Statistical WBS and Network

Dear All,
We have budget control activated on cost centers via the use of PSM. We now want to use Project System module to execute a project for which cost will be charged onto a cost center. An option already investigated is that of using statistical WBS, which provides two advantages:
1) No hassle of periodic settlement to cost center as cost is updated simultaneously.
2) Budget control remains in-tact because any cost posted (statistically, i.e. type '11') on a wbs will be posted (actually, i.e. type '4') on the cost center for which budget would be checked.
My problem arises when we try to use networks. It is my understanding that network orders cannot be made statistical and therefore any cost posted to them (either direct journal entry or via PO, GR/IR) is done actually (i.e. type '4') and not statistically. No actual entry is posted on the cost center, and I have to manually run the settlement on the network. This settlement process than automatically posts the cost to wbs which eventually goes as actual cost to the cost center. However this case has two major problems:
1) Increased overhead of periodic settlement for the network
2) No budget control as cost posted on the network can exceed budget available on the cost center (the budget error would only arise when settling the network).
My prime objective is for the budget control to remain in-tact for which i need an option of automatic cost posting from the network to the cost center as soon as it is posted (something possible for statistical wbs).
Any help in this regards would be highly appreciated.
Regards,
Ammar Zaheer

Is there any work around? I heard about periodic reposting, has anyone tried it before? What if I create my PR or PO on the statistical WBS?
Regards.
Ammar Zaheer

Similar Messages

  • Unable to caluclate cost in CJ20 for wbs and network level.

    Hi All,
    I have a query in the project Builder(CJ20N).
    I created Project>WBS Elements>Network> and posted costs via assigning activity.
    If I select an activity and go to edit>Costs,  the "calculate costs" option is activated.  ( I get "Message Costs were calculated: See menu Edit -> Costs -> Planned - Actual")
    And also I am able to view the cost in Edit>Costs> Plan/Actual.. "Activity/Element". Please see the screenshots of Plan /actual comparison.
    However if I select the WBS or Network and go to edit>Costs,  the "calculate costs" option is disabled (frozen) and also in the same path Plan/Actual> "activity/Element"  option is disabled (Frozen).
    Request you to review the attached screenshot and advise is there any way to defreeze the option "calculate costs" and view the costs in WBS and Network level?

    Hi,
    why you want to see plan cost in project builder CJ20n? any specific reason please let us know...
    every structure report having this kind of feather as CN41n/CNS41 then check these two report.
    and lots of hierarchical report is there for seeking plant cost in project as Gokul suggested above.
    so in project builder only plan VS actual cost can be look like by network activity.
    Regards,
    Sanjeev

  • INOB Issue while archiving WBS and Networks

    Hi All,
    I am using PS_PROJECT archiving object for archiving WBS Elements and Networks. But during Write phase, below error message was dislplayed:
    Error Message
    There is no entry for instance 000000000001489184 in either INOB or IBase
    Job cancelled after system exception ERROR_MESSAGE
    Could you please help me when this error occurs and how to solve this problem.
    Version: SAP R/3 4.7
    Regards,
    Sandeep

    Check tcode CUTABLEINFO and insert the instance number you have into the Instance(CUOBJ) field.
    Be sure to check at the very least at the bottom of the screen the check boxes for IBINOBS and IBINOWN.
    The owner of the configuration is the object that originated the instance.
    An observer of the instance is simply an object that needed a copy of the characteristic values in the instance. If any transaction can find your instance's owner, it's this one.
    Or
    You can also refer SAP 1470060 - Error CX 074 (There is no entry for instance XXX in either INOB or IBase)
    Hope it can assist you.
    Thanks & Regards
    JP

  • Statistical wbs and assets

    I am aware that statistical wbs do not settle.  However, someone told me that it is possible for a statistical wbs to direct post to an asset.  I believe they said the asset number was part of the wbs number.  But I don't remember all of the specifics.  Is anyone familiar with this?

    Hi
    Please read note 21583 and 684659!
    Best Regards,
    Blaz

  • ACTUAL COSTS:REPORT WITH STATISTICAL WBS AND ASSETS ASSIGNED TO THEM

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
        Assets assigned to each WBS
              Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    An statistical WBS element is an SAP object . Statistical means that you need another object to post the cost or income, let's say,an asset.
    Actual costs are the real postings you have in an object, coming from MM, SD, GL ... (just the contrary as budget or planned values).

