Specification for batch managed procured material

Hi all
I have created bom for non batch manage material.
I have added batch managed procured material in bom, I have done classification of  batch managed procured material in BOM .
I have created production order for header material of bom manually and done MRP after that. It has created PR for that material.
But in PR. iam not able to see specification from classification data (BOM ) for procured item.
Is there is any config iam missing?

Closing thread in MM forum and opening it in PP.

Similar Messages

  • Specific Identification Cost for batch managed items (Follow-Up from P2P)

    Specific Identification Cost method is used for serial and batch managed item. Using this method, the outbound cost of such items would be the original cost of specific goods, which can be determined according to the serial or batch number of that item.
    Business One allows the user to receive batch managed items with a batch number that already exists in the DB. It’s possible that the received quantity is added to on-hand quantity in the warehouse. In such case, the quantity on-hand of that batch and the received quantity may have different costs.
    What should be the system behavior in such case:
    1. Block receipts to the same batch with different costs.
    2. Write the difference to a price difference account, as done in Standard Cost method.
    3. Manage the batch cost with Moving Average method.
    This thread is continuation from 'Specific Identification Cost for batch managed Items' <a href="http://p2p.sap.com/businessoneforum?type=join&login=1&uid=41FB661A76CED536C825C4E2B6FF4397&cid=91&go=z37225">discussion</a> in P2P SAP Business One Forum (Product Development Collaboration).
    Previous discussion on P2P is summarized in the attached file.

    Hi Peter,
    This is a very important functionality that you are describing here. For example, in the Steel industry, it could be extremely useful to cost by batch or serial number.
    If you receive a batch that already exists in the system and if the costing method for the product is moving average, then teh cost of the batch should be calculated based on the moving average as well.
    If the costing method is standard, then the cost should go in a variance account.
    If the costing method is FIFO, then it is a getting trickier...
    Regards,
    Vincent

  • QM In-Process Inspection for Batch Managed Material

    Hi,
    I have a issue related to UD of In-Process inspection for batch managed material. The production process is discrete manufacting for a cold rolling mill. A production order can have mutiple coils as per the production amount. To track the individual coil , batch management has ben activated. We have both in-process as well as inspection after production here.
    For inspection after production we are fine as we are doing partial confirmation after every coil and have separate inspection lot having different batch number.
    But for in-process I can have only one inspection lot for the production order (created on release of the production order). I can do the result recording but while trying to do UD u2013 it is asking for a batch number as the material is batch managed. W/o entering the batch number system is not allowing me to do the UD.
    Is there any solution/work around of this problem.
    -Regards
    ashim

    Hi Ashim,
    you raised a very good question? i am helpless here to execute same scenario,
    but i disussed with my QM guy here, he said, once the material is batch managed then it has to ahve batch in UD.
    so i discussed ur case, which is very much valid for heavy ind like cement and all,
    so what i suggest, u create a dummy batch in the UD for in process (no inventory posting)
    and at confimation give ur usual batch (if system propose the dummy batch which u give in the UD for inprocess, try to change there--- i hope it should allow)
    i would really like to here answer from u for this.
    try to do as suggested, and let me know the results.
    REgards,
    Pravin mukkawar

  • EWM - Batch Management at material/plant

    How can I manage batches at material/plant level within EWM?  I am being told that EWM does not allow batch management at material/plant level. It allows batches only at material level.
    Can someone please shed light?
    Thanks,
    Satish

    Hi
    It is not simple task. Make sure you don't have any stock left in the concerned plant(s) for the present and the previous month (the batch management flag is valid for all storage locations of a plant).
    Archive/delete all existing batches for the concerned plant(s).
    Now you should be able to unflag batch management.
    regards
    Srinivas

  • Unmark batch management at Material Master Record.

    Hi all:
    Is it possible to unflag the batch management mark from a material (with an existent batch) and use it again?
    The material is already marked for batch management use. An initial stock (with batch) was made.
    Then a necessity to unflag (batch management) the material; arised.
    Stock was deleted and batch marked for deletion at Plant and batch stock level.
    The system doesn't permit to unmark the batch management because it says that "Batches already exist".
    Thanks for any help.

