Statistical WBS setting.

Dear All,
We have a WBS which is account assigned and have also some actual postings on It,the project is defined as statistical(tick set at project definition),as we can undo the statistical tick at the WBS level(control tab), the WBS does not have the statistical tick marked, and actual postings have been done.now the statistical tick/CCtr post is greyed out.
                      Is it posible to have the statistical tick reset and set the costcenter.ie to set the WBS as statistical again,
,i tried and reversed the actual, the fields are still greyed out..Is there any solution for the same
Request all to please let us know your recommendations on the scenario above.
Thanks and Regards,
Vinayak.

Hi,
As told by Ahmed, you have to create new statistical WBSE and run the Txn KB15N manual
cost allocation. Enter the old WBSE and new WBSE with cost element and
amount. Old WBSE will be credited and new WBSE will be debited.
I hope it will work in your case.
Regards

Similar Messages

  • Statistical WBS Element - do we need to set as Account Assignment Element?

    Hi,
    I would like to know if I define the WBS element to be statistical (statistical ticked in Control tab) and would want to have posting.  Do I need to set it as account assignment element?  (I noticed system is not allowing me to post if I do not set it as account assignment element).  I want to make sure the actual cost would be be posted to the WBS element as the WBS element should just be statistical in nature.
    Please also confirm if I always need to specify actual cost center posted if the statistical field is ticked PRPS-KOSTL.
    Thanks!

    Yes, so the account assignment should always be ticked if I want to post actual to STATISTICAL WBS Element.  Now I would like to confirm if I always need to specify actual cost center posted if the statistical field is ticked PRPS-KOSTL.
    Also, I understand that if I run CJI3, for statistical Actuals posted, its value type will be 11 - Statistical Actual instead of 4 - Actual.
    Thanks!
    Vivian

  • How to set Statistical wbs element?

    hi,everyone. i'm a green hand in PS.
    i know Statistical wbs element is different from normal wbs element from you guys.
    but i don't know how to set a Statistical wbs element, i mean how to make a normal wbs element  become a Statistical wbs element?
    regards,
    tiger wu

    Yes, if you choose this (in which the Statistical check box is ticked) to create a project, all the WBS will be statistical.
    To create a project in which some of the WBS are statistical and some are not, you don't need to configure this (check Box) in Project profile. You can create a project (CJ20N) and for WBS elements on control tab, you can check this or leave it.
    Hope it helps.
    Arya
    Edited by: Arya Singh on Aug 30, 2008 8:09 PM

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • Change WBS's statistical WBS element

    Hello;
    We use the SAP PS module. I create the WBS and WBS's statistical WBS element (XSTAT) set the true.
    I need the change WBS's statistical WBS element and set the false. But WBS's statistical WBS element read only on the screen.
    How is change WBS's statistical WBS element?
    Thanks.

    Hello
    Set a substitution rule for a particilar proj profile/type, to set the WBS as statistical on saving.
    Sarang

  • PM Budget - Statistical WBS element

    Hello,
    My intention is monitoring the PM budget for a plant by linking every PM order to a statistical WBS element.
    After posting on the PM order and performing costplanning via CJ40 i get a overview in transaction: S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %.
    However. Not every PM order shows up in the report. I thought it had something to do with the moment you assign the WBS element to the PM order but this didn't prove to be a valid statement (before or after actual postings on PM order).
    I can probably find out by extensive testing, but i was wondering if anybody knows if there are specific rules regaring the usage of statistical WBS elements in PM orders? More specificaly, when the assignment will NOT work and the actual costs will not show up in S_ALR_87013543.
    Kind regards,
    Peter Hageman

    Settling was done towards a Costcenter. The WBS element used is a statistical WBS element, that only can be used for reporting purpose. how the settlement rule is set up doesn't matter in this case.
    Issue no longer exists.
    Solution was evident. WBS element in the order was stored on the location tab, and in order to use CJI3, you have to link it on the additional data tab...

  • Change the PYP's statistical WBS element

    Hello;
    We use the SAP PS module. I create the PYP and PYP's statistical WBS element (XSTAT) set the true.
    I need the change PYP's statistical WBS element and set the false.  But PYP's statistical WBS element read only on the screen.
    How is change PYP's statistical WBS element?
    Thanks.

    Thanks

  • Statistical WBS Element in Sales Order

    Hi,
    I tried to post a sales order with a statistical WBS element but the system shows me an error saying I can't open it because the WBS is statistical (Message CJ070).
    Could it be a problem of Controlling Area or Operating Cornern?
    Is there a setting that allow me to open a sales order on statistical WBS element?
    Thanks

    are u posting to some other cost object also. normally they wud have to be posted to a COPA also with the cost element being 11 category.
    the wbs will receive the statistical posting, so there needs to be a real object also.
    see whether the real object is getting derived.
    the system is nt finding the real object and trying to post with the WBS in real, but since its statistical, the error.
    any other calrifications. plz post.
    regards
    anantha

  • Open a Sales Order on statistical WBS element. How?

