Hi dudes,
We are implementing SAP for our Subcontractor.
our SC  receive all components from our company ( on free ) but sometimes they purchase the same material themselves for other uses. so we decided to use split valuation to separate valuated and non-valuated materials.
I did configuration and created 2 valuation type ( valuated - nonvaluated )
when I create Purchase order it askes for valuation type but even when I use non-valuation type in PO it asks for price!!!!
do any of you have used split valuation for this target?
have the same problem?
what should I do actually??

Hi,
Is someone in the subcontracting plant going to do a process order on the materials you send them? Or are you only going to track the finished inventory once it reaches your plant?
In the first case:
1) Create a STO to the SC plant. This stock will have to be priced.
2) Inventory reaches SC plant. They perform production process.
3) finished inventory is sent using another STO.
2nd Case:
1) Create a SC vendor using the SC plant as a vendor.
2) Create a SC PO to this vendor using this vendor and transfer goods to him. In this case, goods are transferred for 'free' as they really belong to you and not to the SC
3) Once the production process is over and the finished product is sent back to you, do a GR. The raw material sent to the SC will be consumed.

Similar Messages

  • Splitt valuation for non valuated material

    Hi all,
    Is it possible to make splitt valuation for non valuated material? if yes how?
    Our business scenerio
    Large no of spare parts (ERSA).Divide spare parts material type into 2,
    1 for valuated and another for non valuated,
    For non valuated spares,copy from ERSA make  it ZBLB for non val spares
    now
    How to make the split valuation for ZBLB material type material's ??
    Do u have any idea ??
    Regards,
    Hareesha

    Hi
    Split valuation is the concept used for individual valuating of different lots of same material.
    Here you have created a new material type ZBLB from ERSA for maintaining non-valuated materials. There are several significant points in your actions.
    1) When u  are able to maintain materials seperately with different material types, what way u want to use split valuation concept?
    2) As the non-valuated material implies for no value updating, the material type does not provided with accountign view. So no valuation class and obviously no valuation type. The prpcurement of non valuated material will be account assigned.
    3) For non-valuated materials, either u have to use standard material type UNBW or copy from UNBW. donot copy from ERSA.
    I hope your doubts are cleared. Please come out with your comments if any specific.
    warm regards
    sairam akundi

  • Initial entry stock (561) is valuated for non-valuated material

    Hi Gurus,
    I am doing initial entry of stock balance (MvT 561) for several non-valuated material. But when I check the table MSEG, I got status of "X" in the field MSEG-WERTU, which mean the material is valuated. The consequence is the value is updated, so I get inconsistency in stock (stock value is updated, table MBEW)
    So how can I can get valuated when I done my first initial entry of stock balance for non-valuated material?
    How can I trace, where did I go wrong?
    I have checked these:
    - I checked the material type, and it is properly configured (quantity update only).
    - No changes have been made in the material type.
    - No changes have been made in the material master data.
    Please help, and thanks!

    Hi,
    Please refer the below links....
    MB1C 561 With no Financial accounting Document created
    Valuated material to Non valuated material movement
    I am getting accouting Document when I do GR
    Regards,
    Udaya.

  • POS for non valuated materials

    Now I am creating POS for non valuated materials. But system is asking Price for Non Valuated Materials. Please tell me how can create POS with our price for Non valuated Materials.

    Hi,
    Are you purcahsing non valuated material (UNBW material type) for free.If not keep a price in PO  ( with account assignment category K)& do GR (where it will hit expense acoount & GR/IR account) &then IR.
    For more check OSS Note: 456691
    Regards,
    Biju K