    Hi
    It is not simple task. Make sure you don't have any stock left in the concerned plant(s) for the present and the previous month (the batch management flag is valid for all storage locations of a plant).
    Archive/delete all existing batches for the concerned plant(s).
    Now you should be able to unflag batch management.
    regards
    Srinivas

  • ATP check for batch managed products

    Hello All,
    I have a requirement for ATP check for batch managed products and would be glad if someone can help me on that.  One of the characteristics on my product is expiry date. Business wants to restricts confirming products which has an expiry date of less than 90 days for orders outside the country. How can we achieve that?

    Hello
    You can try with activating Shelf Life Expiration Date (SLED).
    For config, check SPRO - Logistice General - Batch master - SLED
    Then finally setup Customer Exit to calculate/check the SLED.
    Exit EXIT_SAPLMHD1_001 for enhancement SAPLMHD1.
    Further, you can refer following SDN thread for reference/understanding:
      - SLED by customer/ material
    Regards
    JP

  • Customer exit for Batch management

    Hi experts,
    I'm using customer exit for batch management for internal number assignment.
    I need the Batch number as i mentioned below 
    DDMMYYB01
    DD-Date
    MM-Month
    YY-Year
    B-Block
    01-Number
    For this i need to give logic. How to give i'm not getting. This batch number creation will come at the time of GR.
    Anybody help me?
    Naren

    Hi
    Please use the user exit SAPLV01Z as I mentioned in your other thread, please go to SMOD to read its documentstion.
    In SMOD, select the 'Documentation' and click 'Display', this will show the overview documentation.
    Select the 'Componnet', then ciick the 'Display'. select each component and click 'Documentation Ctrl+F4) this will show the detailed documentation of them.
    Best Regards.
    Leon.

  • Material getting set for Batch Management in O/B delivery

    Hi Folks,
    For a material which is not batch managed, I created an outbound delivery.
    For some reason, the material is getting set as 'BatchManagement' even though the Batch Management indicator is not set.
    Due to this PGI is not possible.
    Any thoughts on why the 'Batch Management' indicator has been set and how to resolve this?
    Regards,

    Hi Jürgen  ,
    I am unable to replicate this problem in Q. Its occuring only in P while doing a goods issue.
    Message is
    "The batches are not defined for delivery item XXXXXX".
    As I said earlier, we have not set the batch management check box in MM.
    However the outbound delivery has the batch management check box selected .
    Anything I missed to check? Q is almost identical to P. But still issue is only in P.
    Regards,

  • MB1C LSMW Recording fails with missing Prod Date for Batch Managed Material

    An LSMW recording for transaction MB1C that was batch managed was successfully recorded.  This included the entry of the Production Date before pressing enter to post the Good Receipts.  However, when the transaction was executed, the error came back, "Enter the date of production".  In looking at the screen in the lsmw batch results, it shows the date in the production date field.
    I also tried to create the recording in the Transaction Recorder (trancode SHDB), and process the recording simulating the background mode and got the same results.
    Any ideas why it seems to be ignoring the production date?  Any help will be greatly appreciated.

    An LSMW recording for transaction MB1C that was batch managed was successfully recorded.  This included the entry of the Production Date before pressing enter to post the Good Receipts.  However, when the transaction was executed, the error came back, "Enter the date of production".  In looking at the screen in the lsmw batch results, it shows the date in the production date field.
    I also tried to create the recording in the Transaction Recorder (trancode SHDB), and process the recording simulating the background mode and got the same results.
    Any ideas why it seems to be ignoring the production date?  Any help will be greatly appreciated.

