SRM 7.0 Central Contract-For Centralized Purchasing Scenario

Hello Experts
Is it possible to set up a corporate (read Centralized) Purchasing strategy, where in One Central purchasing organization creates and manages Central contracts for various Plants assigned to different company codes using SRM 7.0 with ECC Backend?
Tried to set this scenario up by assigning Purchase organization directly to Plants (in ECC) but the Contracts were failing during replication in ECC.
Any inputs on this are appreciated.
Thanks
Raman.
Note: Contracts went through successfully in ECC after assigning the Purchasing organization to Company code.

Hi,
Please check this.
SPRO -> Enterprise structure -> Assignment ->
Logistics - General -> Assign Plant to company code.
Assign plant to company code
In the IMG activity "Assignment Plant - Company Code" you assign each plant to a company code.
A plant can only belong to one company code.
Note
Complete functionality of the system can only be ensured if the plants assigned to a company code are only those situated in the same country as the company code.
It is therefore recommended that you also create a company code for each country in which a plant is situated.
Examples
Only then are tax postings created when transferring stock between plants in different countries.
The taxation procedure and Intrastat declaration are supported only for the country of the company code.
Requirements
Before you can assign plants to company codes, you must define the valuation control.
You may change the valuation control in the production system only after contacting your SAP consultant. Changes may cause inconsistencies in documents.
Actions
Assign your plants to company codes.
Regards,
Masa

Similar Messages

  • Central Contract for various company code

    Is it possible to create a central contract for several company code & to Generate Contract release order to a particular company code.

    Hi Chandra
    U can Go for centrally agreed contract
    Contract items can relate to a single plant or to all plants covered by a purchasing organization (centrally agreed contract).   
    All the plants of a purchasing organization can order against a centrally agreed contract.   
    An enterprise working with a central purchasing organization covering several plants can negotiate better conditions at a high level.  
    Centrally agreed contracts can be entered into with a vendor’s entire corporate group. The individual contract release orders can be issued to different individual companies belonging to the vendor corporate group. This is made possible by the partner functionality.  
    You can stipulate that certain plants are to be supplied by certain companies belonging to the vendor corporate group.
    Vishal...

  • Creating Central Contract using Reference Purchasing Org

    Hi,
    We are using two type of purchasing organization:
    a.Global Purchasing Organization - It is not assigned to any company code or plant.
    b.Country Purchasing organization u2013 It is assigned to Global Purchasing Organization. This cross-plant country specific purchasing organization is to procure materials for several plants independent to a company code. We have assigned the purchasing organization to the plant and not to a specific company code.
    Global purchasing organization has been setup a reference purchasing organization to be able to create central contracts that is independent of company code and plant.
    However whenever we create the central contract using the reference purchasing organization, the system will not proceed unless we define a company code. Please let me know how we can avoid the Pop up message u201CThe Purchasing organization XXXX has not been assigned to a company code. Please enter a company code.u201D
    Please note that neither Global nor Country purchasing organization is assigned to company code. The company code will be determined only from Plant.
    Please help.
    Regards,
    AG

    Hi.
    In your case, both the Purchase organizations ( Global Purchase Organization & Country Purchase Organization ) are not assigned to the company code. But Country Purchase Organization is assigned to the plants from the different company codes and Global Purchase Organization is not assigned to any plant also.
    In this case, If you are creating central contract with the Global Purchase Organization , you will get error. Becuase Global Purchase Organization is not assigned to any company code or plant.
    If you are creating central contract with the Country Purchase Organization, system will allow. Because this purchase organization is assigned to the plants from the different company codes. Based on this plant, system will identify company code.
    So, conclusion is Purchase organization is must be assgined to the plants. This setting is mandatory in order to indentify company code which is giving in the Purchase document. But the assignment of company code to the purchase organization is optional.
    So, assign plants to the Global Purchase Organization and try to create central contracts. It will work.
    Regards
    KRK

  • Where to start central instances for central adaptor engine

    hi all,
      in integration directory under cache notifications for central adaptor engine (central instances) are  stopped.
    please how can i restart the cache instances.
    regards,
    krushi

    Have you tried the tips given in the SAP note...
      Go through this PDF https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/1a69ea11-0d01-0010-fa80-b47a79301290
      it shud help u to troubleshoot the problem...
    Regards,
    Prasanthi.