  • Stock Transport for Non Valuated Account Assigned Material

    Hi Experts,
    I have to satisfy some unique requirement from my demanding FICO team to make certain process work our way.
    Following is the scenario...
    1. Plant A and plant B belongs to the same company.
    2. Plant A makes material X (non valuated, ind/coll indicator = 1).
    3. X calls for sub-assembly Y (non valuated, ind/coll indicator = 1) which is a make item in plant B. <b>X and Y belongs to different Profit Centers</b>
    4. Sales order placed at plant A for material X.
    5. MRP runs and creates a stock transport order in plant A to buy the non valuated material Y from plant B. STO is account assigned to the sales order.
    6. Plant B makes the material Y by creating a production order that is account assigned to the same sales order and does PGI to ships it out to plant A.
    7. Plant A GRs the material Y and this puts it in sales order stock. No value move, just qty move. Also no FI document created.
    8. Plant A issues component Y to the production order created for material X. Cost of Y doesn't show up in the production order as it is non valuated.
    9. Upon settlement of the production order in Plant B, the <b>ACTUAL</b> cost gets settled to the sales order in plant A. So at the time of settlement the <b>profit center switch happens for Y (i.e. the profit center for Y changes to match X's profit center)</b>
    This is a beautiful process from logistics point of view. BUT, my FICO has unique requirement for inter company sales for our organization. For them to consider a process as inter company sales, the following constraints has to be met...
    <b>1. Ownership of material remains with producing profit center until consumption by the receiving object. (with the above mentioned process the profit center switch happens during prod. order settlement)
    2. Cost for the consuming profit center will be moving average, standard cost or planned cost. (we are dealing with non-valuated materials and the settlement happens at actual cost)</b>
    I need your expertise to help me define a work aroud. I am thinking about a lot of options to somehow make it work but can't seem to get solutions. Following are my thoughts...
    1. Is it possible to possible to make the settlement with planned cost instead of actual cost?
    2. Is it possible to make a profit center switch during consumption rather during settlement?
    3. Is it somehow possible to create an underlying FI document during GR at plant A? (I know SAP does not create a FI doc. for non valuated materials).
    4. Or can plant B send an invoice to plant A for the STO? (I believe this can be done for cross-company STO) I am thinking doing an Invoice Receipt at plant A instead of doing a settlement might show up the cost for Y in the production order for X.
    An IR with the planned cost would be an awesome solution to get the buy-in from FICO. Can this be done?
    I hope you don't mind my lengthy message... Waiting for some positive response.
    Thanks.

    Anyone??? This is kinda urgent?

  • Moving Average Price for Non-Valuated Material

    Hello Experts
    The question may seem to be quirky but need your advice for the below.
    My client is buying non-valuated material against a cost center, they do not want to keep the stocks valuated. No value update only quantity update. The accounting documents are the following when the GR is done by receiving folks
    Qty of material XYZ goods receipted = 10
    Debit     Consumption GL   12345678       10 USD          Cost Center ABC123 (This is a warehouse cost center)
    Credit    GR/IR account                            10 USD
    Qty of mateiral XYZ issued = 5
    The goods are later on issued to Production cost center and the client was the below entries to be passed with MOVING AVERAGE PRICE.
    Debit    Consumption GL 12345678           6 USD          Cost Center ABC456 (This is production Cost center)
    Credit   Consumption GL 12345678           6 USD          Cost Center ABC123 (This is warehouse cost center)
    I am aware that as this is a non valuated material the above entry is not possible. Maybe, I will use BAPI_ACC_DOCUMENT_POST for the generating the accounting document when the goods are issued from warehosue to production center.
    My question is how can i get the moving average price.
    Regards
    Chokkalingam Pillai

    you can have an accounting view for non-valuated materials, this helps for example with purchase requisitions as they could take the valuation price from the material master and the user does not need to enter a valuation manually.
    But the material master moving average  price cannot be calculated and updated automatically, as it is not foreseen in any standard program to do this for cost center procurement, since SAP only calculates a MAP for valuated stocks.
    Further it is not logical to issue non-valuated stock valuated (even with a different price) from cost center to cost center.
    It looks like you want to  have a kind of internal billing for warehouse services, as you end up with a negative amount in the warehouse cost center which is then the profit.
    Why don't you just  create a report to run at the end of the month, listing all goods issue movements with their cost centers and taking the price from last PO (or from material master if you decide to maintain it manually) and use this for a manual cost center posting in CO module

  • "Taxes for SEZ" and "Opg Stock of Material for Non Valuated Project Stock"