    Hi,
    I tried to open a sales order on a statistical WBS element but the system shows me an error saying I can't open it because the WBS is statistical.
    Could it be a problem of Controlling Area or Operating Cornern?
    Is there a setting that allow me to open a sales order on statistical WBS element?
    Thanks,
    Diego

    To best of my knowledge, WBS is only a search criteria if u wish u take a doc as ref. in sales order. this ref. will happen only if the previous doc is prepared with ref to WBS. may be at header or item level. but i wonder how will it track the doc if there are multiple WBS in previous doc. u can assign WBS in account assignment tab page.
    I wonder if i have helped u with my answer.

  • PS : Revenue on a statistical WBS

    I would like to be able to show revenue from a SD order shown against a statistical WBS element. Can somebody guide me through how I would need to set this up?
    Thanks, Mark

    Hi Mark,
    As per SAP note 43875 you cant assign SO to statistical WBS. They have provided a work around to do it via statistical internal order which is linked to statistical WBS.
    Regards
    Shrikant

  • Line item report on Statistical WBS element.

    Hi All,
    I need to extract Line report on statistical WBS element. I tried CJI3 and end up with the message No costs, revenues or finances were selected.
    can some one help me on this.
    Thanks and Regards,
    Vinod

    Hi,
    Please check below:
    Table PRPS: Select OBJNR and pass to RPSCO and check if any value exists there. Note down the Value type, Year.
    While in CJI3, please check if any dynamic Selection is active, remove all.
    if mutliple selection shows any exclusions, remove all.
    Posting Data: Remove the values. (Or put from 01.01.1900 to 31.12.9999)
    Select the standard SAP Layout (Starting with 1SAP)
    Value type=11 should be selected by default (Ensure it is checked)
    Hope it helps!
    Thank you and Regards,
    Varshal Kachole

  • Report: Statistical WBS elements with assets assigned to them - actual cost

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Hi
    There is not a standard report which can cater to your requirements. You need to develop one.
    You can take the refernece from CNS41 report for development. Some of the fields you need are PRPS-XSTAT for statistical WBS and will have to use tables ANLA and ANLC to fetch asset master data.
    Regards

  • ACTUAL COSTS:REPORT WITH STATISTICAL WBS AND ASSETS ASSIGNED TO THEM

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
        Assets assigned to each WBS
              Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    An statistical WBS element is an SAP object . Statistical means that you need another object to post the cost or income, let's say,an asset.
    Actual costs are the real postings you have in an object, coming from MM, SD, GL ... (just the contrary as budget or planned values).

  • Asset budgeting through Statistical WBS

    Dear Experts,
    I have configured and assigned Statistical WBS to Asset to carry out active budgeting. To my knowledge I have configured all relevant configuration but when I create PR over this Asset, WBS field is not updated in the PR and therefore no commitment / budget check is performed.
    However, in this same scenario I created internal order and assigned it to WBS. Here then I assigned the Internal Order to the Asset. Budget check in this case runs fine.
    As you may see from figure above B-OA01-001-001 is assigned to an Internal Order where it correctly carry out commitment / budget check when I create PR against Asset with Internal Order as Investment Account Assignment. Also it displays Internal Order number along with Asset number in PR account assignment tab.
    But when I assign WBS directly to an Asset in origin tab of Asset Master no budget check is carried out while creating PR. Also WBS field is also not updated in PR account assignment tab with Asset.
    Note: Budget in both cases is assigned to WBS element.
    Regards,
    Saif

    Salaam Saif!!
    You need to do settings in T code ACSET... You must assign WBS Element in ACSET against APC postings
    Refer below
    Incase you dont find these in dropdown list in ACSET, activate them in ORFA > Integration with the General Ledger> Additional Account Assignment Objects > Activate Account Assignment Objects
    Br. Ajay M

Maybe you are looking for

  • Account assignment to Profit. segment not supported with this G/L account

    Hello Guru,             we have activated the COPA- Costing based. after activation while doing the Shipping Cost calculation thr T.C VI01 system is throughing error message Account assignment to Profit. segment not supported with this G/L account Me

  • MULTIPLE UPLOAD file problem

    Hello, I have a problem with multiple upload file tool. Because my server need, in order to upload files in its folders, to be logged only with ftp user (that is unique). Now, I need that when I upload a file its name will be stored on db table "file

  • All of my contacts and calendar information has disappeared. How do I get it back?

    All of my contacts and calendar information has disappeared. This is not the first time this has happened, and when it happened in the past I just turned on my contacts in the iCloud in "settings." This didn't work this time and I was curious if anyo

  • How to open a copied iPhoto library

    I recently got a new 2014 MacBook Pro. My old MacBook Pro is a 2009. I had a 1TB hard drive in my old MacBook Pro and decided to put that into an external drive to keep with me to use with my new computer. I didn't want to take out or mess with the s

  • File name duplicated

    I cannot buy anything with Itunes. Whenever I try to download anything from my PC (No Wifi available) I receive the message Duplicated file name. I've restored the Ipad mini to default factory settings twice, and the problem persists. Any idea what i