to cancel PREPARE, apply SPAM update and after that start PREPARE from scratch.
    Cheers

  • Netweaver Sneak Preview Installation hangs at phase 18 of 29

    Downloaded Sneak Preview SAP Netweaver 04 Java edition file 1:NW04SneakPrevJavaSP11.part1.rar and file 2: NW04SneakPrevJavaSP11.part2.rar. Extracted into a directory and started installation using SAPInst.cmd.
    Installation went thru fine till phase 17 and in phase 18 it is taking for ever to complete. Also in the status bar it shows EP_LOCK_APPLS loaded (1 rows). It has been in this phase 18 for more than 3 hours.
    Any help is suggested.
    thanks

    Hi Chess,
    I have also faced this problem several times very recently also.         
    This is mainly because of registry cleanup problems.Do as follows :-
    1)goto start -> run -> type regedit.
    2)Serach the entire registry for sapdb,maxdb,xserver instances and entries.
    3)Delete all the nodes of the above sapdb,maxdb & xserver.
    4)Only caution is if the left hand frame of the registry shows any environment values of sapdb,maxdb and xserver don't delete that particular node.
    5)After all deletion double-check one more time in the registry and reboot your machine and start a afresh instaallation.During afresh installation the installation software should ask you for DB buffer cache size.If you get that you are sure that your registry is totally cleaned and fresh and definitely the installation will go through.
    Hope it helps.
    All the best.
    Regards,
    Guru Subramanian B.
    P.S :- Consider rewarding points if my answers are helpful to you.

  • SPAM - SAPKB70016 error during phase Generation of Programs and Screens

    Hi experts,
    I am trying import package SAP BASIS 700 level 16, but i have still errors in phase Generation of Programs and Screens:
    Program /OSP/SAPLR3_REPORT, Include /OSP/LR3_REPORTU38: Syntax error in line 000014
    Type '/OSP/REP_BADI' is unknown
    Program CL_HRBAS_INFTY_BL_COMPUTATION=CP, Include CL_HRBAS_INFTY_BL_COMPUTATION=CI: Syntax error in line 000005
    Type 'HRBAS00INFTYBL' is unknown
    Program CL_HRBAS_OBJECT_OPERATIONS====CP, Include IF_HRBAS_BUF_INTEGRATION_TO_PAIU: Syntax error in line 000007
    Type 'HRBAS_PD_PA_INTEGRATION' is unknown
    Program CL_HRBAS_RHOMBUFFER===========CP, Include IF_HRBAS_BUF_INTEGRATION_TO_PAIU: Syntax error in line 000007
    Type 'HRBAS_PD_PA_INTEGRATION' is unknown
    Program CL_PROXY_WSDL2ABAP============CP, Include CL_PROXY_WSDL2ABAP============CM03G: Syntax error in line 000004
    Type 'SPRX_PROXY_NAMEPROPOSAL' is unknown
    Program CL_WDR_CFG_PERSISTENCE_COMP===CP, Include CL_WDR_CFG_PERSISTENCE_COMP===CM005: Syntax error in line 000014
    Transformation 'WDR_CFG_COMP_TRANSL' has no activeversion
    Program CL_WSSE_PROCESSOR=============CP, Include CL_WSSE_PROCESSOR=============CM009: Syntax error in line 000131
    Transformation 'SEC_SAML_ASSERTION' has no activeversion
    Program SAPLPA_PACKAGE_CHECKS, Include LPA_PACKAGE_CHECKSTOP: Syntax error in line 000030
    Type 'WB_PACKAGE_COMPONENT_CHECK' is unknown
    System is: SAP ERP 6.0 IDES EHP3, kernel221, WIN2003, Oracle 10.2.0.4
    Can you help me pls?