  • User status linking between wbs and network

    Dear All,
    I got one requirement in which i am using user status at wbs level to block all the transactions. Now the  problem which i am getting is that even though i am maintaining the user status at wbs level, users are able to post the data on network activities. If i am maintaining the user status at activity level than i am able to stop the same.
    Kindly suggest cant we maintain user status at wbs level and stop fi posting at activity level. Is there any way to achieve this.
    Regards
    Abhishek Sinha

    Dear Abhishek,
    Use same sataus profile on Neworks also after having included Network activity & Network header as affected object types in OK02
    regards,
    Sam L.

  • PS Issue Business Area and Profit Center - differing in WBS to Network

    Hi
    my team has used COPY NETWORK option and copied a network under WBS in Project Builder (CJ20N), It has observed that org elements of WBS and Network, Acticity are differing.
    Now there are thounds of records of the same, (Org Elements differing in WBS to Network).
    Can you sugest me is there any option to resolve the issue and settlement can be made correctly
    regards
    sri

    Hi
    Once actual postings are made on object (like network or WBS element) you cannot change CO elements (profit center, business area). Those will be disabled. However if no postings happen then you can edit those data.
    If postings already happened and you are not able to change the fields, you can create new network and activity under same WBS element and can transfer the cost (line item wise) through FI (I belive F-02 or FB50 transactions). Please check with your FI counter part once.

  • How to upload and download Long text for WBS, Project, Network

    Hi all,
    I have two isssues.
    1) I am extracting Projects, WBS , Network , Network activity and network activity element from a SAP 4.7 system using bapi's
    BAPI_PROJECTDEF_GETDETAIL
    BAPI_PROJECT_GETINFO
    BAPI_NETWORK_GETINFO
    BAPI_BUS2054_GETDATA
    I am able to get all the details except long text. I want to know how do i extract the long text other than getting it manually by using select_text and Read_text Function module, is there any bapi to achieve this.
    The reason why i am not using Function modules Read_text and Write_text is, object name( TDNAME ) value stored in STXH table for project, wbs and network are the project, wbs and network itself so i dont have any issues with this but the TDname value for activity and activity element are completely different ( Routing number and counter is stored respectively ) which i am not getting as the part of the bapi(BAPI_NETWORK_GETINFO) output.
    2)  I have to upload the extracted Project and it sub object data to ECC 6.0 system , i am able to achieve this by using BAPI's BAPI_PROJECTDET_CREATE, BAPI_PROJECT_MAINTAIN and BAPI_NETWORK_MAINTAIN. I am not able to load the longtext for the same, is there any way to load the long text .
    All help will be greatly appreciated and rewarded.
    Thanks & Regards,
    Rajanidhi Rajasekeran.

    One thread in the correct forum is good enough, no need to double post across ABAP forums.  Thanks.
    Regards,
    Rich Heilman

  • Report: Statistical WBS elements with assets assigned to them - actual cost

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Hi
    There is not a standard report which can cater to your requirements. You need to develop one.
    You can take the refernece from CNS41 report for development. Some of the fields you need are PRPS-XSTAT for statistical WBS and will have to use tables ANLA and ANLC to fetch asset master data.
    Regards

  • No Error when Statistical WBS is closed

    Hi,
    I had created Statistical WBS elements and assigned this to Maintenance orders, System allows me to close the WBS element even when the Orders are open and also allows me to assign & issue materials without checking the budget ( as the WBS is already closed).
    How system allows closure of WBS when this WBS element is assigned to some orders which are still open ? Is there any user exit available to prevent this ?
    thanks in advance.
    Regards
    Vinodh

    Hi Vindoh,
    The reason being your WBS is statistical. Statistical WBS are only meant for statistical postings. You cannot settle them or carry overhead. Just try to maintain settlement rule on statistical WBS and you will get the following message
    Statistical WBS element: No surcharges, settlement etc. N-000298
         Message no. CJ714
    Diagnosis
         A statistical WBS element cannot be settled, nor carry overheads, nor
         can results analysis be carried out for it. Therefore it does not mak
         sense to maintain control parameters for these functions for statisti
         WBS elements.
    System Response
         If you have identified the WBS element as statistical, these control
         parameters will not be displayed in the work breakdown structure.
    The real cost objects are Cctr or Orders. They are only meant for reporing or exercising budgetory controls mainly during Asset procurement.
    Thanks
    Sarang

  • Statistical WBS & WBS with Planning element in summarization

    Can statistical WBS and WBS with planning element are included in summarization?
    Thx

    Hi,
    Summarisation reports output  are same as the equivalent standard reports but they vary only in the hierarchical display of values. The hierarchy of the report depends on the fields you are using to create a summarisation hierarchy.
    Regards,
    Arul.

