Hi all,
Is there any standard report in PM where i can find Maintenance order number,Purchase Requisition no., Purchase order no. and the services taken in the maint. order.
If such a report is not there, pls tell me the logic to create it.
Thanks
Sabyasachi Banerjee
Hi.
Please find below tables for your logic
Technical Objects -
> IFLO,ITOB, EQUI
Maint Orders----
> AUFK,AFVV,AUFM,AFPOAFVC
Reservation & Conf----
>RESB,AFRU,REUCK
Materila Document -
>MSEG,
PR----
>EBAN,EBKN
PO----
>EKPO,EKKO
SES----
>ESSR
Ramesh
Similar Messages
-
Standard report for sales order
HI all
I would like to know whether there is any standard report for sending confiramtion mail to customers once the shipments are planned.
Or atleast to track the status of sales order (to find out whether the shipment is planned) so that i can club the mail program with this.Hi,
Check the following links:
http://sap-img.com/abap/make-e-mail-sender-of-po-the-po-creators-name.htm
http://sap-img.com/abap/sending-mail-when-the-purchase-order-is-released.htm
Regards,
Bhaskar -
Standard report for Open Orders & JIT lines
Hi,
I need a standard report that will list out all open Purchase Orders and All Open JIT lines for a Supplier for Perticular plant.
Is there any standard report that can pull this data.
Regards
SandeepUse ME2M / ME2N and ME2L reports with selection parameters WE101 and scope of list EINT
-
Standard report for production order
Dear all
Is there any standard report with reference to material for all procuction orders ie open,closed etcHi,
COOIS - Production order information system
For Open Prod orders
Enter material number and sys. status CNF tick Excl.
For Closed Prod orders
Enter material number and sys. status CNF, DLV.
Regards,
Sankaran -
SAP Standard report for Purchase order Amendments
Hello MM Gurus,
Kindly let me know whether any standard report available in SAP on
Purchase order amendments.
Regards
YogaHi Yoga,
You can do a small work around.
Activate version management in PO.
Then, you can get the list of changed POs from the transaction ME2N, by clicking on the dynamic selection icon (icon with 3 colored lines) and entering values for the "Version" field.
You can enter multiple values there, say, 1,2,3..5, depending on the maximum number of versions that will be created.
This selection will give you the list of amended POs.
Regards
sampath -
Standard report for Planned Order
Hi
Can i Know the standard report T Code for the Planned order.
Thanks
VijayDear
Use T- code SE16N and there u enter PLAF table name ( planned order details) and execute ull get the complete details of planned orders
With Regards
Pushpalas -
Standard reports for Sale Order costing
Hi all
Can anybody Please tell sale Order costing reports.
Thanks
Sandeepfor doing mass sales order costing use CK55
or for individually in VA02 -->Extra --> costing.
& for report use KKAC.
rgds
Arpit.
Edited by: Arpit Shah on Jan 1, 2008 2:34 PM -
Standard Report for Quotation Order conversion status
Here i need a report where i can see the list of Quotations and Whether it has been converted to order or not.......
Hi,
In case your business process starts from quotation then you dont find quotation number in VBFA-VBELV in case the quotation is not converted into order.
Check this logic for your report
VBAP-VBLEN (Quotation Number) = VBFA-VBELV
If VBFA-VBELN is not initial, then quotation is converted. VBFA-VBLEN is orer number.
Hope this helps.
Regards,
Sharan -
Standard report for sales history.
hi,
i need a standard report for sales history(all sales order ) for my company code. in va05 transaction it shows only for sales area. give the tcode .
regards
muthuraman.dHi,
There is no standard report for sales order list on the basis of company code.u have to develop it.
OR
Create report with SAP Qury
OR
u can us VA05N tcode >>> Speciefy sales organization from - to (all sales organizations from one company code).
Kapil -
Standard report(for open PO order items) with estimated Delivery dates
hi friends
i would like to know if there is any standard report(for open PO order items) with estimated Delivery dates on it.
thanks
alahariME2M (by material)
ME2L (by vendor)
ME2N (by number)
Use selection parameter WE101 for open GR
and scope of list EINT (scheduling lines) -
Standard Report for missing parts at production order operation level?