  • SRM Central Contract

    Hi,
    We have created successfully Central contracts and distributed to ECC 6.0. I have created Central contract for central purchasing org A as 45xxxxxx and distributed contract for purchasing org B as 54xxxxxx
    I have created purchase order for purchasing org B in SRM. Can I use distributed contract for purchasing org B in SRM?
    Do I have always go for PO creation for purchasing Org A in SRM?
    Thanks
    Ravi

    Hi Ravikumar,
    You donot need to distribute back your ECC contract to SRM system.
    The concept of central contract is to use one contract to be used across system landscape.
    You can assign local purchasing organization as well as backend purchasing organization to a central contract for distribution. For backend purchasing orgs, the system will create individual contracts for the backend porg. Any consumption of backend contract will keep the central contract in sync. For local SRM porg, it will not create separate contract. It can directly use the central contract in SRM.
    So, the answer to your question is big yes. However, it will be relevant only if you are working with extended classic scenario. In classic scneario, the local contract will not be populated for consumption.
    I hope, it helps you.
    Thanks and regards,
    Ranjan

  • SRM 7.0 Call offs against Central contracts

    Hello,
    We are implementing Central contracts in extended classic scenario.We found that when call offs are done in srm by creating a PO in SRM with central contract as Source of supply, the Central contract fields in PO Line item does not get populated when the PO is transferred to ECC.Nor does the Release value get updated against the Backend contract (as seen in ME33K) though the release value is getting in SRM Central Contract document.This makes the release values in ECC Contract document out of sync with the value in SRM contract document.
    Has any one faced this issue? Is this because of a missed setting or Is this a bug or is this the way it works?
    Thanks
    RamanAK.

    Hi
    give more details of the CCTR contract USAGE in the existing landscape
    i could remember the PCTR behaviors in the ECS mode..
    Actually contract information will not be transfered  in the PO line when replicate to ECC since this contract is local.
    the release values are available only in SRM front end ( total value of contract as well as each line of contract vs PO released).
    Did you distribute the contract to backend system as well ?
    so now your contract is available for both system
    i.e ECS - shopping cart - SRM
    and ECC purchase request as well - ECC
    Are you enjoying the contract in the both systems?
    Earlier GOA release values are updated in SRM via BLAREL idoc technology
    but now adays in CCTR interfaces
    PurchaseorderErpcontractReleaseNotificationOut - ECC
    PurchaseorderErpcontractReleaseNotificationin - SRM
    The release value synchronisation continous challenges to the BUYER .
    So please clarify with SAP how SRM PO release value and ECC PO release value sync in the ECC purchasing contract.
    dOUBLE CHECK
    PurchaseorderErpcontractReleaseNotificationOut - ECC
    PurchaseorderErpcontractReleaseNotificationin - SRM

  • Central Contract Management in case of Classic Scenario

    Hi,
    At our current implementation, requirement is to implement both Service procurement(with hierarchy) and Central Conract Management. I was exploring the possibility of utilizing Central Contract Management with Classic scenario.
    Will the Central Contracts created in this fashion be available in Sourcing Cockpit for the buyer to select against Purchase Requisitions? Will the Central Contract be visible at all in SRM in this case ?
    Please respond only with reference to Classic scenario.
    Thanks,
    Abhilash

    Yes the Central Contract will be available in the Sourcing Cockpit, both local and classic scenario's. Yes the Central Contracts will be available for the creation of Purchase Requisitions in R/3 and to assign SOS in R/3.
    Do know that for SRM 7.0 PI is required for setting up Central Contracts. This is promised to change with the release of EHP1 for SRM (due june 2010).
    Kind regards,
    Tim

  • Updation of central contract

    Hi all,
    We have a SRM 7.0 system with ERP 6.0 as the backend. I have created a central contract for an item - A with vendor - B  in SRM and distributed it to a purchasing organisation (3002) through assign distribution functionality.
    Now when i create a shopping cart for item A , the central contract appears as a source of supply and i can proceed with ordering of this item. But the problem i am facing is that the central contract is not getting updated in the backend ie the quantity does not decrease after buying the item - A.
    Pl let me know if any message types need to be defined for updation to be posssible.
    Thanks.