    thank you for your help Sunny
    I solved problem:
    1.)
    Program /OSP/SAPLR3_REPORT, Include /OSP/LR3_REPORTU38: Syntax error in
    line 000014
    Type '/OSP/REP_BADI' is unknown 
    (SE18 -> reactivated Enhancement Spot /OSP/REP_ENH_SPOT  )
    2.)
    Program CL_HRBAS_INFTY_BL_COMPUTATION=CP, Include
    CL_HRBAS_INFTY_BL_COMPUTATION=CI: Syntax error in line 000005
    Type 'HRBAS00INFTYBL' is unknown
    Program CL_HRBAS_OBJECT_OPERATIONS====CP, Include
    IF_HRBAS_BUF_INTEGRATION_TO_PAIU: Syntax error in line 000007
    Type 'HRBAS_PD_PA_INTEGRATION' is unknown
    Program CL_HRBAS_RHOMBUFFER===========CP, Include
    IF_HRBAS_BUF_INTEGRATION_TO_PAIU: Syntax error in line 000007
    Type 'HRBAS_PD_PA_INTEGRATION' is unknown
    Program CL_PROXY_WSDL2ABAP============CP, Include
    CL_PROXY_WSDL2ABAP============CM03G: Syntax error in line 000004
    Type 'SPRX_PROXY_NAMEPROPOSAL' is unknown
    Program SAPLPA_PACKAGE_CHECKS, Include LPA_PACKAGE_CHECKSTOP: Syntax
    error in line 000030
    Type 'WB_PACKAGE_COMPONENT_CHECK' is unknown
    (SE18 -> reactivated types)
    3.)
    Program CL_WDR_CFG_PERSISTENCE_COMP===CP, Include
    CL_WDR_CFG_PERSISTENCE_COMP===CM005: Syntax error in line 000014
    Transformation 'WDR_CFG_COMP_TRANSL' has no activeversion
    CL_WDR_CFG_PERSISTENCE_COMP===CP ,
    Program CL_WSSE_PROCESSOR=============CP, Include
    CL_WSSE_PROCESSOR=============CM009: Syntax error in line 000131
    Transformation 'SEC_SAML_ASSERTION' has no activeversion
    (Tcode STRANS -> reactivated Transformations
    Edited by: Miroslav Mihok on Oct 6, 2009 3:37 PM

  • Transport hangs at phase set version flags

    Hi
    We suddenly cannot any transport into our PRD system, when we transport a simple transport it stays at the phase set version flags finished with return code 0.
    I changed the Kernel and tp R3trans, checked the tmp folder in  usr/sap/trans  with no luck.
    Does anyone have an idea where the problem could be?
    thanks
    Murat

    Please check the logs in
    /usr/sap/trans/tmp
    /usr/sap/trans/log
    Markus

  • Error during application of scm 7.0 support pack

    While applying support pack to our SCM 7.0 system (New Installation),
    We encountered a SPAM error in xpra_execution phase, due to automatic
    termination of job RDDEXECL scheduled by user id DDIC on client 000.
    The details of the error are:
    Message id: Brain
    Message number : 366
    Message type: A
    Error: Error during SID assignment for characteristic 0REQUID (current
    value 2)
    We had a look at few notes mentioned by SAP support on 1319241. which
    specifies a solution as
    u201CIf you encounter the error message above, please run the Elementary
    test - Compare Number Range and Maximum SID - for Master Data 0REQUID
    in transaction RSRV. When it turns red, the error can be corrected by
    pressing the "Correct Error" button.u201D
    But we are already getting the light as green in the elementary test
    for the Master Data 0REQUID in transaction RSRV, though we still
    execute the same and problem is still the same i.e. RDDEXECL
    program/job is getting terminated.
    Regards
    Edited by: pranav kumar on Feb 25, 2011 8:20 AM

    Hi SM
    Just login to client which has been mentioned in table RSADMINA,then run rsrv you will get error.correct it.then you will be able to import support packs.
    Regards
    Pranav

  • ERROR WHILE IMPORTING SUPPORT PACKS

    Hi all
           After successfull installation of ECC - SERVER , while importing SAP_BASIS support pack , spam stuck with XPRA_EXECUTION phase.
    Kindly advice me resove this issue
    selvan

    Hi,
    Provide Import and Action Logs for the Exact error (SPAM >Goto> import/action logs.
    Regards
    Umesh

Maybe you are looking for

  • Non PO invoices sent for Approval - getting error message - Tax Jurisdictio

    Hi Experts, Our clients have just upgraded from SAP 4.6C to ECC 6.0 and when the Non -PO invoices are sent for approval the user is getting the below error message. 'Specify a tax jurisdiction key' - Message no. F5566 Could any one suggest what the r

  • Mac Pro kernel panic, RAM does not seem to be problem

    My Mac Pro (late 2006) now has kernel panics at startup. Problem first happened while computer was in sleep mode, a second kernel panic happened about 10-15 minutes after reboot the first time. Now it happens at startup every time. Zapped PRAM multip

  • BADI - BBP_CATALOG_TRANSFER - Debuging in web browser

    Scenario: The end user will launch a catalogue via the EBP system. The user will search for materials and services within the catalogue search engine. The materials and services will be displayed with the numbers from the R/3 system. The end user wil

  • Subject: Undelivered Mail Returned to Sender

    On mail to a few addresses I am getting: 550 Access denied - Invalid HELO name (See RFC2821 4.1.1.1) (in reply to MAIL FROM command) I have multiple domains hosted on my server so that my be part of the problem but I really do not know where to go fr

  • Core dump failed, errno=4

    I'm looking into some dumps from Orcale and found one that mdb gets the following error: core file may be corrupt I found the following message on /var/adm/messages. [ID 457380 kern.notice] NOTICE: core_log: f90webm[6192] core dump failed, errno=4 Wh