Start/Finish vs Schedule Start/Finish vs Actual Start/Finish

Hi,
I'm new to MSP 2013 and I'm confused on the way MSP handles Start/Finish dates. While I understand the rational of it adjusting the schedule so you see how actual dates impact the schedule, I find it confusing that there are multiple columns with different
labels performing the same function?
"Scheduled Start" would lead you to believe this is your initial planned start date and remains static while "Actual Start" would be, well, the Actual Start date. So one value by definition would be different than the other, yet when any
of these dates, "Scheduled Start", "Actual Start", or "Start" are changed, they all change to the same value.
My questions are:
Why do the "Scheduled Start", "Actual
Start", and "Start" dates all change to the "Actual Date" when entered?
Is there a scheduling technique or purpose for this to work this way?
Also, since the "Scheduled Start" date changes, how does MSP 2013 handle Earned Value?
       Since Earned Value calculations rely on your Planned Value which would be based on the Budgeted Cost of Work Scheduled          and the Earned Value which is
the Budgeted Cost of Work Performed vs. the Actual Cost of the Work Performed at "a point          in time," how could it provide a reliable figure if the scheduled date is moving? Is it using the "Baseline Start/Finish"?
I hope you can answer this for me or direct me to a resource that can. Thank you for your consideration.
Marc      

Marc,
When Project was first released there were only two basic start field, Start and Actual Start (in addition of course to the Baseline Start field and a few others). With the release of Project 2010, a manual scheduling mode was introduced. That's when things
got a little more confusing. Instead of leaving the Start date as is, the Start field was converted to a text field and the old Start field was renamed as Scheduled Start. When in auto-schedule mode, both Start and Scheduled Start are exactly the same.
Now to answer your questions. To keep it simple, let's assume you are using auto-scheduling.
1. In order to keep the schedule dynamics intact, it is necessary to update the Start field to agree with what really happened, namely with the Actual Start date. If you do not enter anything into the Actual Start field, Project automatically assumes the
task started as scheduled, on the Start date.
2, Yes, Project does its scheduling based on the current plan which is represented by start, finish and other data. Once the project starts, that current plan must be updated so the actual date values come into play. As noted in the lead in paragraph, Scheduled
Start and Start are the same for auto-scheduled tasks.
3. Earned value is based on the actual values and the saved baseline data. The "point in time" you refer to is the timescaled data as of the status date.
Hopefully, this clear up at least some of your confusion.
John

Similar Messages

  • Why do Start/Finish dates automatically change to match Actual Start/Finish dates?

    Please excuse my ignorance, but what is the
    rationale for MS Project automatically changing the "Start" and "Finish" dates to match the "Actual Start" and "Actual Finish" dates when they are inputted?  Can this "feature" be disabled?
    Thanks in advance for any assistance.

    Hi,
    In the end, yes, once actuals are recorded, all these values are the same - but before that they can all be different!
    Before an actual start is recorded, the column shows "NA" (wich obviously is different from Start :-)). To the scjheduling engine, thsi means the start can be freely calculated (from predecessors or resource leveling, f.i.) whereas when a date
    appears in Actual Start, Project will take that value as carved in granite - it is supposed to show past reality, and reality is more powerful than values calculated by the scheduling engine!
    So these two values are not Always identical!
    As for Scheduled start, that is indeed meaningless for automaticlly calculated tassk. But for manually scheduled tasks it does play a role. For a manually schduled task, you can set any start value you want (even a litteral such as "when we have
    the time"). Still, there is an option to make manually scheduled tasks obey links - the result of that calculation is then put into scheduled start - and so there can be a difference between these two columns as well.
    So, no, these 4 values do not have the same function. They are ony identical as soon as actuals are recorded but what do you expect? There is only one past reality, Project does not work with a parallel universum :-)
    Hope this helps,

  • Early schedule start date, early schedule finish date

    I want early schedule start date, early schedule finish date and project cost plan in my report. This is a PS requirement. In the standard cube (0PS_C02) I can find actual start date and actual finish date. Has anybody used early schedule start date and early schedule finish date in the reports? If yes then did you get it using standard cube/ODS or you went for enhancement?