    Hi Nikhil,
    How did you fix this issue? I've created a central contract in SRM 7.01 and distributed successfully to ERP. When i created the PO in SRM, SRM contract release values is not updated in SRM.Or when i created PO in ERP using SRM contract as SOS, that PO is not updating SRM release values.
    Regards,
    Gigies

  • Central Contract in Classic Scenario

    Hi Friends,
    I have done the central contract scenario in Ex classic  where Local contract will be distributed to ECC .
    Can we use the central contract concept in Classic Scenario and is there any limitation based on scenario.
    As in classic the documents are created in ECC , so for central contract also there will be no local contract ???
    Can anyone please help me to understand the same.
    Thanks
    IS

    Hello,
    Yes, this concept can be used in classic scenario as well.
    You can use them as source of supply, since in classic scenario ECC contracts are considered as soruce of supply. Therefore, replicated contracts will be proposed as SOS for shopping carts.
    Regards,
    Ricardo

  • Central Receiver role in Classic Scenario

    Hi All
    We have a requirement for a user who can enter goods receipt in SRM on behalf of other users.
    We tried to set up the central receiver role provided by SAP , however encountered some issues:
    1) In the POWL for the central receiver, only the PO's created locally are visible. So none of the Classic PO's in ECC could
    be seen
    2) When in the" Create Confirmation" screen, I manually searched for a PO, It allowed me to proceed One screen, however I couldn't enter a confirmation as I got an auth error:
    Partner xxxxx not found with partner function type xxxx.
    I thought the central receiver was entitled to confirm all PO's without question.
    Kindly advise
    Thanks
    Kedar

    Hi Ranjan
    The only tab I have is Central confirmation & worklist.
    I didn't modify the role , but just using the standard portal & SRM role offered by SAP for Central receiver.
    Inside central conf, I have the 2 problems I mentioned.
    I cannot find backend PO's & secondly when I try to confirm other person's PO/shopping cart I get the partner function error.
    Is central confirmation from SRM , even supported in classic scenario?
    Thanks
    Kedar

  • Badis for PO and Central Contract in SRM 7.0 in classic

    Hi everyone,
    I need you help. We are working in a implementation of SRM7.0 with ECC 6.0 Ehp 4 in a classic scenario. We want to know which badis we can use in order to change the purchasing group of the PO an Central Contract when their are transfered to ECC.
    BR,
    Ivá

    Hi Muthu,
    We are wondering if it is posible the following:
    - An user wants to create PO form SRM. This PO in SRM has the Purchasing group XXX, but (for any reason) we need when this PO is send to ECC, the system changes the purchasing group to YYY.
    BR
    Ivá

  • Purchase Order - Retrieve net price from Central contract (SRM or ECC)

    Hi,
    I'm doing a test by creating a PO referencing a Central Contract, which is made in SRM. When creating the PO, at this moment the net prices is retrieved from SRM.
    Question: Is it possible to retrieve the net price from the copied contract which is in the Local ECC system?
    (Customizing in ECC) SPRO -->Integration with Other mySAP.com Components >Supplier Relationship Management>Central Contract-->Price Calculation
    The value what is at this moment:   SRM Pricing Immediate
    Should the value be: 1 SRM Pricing Immediately Only for Hierarchy Contract Item
    Regards,
    Alexander

    Check for existing screen layout name from below settings -
    Goto SPRO -> IMG Settings -> Materials Management -> Purchasing -> Purchase Order -> Define Document Types
    Check for Field selection key against the PO Type.
    Then goto below setting -
    SPRO -> IMG Settings -> Materials Management -> Purchasing -> Purchase Order -> Define screen layout at document level
    Select the screen layout / Field selection key in this setting and modify the field selection group Quantity and price. Make Price and price unit as display only as per your requirement.

  • SRM, MDM, ECC integration for central contract management.