Hi PP Gurus,
We have standard report for missing parts at production orders level.
For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
Please help.
Thanks,
Reddy.Hi Arvind,
Thanks for for your response.
1. List: Components, Layout: Standard layout set the Missing part
It shows the component requirement/withdrawn quantity for each operation of production order. It is not showing the commit quantity.
2. List: Components, Layout: Pick list set the Missing part
It shows the component requirement/withdrawn quantity for each production order.
3. List: Components, Layout: Missing Parts List-Material View set the Missing part
It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
4. List: Components, Layout: Missing Parts List-Order View set the Missing part
It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
We are unable to get the solution from all these 1 to 4 reports from COOIS.
Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
If avilable, what is the procedure to be followed?
Thanks,
Reddy. -
Can we take standard report for all sales orders based on the condition typ
Hi all,
Based on the condition type, we need to take a report for sales orders on the particular date.
Thanks and Regards.....VMHello again.
Searching for a solution, I found a Logical Database for sales orders, that have all the information that you need.
Using like reference the post of Bhagavatula, in the same transaction SQVI you can use, instead of the suggested join, you can select a logical database called VAV in Data source.
This logical database links the tables, VBAK, VBAP, VBUK and KONV that is the central point of the question.
You can list the information of logical database using the transaction SLDB.
In 'Logical Database' inform VAV.
Press F8 to list all the fields.
More information about logical database in:
Link: [SAP Logical Database|http://help.sap.com/saphelp_46C/helpdata/EN/9f/db9b5e35c111d1829f0000e829fbfe/content.htm] -
Standard report for solve inconsistencies with user SAP.
Dear Experts.
We have a problem with a user(ZEST) that in the portal when I open a service(application) display a blue Window of Internet Explorer without display information.
We have copied this user((ZEST) TO (ZEST2 )with the same roles , however this user new work fine.
My question is:
There are a standard report for solve inconsistencies?
We have deleted the user and have created it of new, however this not work.Run the t-code SA38
Specify the name POWL_D01
In selection screen specify the user id in USER field of which your facing issue
Click on Execute
Run the T-code SA38
Specify the name POWL_WLOAD
In selection screen specify the user id in User input field of which your facing issue
Click on Execute
Now you check it issue will solve. -
Require Standard DataSources for Purchase Orders
Hi,
Please provide me the standard datasources for purchase orders to get the data updated automatically in a BI System.
I have to display report containing the purchase orders details of each day.
Regards
Sunil KumarHi,
Following link will give you complete details of purchase order deports and data sources.
http://help.sap.com/saphelp_nw70/helpdata/en/df/cfb839f6a7a307e10000000a11402f/frameset.htm
Regards,
Vishnu -
Standard report for the cost of raw materail in production of finished good
Is there any standard report for calculation of raw material cost from the production order of finished goods.?
plz help in this issue.
Thanks.closed
Maybe you are looking for
-
Help! Extending PDF adds duplicate pages
I am creating a dynamic XML form. There are 2 sections in the form where the user may need to add additional pages, which I have added buttons for using instanceManager. Everything works just swell, until I open it in Acrobat to extend the features s
-
Undo GR with a deleted delivery note
Hello, I don´t know if somebody has been in the same situation and could help or give us a solution: We would like to undo the Goods receipt from a Purchase order, but SAP doesn´t allow it due to the delivery note has been canceled by mystake. T
-
Building reports into word document from web application
Is there any package that allows easy report generation into microsoft word from any part of ur application. thank yuo
-
RSS in Collab 4.5 Working?
Did the RSS feature in Collab 4.5 work for you? I am currently getting an error "HTTP Status 400 - Invalid path /project/module/ was requested" When I click on the RSS image. I have imported the web service as suggested on the function1 blog. This is
-
My hue/saturation filter quits working in Photoshop CS3
I keep having this issue where my hue/saturation filter just quits working. I use that filter religiously so it has to be fixed each time it occurs. I've only had the Adobe CS3 for 3 months and I've had to resolve this 3 times now. Each time this