    HI,
    He have to go for few tables in which u can find all the data.
    Firstly u have to enhance the datasource .
    First go to table AFKO here you insert  AFUNR (Order Number) this table you will get AUFPL .
    Then take AUFLP and go to AFVV table and insert AFUPL . you will get all the activites and all dates of each activity  for example early start date ,early finish date, foirecost date etc.
    Thanks and Regards
    Dinesh

  • 2LIS_04_P_MATNR Delta - Actual Start and Finish Dates

    My company is experiencing a problem with retrieving the actual start and finish dates and times from the 2LIS_04_P_MATNR data source with delta extraction. The R/3 source system is version 4.6C. The BI system is version 7.0. Specifically, the data source fields GETRI, GEUZI (finish), GSTRI, GSUZI (start) are sometimes never populated with data. These fields are often blank in the production data extracted. It was observed that the actual delivery date for the order (posting date of goods receipt from process order) was often an earlier date than the GETRI date. This scenario was tried in test systems, and it was found that if the final goods receipt for the process order was posted before the end of the last phase was confirmed, the actual finish date and time fields were not transferred to BI from R/3. In fact, it was noted that a new record was not created in the 2LIS_04_P_MATNR delta queue when the end of the last phase was confirmed. Regarding the actual start data, this is missing if a goods receipt from the process order is posted before the start of the first phase is confirmed.
    Has anyone else experienced this problem? How was it resolved?
    SAP Notes have been searched regarding this problem, and in fact, a customer message has been opened with SAP for this problem. However, we thought we would try asking the community as well, to see if any other users have experienced this, and how the problem was resolved. We also understand that it may be an unusual practice to post a goods receipt from the process order before the end of the last phase is confirmed. In a more general sense, has anyone else experienced that some of the data source fields are never populated if the R/3 information is entered after the posting of the final goods receipt against the process order? Our testing indicated that no more delta records are created for the 2LIS_04_P_MATNR data source after the final goods receipt was posted.
    Thank you,
    Chris Sopek

    Hello,
    we are experiencing your same problem! The only difference to your scenario is that wer are currently operating on SAP ECC 6.0.
    Did you receive any answer from SAP?
    We opened a request for the same topic.
    Thanks

  • Making actual start & finish time fields mandatory in COR6

    I need to make the actual start time (AFRUD-ISDZ) & actual finish time(AFRUD-IEDZ) fields mandatory in COR6. Currently the system gives a default value of 00:00:00.

    Hi Manish,
    Have you also checked changing the setting for these fields
    AFVGD-isbz...?
    Also one more option would be use of transaction variant.

  • Request vs Actual Start Date in Scheduler Jobs

    Hi, I want to run a PL/SQL block, all days, at 1:00 AM
    I've defined the following scheduler job, in a new (and empty) Job Class:
    <font face="Courier New">
    SQL> select job_name, repeat_interval, job_class, job_priority from dba_scheduler_jobs where job_class = 'MY_NOCHE_JOB_CLASS';
    JOB_NAME...........: UNIFICA_CLIENTES
    REPEAT_INTERVAL....: FREQ=DAILY;BYHOUR=1;BYMINUTE=0;BYSECOND=0
    JOB_CLASS..........: MY_NOCHE_JOB_CLASS
    JOB_PRIORITY.......: 1
    </font>
    However, the process is starting later, for example:
    <font face="Courier New">
    Request Start Date....: Nov 10, 2010 1:00:00 AM -02:00
    Actual Start Date.....: Nov 10, 2010 4:06:33 AM -02:00
    </font>
    Why is the difference between Request Start Date and Actual Start Date ?
    Is there any way to enforce the start of the Job at any time ?
    OS: Solaris 10 8/07 s10s_u4wos_12b SPARC
    DB: Oracle Database 10g Enterprise Edition Release 10.2.0.5.0 - 64bit Production
    Thanks in advance

    The database is not down since at least 2 months
    <font face="Courier New">
    SQL> select LAST_START_DATE from DBA_SCHEDULER_JOBS where job_class = 'MY_NOCHE_JOB_CLASS';
    LAST_START_DATE
    ────────────────────────────────────
    17-NOV-10 04.21.00.447083 AM -02:00
    </font>
    Any advice ?

  • I rented a movie directly from Apple TV. I finished downloading successfully, however, I didn't start watching it right away. Now, a day after, I want to watch it, but ATV tells me I have to start the downloading process all over again. WHY?

    I rented a movie directly from Apple TV. I finished downloading successfully, however, I didn't start watching it right away. Now, a day after, I want to watch it, but ATV tells me I have to start the downloading process all over again. WHY? I thought after sucessfully downloading the movie to ATV, it would be available for 30 days in my ATV, without having to download again. To my surprise, it tells me I have to download all over again. It took me 3 hours to download the movie, now I have to repeat the process? Can someone tell me why? Thanks.