  • Networks and activities attached to statistical WBS

    Hi,
    I have a statistical WBS which is attached to networks, and activities. It looks like in standard SAP, the networks and activities cannot be made statistical. So the networks and activities carries actual cost (after posting). Is there a way in SAP to make this actual cost in network and activity as statistical? Or do you think that we need to settle the cost somewhere?
    Thanks in advance for your reply.
    Aman

    As I stated before, I also know that networks, and activities cannot be statistical. My question is what would be the solution in this case? Anyway, we've decided to make all objects as statistical WBS elements to resolve the issue. Closing the thread.

  • Statistical WBS elements-Budgeting and Use

    Hi Guys,
    Need some KT from you all regarding Statistical WBS Elements.My queries are
    1.Can a statistical WBS element be budgeted? If yes how are the Budget  distributed to those below.
    2..If a level 2 WBS is marked statistical and it has 3 WBS under it which are Acc asignment element then how is the budget distributed.
    3.can you provide some good example of the use of Statistical WBS element?
    Thanks in Advance
    ssk

    Hi Shourya,
    1. As mentioned above Statistical WBS can be budgeted like any operative project and the budget can further be divided into lower level WBS elements and Availaility Control can be activated on these.
    2. Again as stated above the budget distribution is normal. For ex- If a level 2 WBS is statistical and level 2's underneath that are real WBS.
    3. We can use the Statistical WBS for capital projects. For ex- We can assign a Statistical WBS in Master record of AUC for Availability control of budget for Capital spending. And then when we create a PO with Account Assignment category A with same AUC, budget control (Availability control) is activated through the statistical WBS.
    Someone might ask but why we want to use WBS for budget control why not I/O? It's because it provides more visibility over different departments (divided by structure). And via this process we can see all our PO's on AUC directly from Asset Explorer (AW01N).
    Hope it helps.
    Thanks,
    BS

  • Assigning hours directly to a WBS without Network and activities

    I am setting up a Capital project without the use of activities and Networks. Thus confirmation will be assigned to WBS.
    Can hours confirmations form CATS be assigned directly to the WBS without the use of Activities?
    As I understand you need to set up the Data entry profiles
    Your help would be greatly appreciated
    Thanks
    Johnny

    Hi Johnny,
    Yes, set up a data entry profile which accepts the WBSE as receiver, create a simple HR personnel number & start your postings. It is this simple.
    You can test the same in your dev system. use CAT2 / CATS_APPR_LITE / CATA Tcodes.
    Find the actuals on WBSE in standard reports.
    regards

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

Maybe you are looking for

  • EMAIL-CAN NOT TYPE IN THE BODY OF THE EMAIL

    I can not type on the body of my email through comcast SmartZone.  I am using Internet Explorer 9 and from my comcast home page when I access my email and try and compose an email or reply there is no where to type the body of the email.  When I go t

  • Finder Closes when I try to open Macintosh HD

    I've just noticed this happening tonight. I did perform todays Mac Update but I don't know if they are related. Whenever I try to open "Macintosh HD" (my boot drive) the Finder closes. Does anyone know what the solution could be? I was able to run a

  • Exporting to PNG, need to get rid of "transparent background"

    Hi all, Just trying out Freehand as a solution for creating images for CafePress. I get it all set for 10" X 10", export it to a PNG file and upload it to CafePress. When I try to create a product there, the image is no longer 10" X 10", it is only t

  • Confused a bit

    Hello, I'm taking a PhoneGap Mobile Apps class this semester in college. I'm using Win7, with CS6. We are the ginny-pig class. First time being taught at school. Please explain.We are using Dreamweaver as our IDE? Now I need to download the PhoneGap

  • Sun Directory Server 6.3 Training Workshop coming to USA

    JavaWorkshops.com is going to have 9 public classes over the next few months in the USA. I just wanted to pass this along. I was luck enough to attend their Directory Workshop in London and it was amazing. The instructor is a former Netscape professi