  • Inventory Count for Batch Managed materials - Plant, S.Loc and Batch Wise

    Hi.,
    In the company's current scenario, the printing of batch managed materials are scheduled under 3 Job names.
    1. First job determines the materials/batches that need to be created today using Program RM07ICN1
    2. Second Job Processes the BDC Session created by Program RM07ICN1 using Program: RSBDCSUB
    3. Third Job prints the Inventory tickts at the appropriate Storage location using Program: RM07IDRU
    Each Job has its own variant.
    The Variant for SL.No 1 is defined w.r.t
    i. Material Type : Two Material types have been defined
    ii. Under selection variable, GIDAT ( Planned count date and GBDAT are flagged.
    Current Analysis:
    A. The inventory documents get printed with Materials as per the cycle counting indicators defined which govern which material has to be currently counted.
    B. Inventory documents are generated for all materials in all the plants and in all the storage locations
    C. Batches for a material number may print on different cycle count documents throughout the year. 
    Customer requirement:
    The inventory documents to print on basis of
    1. Material, Plant and S.Loc.
    This would help in identifying the batches which are currently being counted as well.
    2. Customers requirement is to ensure that all batches are accounted for and will identify any overage of batches since in the current process, they are never reviewed as a whole.
    QUESTION:
    1. How to configure the Customer requriement.
    2. How to configure the Variant/s, if thats the place the configuration has to be done to satisfy the customer.
    3. How to activate the Variant in SE37 after definition in the Step Indicator. Does it activate on execution?
    When i run the Program using SE38 , maintaining options in the Screen ( giving Material, Plant and S.loc), i get the desired list (Batches w.r.t Material,plant.S.Loc). But there is a list of over 150 Batch managed materials and it would not be physically possible to maintain the variant for each each Material,plant,S.loc wise.
    Is there a way to configure the customer requirement/s.
    Any and all help is much appreciated.
    Thanks

    Hello Mahesh,
    <b>Customer requrirement is specific, they want a list of Inventory Documents to be generated on basis of Material in each Plant-S.Loc batch wise.</b>
    Then you need to define multiple varinat for the program.
    <b>(a) If i am giving two variants in the same Program name RM07ICN1, how to execute one after after in sequence.
    In testing, I have defined in the " Step", Progran RM07ICN1 with one variant and Program RM07ICN1 with another Variant. But on execution of Program RM07ICN1 thru SE38, the screen defined latter ( second variant screen data ) is displayed.</b>
    You need to define several steps in SM36 transaction for the program using each variant. SE38 you can use only to save your variant data so later you can use this variant in SM36.
    Once you schedule the job with SM36 and release it then it will automatically execute this job as per your criteria (timeline)
    Hope this helps.
    Regards
    Arif Mansuri

  • Documentary Batches with Batch Management at Material Level

    Hi,
    We have configured batch managment at the material level, and turned on for our materials. This applies to all plants that a material is extended to. Problem is that some plants don't have capability to (or do not need to) trace individual batches. So a "Generic" batch number approach is usually used in those few plants - but this of course still requires that the "Generic" batch number be supplied in all transactions. Some of those plants have just a more limited requirement of batch traceability (e.g. just at receipt or despatch, but not anything else like physical inventory).
    The functions of Documentary Batches seem most appealing. However, according to documentation, and in our tests, it seems that the batch management setting will always suppress the documentary batch functions in a plant, even if we only want generic batches.
    Does anyone know how to allow documentary batches for certain plants to override the "Batch at Material level" setting? P.S. We are not able anymore to re-configure the batch to material-plant level.
    FYI - I have searched Forums, Wiki, Support portal, SAP Help and Release Documentation.
    Cheers,
    Jeff

    hello Gurus,
    Can any body Download OSS note 41715  for me from Marketplace as i dont have access so please.
    regards,
    ninad

  • Does SAP Provide any standard conversion program for Batch Managment activa

    Hi,
    An idea if SAP Provides any standard program to conversion of non batch managed material to batch managed material in a productive SAP Environment and close open documents,
    It would be great help if somebody can reply to these queries.
    Thanks in advance
    Regards
    Bijaya Pradhan

    Hi
    Use the same Driver program RIPROV00 which is used as Script driver program to fire the output from smartforms also
    Only thing is little bit you have to modify the program such that it triggers the smartform instead of Script.
    I think there is no smartform driver program for this IW21.
    see some standard SF driver program like RLE_DELNOTE and
    modify it and use it.
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • BADI - WORKORDER_GOODSMVT - check for BATCH management

    Hi there,
    I have implemented WORKORDER_GOODSMVT BADI (Backflush method) to fill the batch number with a default value for a given plant.
    This is working fine.
    However, I only want to fill this if the Material in the Production Order is "batch managed" (at the moment it's happening for all materials in the Prod. Order ). This indicator field does not appear to be available in the structures of the BADI.
    If I look in CO02 for the order, I can see a column called BATCH which is filled with an 'X' in certain cases.
    An F1 on the screen field says that it is 'RESBD-SPLKZ'
    However, if I check RESB table (or read RESBD using a function module) , this SPLKZ field is always blank for the given order.
    Does anyone have an idea why this is, or where I can find a proper "Batch Indicator" field?
    All suggestions appreciated.
    I have searched forums and can't find relevant solution.
    Thanks,
    David.