    Welcome to the Apple Community.
    The Apple TV will delete content if it is used to plat something else or is turned off. It only has a limited amount of volatile memory.
    If you want to download something for watching at a later time, it would be best doing it from iTunes on your mac/PC and streaming it to the Apple TV when you are ready to watch it.

  • HT1657 I rented a movie and started playing it, but it stopped downloading, and didnt finish within the 24hrs it should... Now I didnt watch crap and dont have a refund nor do I have a way to watch it, and worse yet no way to even re-buy it....

    As the title says....I rented a movie and started playing it, but it stopped downloading, and didnt finish within the 24hrs it should... Now I didnt watch crap and dont have a refund nor do I have a way to watch it, and worse yet no way to even re-buy it....
    I want to see what i rented or get refndeed...
    I will be contacting me credit card tomorrow.
    thanks

    Have you tried contacting iTunes Support (these are user-to-user forums) ? If not then try the 'report a problem' page to contact them : http://reportaproblem.apple.com
    If the 'report a problem' link doesn't work then you can try contacting iTunes support via this page : http://www.apple.com/support/itunes/contact/- click on Contact iTunes Store Support on the right-hand side of the page, then Purchases, Billing & Redemption

  • When does a work cycle on a mailbox server actually start in Exchange 2010/2013?

    So the question came up in work today as to when a work cycle on a mailbox server (e.g. ManagedFolderWorkCycle) actually starts. For example if it's set for 7 days, what 7 days does it choose? Is the first day the day the server was last
    restarted? Or is it the day the MSExchangeMailboxAssistants service was restarted? Is there some set day and hour considered the start? Or something else i'm not thinking of? I've checked various technet
    library articles but it doesn't state how the exact start date and time is derived.

    Hi Iczersigma,
    According to your description, it seems ManagedFolderAssistantSchedule
    that Ed mentioned is the great method to specify the date of service restarting. And I notice that this parameter also used in both Exchange 2010 and Exchange 2013, not only for 2010 RTM.
    Detailed information about this parameter as below:
    The ManagedFolderAssistantSchedule parameter specifies the intervals each week during which the Managed Folder Assistant applies messaging records management (MRM) settings to managed folders. The format is StartDay.Time-EndDay.Time. You can use the following values for the start and end days:
    •Full name of the day
    •Abbreviated name of the day
    •Integer from 0 through 6, where 0 = Sunday
    The start time and end time must be at least 15 minutes apart. Minutes are rounded down to 0, 15, 30, or 45. If you specify more than one interval, there must be at least 15 minutes between each interval.
    The following are examples:
    •"Sun.11:30 PM-Mon.1:30 AM"
    •6.22:00-6.22:15 (The assistant will run from Saturday at 10:00 PM until Saturday at 10:15 PM.)
    •"Monday.4:30 AM-Monday.5:30 AM","Wednesday.4:30 AM-Wednesday.5:30 AM" (The assistant will run on Monday and Wednesday mornings from 4:30 until 5:30.)
    •"Sun.1:15 AM-Monday.23:00"
    If the managed folder assistant doesn't finish processing the mailboxes on the server during the time that you've scheduled, it automatically resumes processing where it left off the next time it runs.
    For your reference:
    http://technet.microsoft.com/en-us/library/aa998651(v=exchg.150).aspx
    http://technet.microsoft.com/en-us/library/aa998651(v=exchg.141).aspx
    Thanks
    If you have feedback for TechNet Subscriber Support, contact
    [email protected]
    Mavis Huang
    TechNet Community Support

  • Exit/Badi for Updating Actual Start Date in CJ20N

    Dear Experts,
    In transaction CJ20N, under Dates Tab for a particular Activity, there is one field viz. Act i.e. Actual start: Execution (date). My requirement is to display PR date in this field. Besides this, Actual finish: Execution (date) should also get updated depending on the Duration field.
    I searched all the exits in the package 'CN' and 'CORU', but none of them seems to be useful
    Please suggest a user exit/BAdI which could help resolve this.
    Thanks in advance

    Hi,
    That BADI would trigger when you change any thing on the WBS and hit save.
    WORKORDER_UPDATE-for network
    Regards,
    Himanshu

  • Actual start date in order

    In any of my order type i cant see actual start and actual finish date and it remains blank though order gets completed.
    Wat can be a possible reason or is there any specific settings for that ???