    Hi Guru's,
    Need two clarifications specific to SEZ:
    a. When an SEZ unit buys any materials from a DTA unit, and if the supplier issues ARE1 form then there is no Excise duty charged on such purchase. Similarly VAT is also exempt and CST is exempt if the SEZ unit issues Form I. However in case the SEZ unit is not NEF +ve after 5 years, then all these benifits taken on ED, CST, VAT etc needs to be paid back to the Govt.
    Hence how is it possible in SAP to capture all these benfits (ED,CST,VAT) in the MIRO Invoice posting stage, so that the details are available when needed?
    b. We are using Project Systems and the project is non-valuated. So in our case all material which we buy for Project is consumed at the GRN stage and there is no valuated inventory.
    However for "Annual Performance Report" it is mandatory to give the Opening stock of material.
    Can anyone throw some light how this can be calculated when we the Project is non valuated?
    Regards,
    Prasad

    Hi,
    This is little difficult to manage a material as valuated and non valuated. To make it non valuated you have to use a material type which is managed only on quantity basis and not on value basis like non valuated stock. Then you can do a material to material transfer posting. I haven't checked this scenario. For more info on this please refer these links:
    http://help.sap.com/saphelp_dimp50/helpdata/en/4c/227bb446e611d189470000e829fbbd/content.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227bdb46e611d189470000e829fbbd/content.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227ba746e611d189470000e829fbbd/frameset.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227be846e611d189470000e829fbbd/frameset.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227b8d46e611d189470000e829fbbd/frameset.htm
    Regards,
    Atal

  • How can we run MDBT transaction for non-valuated items only

    HI,
    We want to run the MDBT transaction for non-valuated items only...but through this transaction we can run for all items..
    How can we run only for non-valuated items???
    Regards,

    Dear Anil,
    MD02 - Material level planning ( Multilevel )
    MD01 - Plant level planning ( Multilevel )
    MDBT - Back ground MRP ( Multilevel )
    coming to ur query if all 20 materials belongs to one storage location or one MRP controller
    Then you perform MRP for that 20 materials with the above given user exit
    Also Plz refer my reply from this thread
    [Re: MD01 Replanification.]
    Regards
    Madhu

  • Proforma invoices for non-valuated returnable packaging

    All,
    just wondering whether it is required to send a proforma invoice for non-valuated returnable packaging that is sent across a border.
    Can anybody help me on that one?
    Thx in advance!
    Regards,
    B.

    Hi,
    Going by std SAP best practices, if you are sending materials across the border and also entering foreign trade export data in your sales documents it is advisable to have a proforma invoice for your returnable packaging materials else they may be subject to other taxes, customs or excise duty.
    You may check with SAP Global Trade Solutions to check about the implications in detail.
    [SAP GTS|http://help.sap.com/saphelp_gts70/helpdata/en/1d/8082ab7248f74ca09861d9713b9a52/content.htm]
    Regards,
    Amit

  • 4.what accounts are generated for Non-Valuated material & for Consignment m

    4.what accounts are generated for Non-Valuated material & for Consignment material?
    please explain me.

    Dear Srinivas,
    Please find below the explanation about both materials in a simple manner.
      "Non valuated material".(UNBW):
    For this material type in the basic settings only Qty. update is active & no value update.
    No accounting data is maintained in Material master hence stock values are not updated.This material is procured only with account assignment.
    Consumption statistic is updated only after Goods Issue.Whenever material will come its value will be always go to consumption account.
    Consignment Material :
    In this case material is still owned by vendor & only kept in your premises. Liability only starts when you withdraw material from consignment stock or post it to your own valuated stock.Liabilities are generally settled monthly.
    At GR wrt PO material is directly put to consignment stock of vendor.It is possible to post another GR into consignment stock.No valuation takes place during GR.
    Once the material is withdrawn from consignment stock( For prod) it is valuated with the price of vendor in as per INFO record.
    If useful reward points,
    Vivek

  • Account assignment for Non valuated Material

    Dear All,
    Please guide how to create PR & PO for non valuated material.
    Regards,
    Manish Jain

    HI,
    Non-valuated material (Material Type UNBW):
    This type of material is managed on a quantity basis, but not on a value basis. This makes sense for materials of low value, stocks of which nevertheless have to be monitored (for example, operating manuals).
    Non-valuated goods receipt
    At the time of the goods receipt, postings to the consumption account do not take place. The posting to the GR/IR clearing account is therefore not applicable. With invoice receipt, the consumption account is debited with the invoice amount. The offsetting entry is posted to the vendor account.
    Regards,
    Pardeep Malik