    Hi there,
    I am questioned by a client with respect to the possibility of the following scenario -
    1. There are several SAP back end systems in place.
    2. SRM 7.0 will be implemented as single sourcing system.
    3. The SAP back end systems carry different material master codes for the same material and this will remain the same and no cleaning effort to have a unique code across all systems is going to be done.
    4. If we use MDM in the mix - will it be possible for the SRM system to act as a central contracting solution and create a central contract with the unique material code in MDM.
    5. On distribution of this contract across to individual SAP back end system the back end should map the MDM code to correct material code in that respective system.
    Any insights with respect to if this is possible with some enhancements or not at all possible will be highly appreciated.
    Thanks and Regards,
    Shantanu Joshi

    Hello Shantanu Joshi
    Your business scenario is standart MDM functionality
    More about how it works you can read from:
    MDM overview
    and standart help links (see scenarios part):
    http://help.sap.com/saphelp_mdm550/helpdata/en/43/D7AED5058201B4E10000000A11466F/frameset.htm
    http://help.sap.com/saphelp_nwmdm71/helpdata/en/43/D7AED5058201B4E10000000A11466F/frameset.htm
    Regards
    Kanstantsin

  • SRM -- MDM -- ECC integration for central contract management for SRM 7.0

    Hi there,
    I am questioned by a client with respect to the possibility of the following scenario -
    1. There are several SAP back end systems in place.
    2. SRM 7.0 will be implemented as single sourcing system.
    3. The SAP back end systems carry different material master codes for the same material and this will remain the same and no cleaning effort to have a unique code across all systems is going to be done.
    4. If we use MDM in the mix - will it be possible for the SRM system to act as a central contracting solution and create a central contract with the unique material code in MDM.
    5. On distribution of this contract across to individual SAP back end system the back end should map the MDM code to correct material code in that respective system.
    Any insights with respect to if this is possible with some enhancements or not at all possible will be highly appreciated.
    Thanks and Regards,
    Shantanu Joshi

    Hello Shantanu Joshi
    Your business scenario is standart MDM functionality
    More about how it works you can read from:
    MDM overview
    and standart help links (see scenarios part):
    http://help.sap.com/saphelp_mdm550/helpdata/en/43/D7AED5058201B4E10000000A11466F/frameset.htm
    http://help.sap.com/saphelp_nwmdm71/helpdata/en/43/D7AED5058201B4E10000000A11466F/frameset.htm
    Regards
    Kanstantsin

  • Badis for Central Contract Replication from SRM to ECC

    hi
    experts
    i am working on a scenario of replicating the central contract from SRM 0.7  to ECC via XI/PI
    let me know what are the Badis to be implemented in ECC for the Same
    looking forward for your  reply

    Hi,
    You do not need any Badi in ECC to distribute central contract to your backend system.
    if your ECC system is on ECC 6.0 enpk 4.0 or more,
    you can directly distribute your central contract from SRM to ECC system using standard ESOA services.
    Thanks and regards,
    Ranjan

Maybe you are looking for

  • Oracle rac o2cb

    I am setting up oracle rac on 2 nodes. Redhat5.5 x64 on vsphere4,esx4.0,FC disks. I have 1 ocr disk,1 voting disk and 3 asm disks.All on vmware raw device mapping. Ocr and Voting are on ocfs2 block devices.I installed grid infrastructure and cluster

  • Trouble playing a complete .mov or .mpeg file

    Hello folks. I'm having trouble playing some downloaded .mov and .mpeg files. For example, I've downloaded a 50MB file and it only plays about the first 30 seconds of the file. However if I put the same file into VLC, I can see the whole movie (albei

  • GPS coordinates are not appearing in LR 5.6

    Why can't I see GPS coordinates in my Mac Pro? I am able to read GPS Coordinates when viewing LR 5.6 in my MacBook Pro but not when viewing the same files onto my Mac Pro. Mac OS X 10.9.5  LR 5.6  ACR 8,6  Nikon D810.  As well I cannot turn off XMP f

  • Can I use this on a tablet?

    with andriod or ios?

  • Start up not happening

    I installed some software (no i don't know which ones i trusted my mac to just know ) and then shut it down. My power did go out that night. I came down the next day to start it up and it was on and just had the apple symbol on the white screen with