    Iftikhar Qayyum,
    There are a few OSS Notes relating to your issue.
    Search [OSS|http://service.sap.com] using CAUFVD-GSTRI
    PeteA

  • Actual Start Date vs Actual End Date - Activity

    In an Activity, I would like to seperately enter the Actual Start Date and Actual End Date.
    - If I try this using (partial) confirmation,  I receive a pop-up with an error that the two dates must be entered together or no dates can be entered.
    The activity in my project can take over a year to complete and the requirement is to confirm start (at start) and to confirm end (at end).
    Does anyone know of a solution for this issue?
    Thanks in advance!

    Hi Patrick,
    I think you need to research a bit more on confirmations in PS. Actual dates in partial confirmations are practically interpreted as provisional actual start dates and actual finish dates. The actual start for the activity remains the same however the actual finish date is overwritten once the final confirmation is entered.
    For example, take an activity with start date 05.09.2011 and finish date as 14.09.2011. Now when you provide confirmations on a daily basis, you can use the following strategy:
    Day 1, 05.09.2011: actual start 05.09.2011, actual finish 05.09.2011, % complete 10%
    Day 1, 06.09.2011: actual start 05.09.2011, actual finish 06.09.2011, % complete 20%
    Day 1, 07.09.2011: actual start 05.09.2011, actual finish 07.09.2011, % complete 25%
    Only when you provide the final confirmation the actual finish date is confirmed. The various confirmation line items may be viewed via CN48N.
    Regards,
    Ammar

  • Need to update the actual start date & time of a operation in workorder

    Hi Experts,
                   I need to update the Actual Start date and Actual start time of a Operation of  a WorkOrder through a Function Module.
    I was looking into the BAPI_ALM_ORDER_MAINTAIN FM, but i couldn't find any field relating to the actual start date and start time of a operation.
    Kindly Suggest me which Function module i can use to complete my task.
    Thanks in Advance
    bye

    Hi,
    It is system's standard behavior and no other MRP type will help you in moving the start date outside the planning time fence. With MRP type P3 new requirements are covered at the end of the fixing period, the end date is set and planed order is scheduled backword. Hence the start date will lie within the planning time fence.
    Rgds,

  • I have noticed an issue with utilizing the "stream" function on iOS 7. If you choose to just stream the movie by hitting the play button it seems to actually start downloading (which is fine) but if you are say halfway thru the movie and stop you can clea

    I have noticed an issue with utilizing the “stream” function on iOS 7. If you choose to just stream the movie by hitting the play button it seems to actually start downloading (which is fine) but if you are say halfway thru the movie and stop you can clearly see that storage has been reduced under the usage, yet under the “videos” tab it still states “No Data” the only way to delete what you have partially downloaded is to fully download the video, which is fine but there is no way to tell what videos have been partially downloaded (I.e which occurs a lot when your child switches between movies using the so called “stream” function). This becomes troublesome once the capacity of the ipad is almost met and you have no way to delete this data since you may have several videos that have started to be viewed (hence partially downloaded). Apple needs to somehow make it truly streaming or provide an update so the storage can be managed. The only way I have been able to remove partially downloaded videos is by doing a total software restore. (The video data that is in question when connected to my MacBook shows up in iTunes as “other”) if you have any insight into this issue it would be greatly appreciated. Thanks.

    Here are the screenshots for what it's worth.
    Not sure why I can't post them in the original post.<br>
    <sub><b>Mod edit: See [https://bugzilla.mozilla.org/show_bug.cgi?id=718813 bug 718813]</b></sub>
    '''Again, when I set my DNS server to automatically detect the servers both problems disappear and I have no issues at all.'''
    IMO opendns is either doing this on purpose (unlikely) or they're under some sort of attack/being used to attack the specific torrent sites although I'm open to other explanations. I believe using the automatic setting for DNS is using my own ISP's DNS servers (which again, work fine... but still...)
    I'd rather not use Google's public DNS servers as Google is to commercial these days and I think there's potential privacy issues.
    '''Again I have changed the setting for DNS servers back and forth several times to duplicate/verify the issue(s)... and the issues only happen with the opendns servers.'''

  • BI Scheduler Service is not getting started

    BI scheduler service is not getting started and showing this error
    Could not start the oracle BI Scheduler Service on local computer.
    Error 1064:An Exception occured in the service when handling the control request

    Refer to Oracle Business Intelligence Infrastructure Installation and Configuration Guide.
    Chapter 10 discussed configuring Oracle BI Scheduler.
    The steps include:
    Create a scheduler schema.
    Create tables in the scheduler schema using scripts.
    Updating configuration options in Job Manager.
    Updating the config files: instanceconfig.xml & credentialstore.xml.
    Start the Oracle BI Scheduler.
    If all goes well, the BI Scheduler should start.

Maybe you are looking for