    Hi Bruce,
    I solved the problem by going to MARC table with material and plant, and checking field MARC-XCHPF ('Batch management requirement indicator').
    if this field was set to 'X', I made my change to the CHARG field.
    Hopefully this helps you.
    this is from a long time ago, I should have updated the post sooner - will mark as solved now.
    thanks,
    David

  • How to Setup Batch Management Level (Material vs Client)

    Hi Experts,
    I had a question about the level at which I should be setting up Batch Management. The requirements that we have are:
    - We want uniqueness in the batch being created.
    - We have split valuation active at the Batch Level.
    Hence, we have nailed down to the following 2 options: 1. Client level or 2. Material level. (I know that I will not be using Plant level because we do a lot of STO's and we do not want to lose the characteristics in the Batch at the plant level. So the plant level is out of scope.)
    Client Level: Although the client level gives us the uniqueness and supports most of our requirements, my fear with going at the client level is that it is too rigid and MAY cause problems in the future. Is that true? What would be issues/ concerns that you have faced when you have had Batch Management activated at the client level.
    Material Level: If I setup the system at this level, I would like to be able to create a Batch number for a material across the entire client only once. E.g. MAT1 can have BATCH 123 only once across the whole client. MAT 2 can have BATCH 123 but the Material# and the Batch # uniqueness should be maintained thoroughly.
    I would like to try out this level but my problem is I am unable to understand and setup this level completely. I have gone through some pretty good discussion on this topic but still am unable to understand it thoroughly. The link to this discussion is (http://www.sapfans.com/forums/viewtopic.php?f=27&t=80407). If you refer to this link, it says u2013 Client/ Material Level. What does client/material level mean? Can you please help me understand it. Also, if I setup Batch management at this level, I would like the system to auto-generate numbers for me exactly as I have mentioned above. Is there a way to do so? I was trying to setup the BATCH_MAT number range object with the batch level at Material level but the system seems to always default to the BATCH_CLT level and give us numbers. Is there a way to fix the system to check the BATCH_MAT number range object and give the batch numbering per my requirements. What happens if I use the Material Level Batch management with BATCH_CLT number range object?
    Your help is highly appreciated.
    Edited by: TV_SINR on Jul 16, 2010 8:52 PM

    Check following customizing:
    Logistics General --> Batch Management --> Specify Batch Level and Activate Status Management
    If you want to change the batch level, you have to start conversion to activate the change.
    Note that you cannot reset conversion from plant level to a higher level, read the documentation for customizing of
    "Specify Batch Level and Activate Status Management".
    If you want to work with same batches for different materials, you should use "Batch unique at material level".
    Logistics General --> Batch Management --> Batch Number Assignment
    Here you can define how the system should create batch numbers.
    Best Regards, Dirk

  • How to deactivate batch management at material master?

    Dear Sir/Madam,
    At the configuration,I have set "Batch Management" to be activated in plant level.  I have a problem which some of the plants do not use batch management.I understand that if you tick "Batch Management" field in material master, batch management is activated for the material in that plant.
    1. How do prevent user to tick "Batch Management" field in the material master which appears in the following views (depending on the material types):?
    - Sales: General/Plant
    - Purchasing
    - Plant data/Stor.1
    - Work Scheduling
    2. Is there any alternate way to prevent user to activate "Batch Management" in that material of their own plant despite it is activated at plant level in the configuration?
    Please advise.
    Thanks.
    Rgds,
    Esther Chong

    batch status management is just what its name says, you manage your batches with status (unreastricted use, restricted use).
    But his comes only into place after you have activated batch managment, it is not causing batch managment, it is only working with batch managment.
    Removing batch managment is almost impossible, you have to archive all batches first, to be able to archive the batches, you have to archive the production orders...creation of a new material is in most cases easier and quicker.
    Wit batch managment at plant level each plant can independently decide if a material is batch managed or not.
    if you want to restrict the entry of the batch management flag, then you have to customize your material master field selection at plant level.

Maybe you are looking for