  • Shopping cart error for non Valuated material,

    Hi Guys,
    I have an issue with shopping cart which is getting error ("Shopping Cart 0000146522 (Purch Requisition 2000039570): 06 326 Please enter document number and item together ")after approval for non-valuated materials when it has a contract number assigned along with item number in the source of supply tab.If i delete the contract number,i am able to reprocess the shopping cart.Please advice why it is failing when it has a  correct contract number.
    With Regards
    Sri.
    Edited by: sri ram on Jun 23, 2009 3:06 PM
    Edited by: sri ram on Jun 23, 2009 5:13 PM
    Edited by: sri ram on Jun 24, 2009 9:49 AM
    Edited by: sri ram on Jun 25, 2009 9:55 AM

    Hi Ram
    SAP Note 918178 - Error message E06 326 while running WRP1
    WRP1 - is a tcode for  replishment planning in ECC.
    but message comes from ECC system .plz explore contract data once again
    note :514430
    Can you recreate in development box with same data . if it so you can debug in development
    br
    muthu

  • Intercompany STO process for non valuated material

    Hi Experts,
    Please advise is intercomany STO process possible for non valuated material?
    Material where only quantity update is there & value costed to a cost object.
    If intercompany process is possible then what are all the steps that complete
    the full cycle?
    Regards,
    Partha

    Hi,
    Intra-company-code stock transfer orders to nonvaluated materials can be created in R/3 without specifying an account assignment.
    Carry out the following steps for the advance correction:
    1. Create the message '159' in the message class 'XC'. To do this, call transaction 'SE91' (message maintenance). Enter the message class 'XC' and create the message '159' with the following short text:
               Message              Message short text
               159          The account assignment category could not be determined
               Save the message.
    Thanks

  • Storage Location for NON valuated material in MIGO

    Hi friends ,
    I have created a purchase order for NON-Valuated material (UNBW) with Account Assignment "K".I did check the material type UNBW configuration where only Value Update is checked for my Plant.
    Now at the time of MIGO , system is asking for Storage lcoation (mandatory) and after MIGO system also updates quantity in Storage Location entered in MIGO.
    while in normal cases (like ROH material type) , if we create Account Assigned PO ( like K) , system neither ask for Storage lcoation at the time of MIGO , nor system updates Qty at any storage location.
    As per my understanding , if we create Purchase Order with account assignment K , system updates value in consumption and doesn't update Qty in stock (although material is stockable) .....which is simply like immediately issue of material to cost center.
    Therefore wondering why system is updating Qty for NON-VALUATED material.
    Does non valuated material means , POST value to Cost center (for account assignment K) and Update Qty in stock ?
    Like in case of Account Assignment , value gets charged to WBS and qty gets updated as special stock "project"
    All replies are welcome .....
    Regards
    Shrey

    By definition UNBW's are ony qty updating and have no value assoicated with them. Since the system needs to stock this qty somewhere it by deafult asks for a Sloc.

  • When posting GI for Non valuated material in Delivery geting error (M8147)

    Hi Experts
    We have a problem that we are trying to send a material from one plant in one company code to another plant in another company code (Inter Company Stock Transfer Order). The material is of type Non Valuated (So it has no valuation class). The PO Order type used and the PO account assignment category is of type saying GR Non Valuated.
    Problem is in the outbound delivery (movement type 645 determined) when posting GI do we get a account determination error (M8147 = Account determination for entry 1000 GBB Z001 not possible), saying that no account could be determined.
    Our understanding is that the GI for the delivery demands a Valuation, which we can not do as the material is NON Valuated.
    How to set the GI non valuated for the outbound delivery, so we can avoid this error? please help
    BR

    >
    Krishna Rao wrote:
    > We assigned the GL for GBB in OBY. But, still the error is coming. Is there any other setup we need to do for Non Valuated material to post goods issue from delivery?
    I cant believe that the same error message is coming up after the maintenance.
    you either maintained an entry at a wrong level within GBB or the message must have changed.
    Make sure that you take any information of this message into account (even the spaces)
    the message is certainly not like you posted here: Account determination for entry 1000 GBB Z001 not possible
    the message carries 4 variables , not only 3