Std Network with Material assignment

Hi,
I am creating Project via Standard WBS and Network. I have also assigned few materials to this Standard NWP. There are few materials assigned to this std NWP all with Base QTY 1000.
So when i add Execution Factor 10 when creating WBS, i expect system to divide Qty of material assigned on Std NWP by 1000 and then multiply by 10, but system is not dividing the Qty by 1000?
Is there some config i need to do so that Base Qty maintained in Std BOM gets divided by the Qty of material that gets assigned to operative WBS being created?
Regards,
Jatinder

Hi,
To my knowledge, the execution factor is applicable only for the quantity at either the WBS or network activity level , not for the requirements it generates.  I may be wrong.

Similar Messages

  • Routing creation with material assignment

    Hello sap gurus,
        I have created routing for semifinished product.Now i want to create routing for finished material but i want to use the same routing as we created for semifinished product by material assignment function in routing.when i go to do like that i am facing one problem.when i go to component assignment for finished material to operation,it shows the component over there which are in Bom of semifinished product,not the component which are in Bom of finished material.so how to do the component assignment if i create the routing by materail assignment function?
            Hope u have understood my problem.

    Hi Jitendra,
    Instead of making the scenario complex, I suggest you to go for separate routing and BOM for the semi-finished and finished product.
    How do you differentiate the routing of both the finished and semi-finished in only one ?
    regards
    Ram Kumar

  • Direct-connect inside network with dynamically assigned IP-addresses

    I have 13+GiB of files to transfer between two computers (one arch and one Win7) and would rather not spend the day moving them ~1GiB at a time via flashdrives.
    I have tried setting up an ad-hoc network on the win7 machine, but wifi-menu fails to connect to it.
    I have tried setting up an ssh server on the arch machine and accessing it via PuTTY on the Win7 machine.
    I have tried setting up an apache server on the arch machine and accessing it via firefox on the Win7 machine.
    I do not have the permissions to statically assign ip addresses on the network, and need to somehow directly connect between these two computers.  Any suggestions?

    5donuts wrote:I've spent the last hour or so trying to set up samba, but I can't figure out how to connect to a Windows shared folder with smbclient, and just cd-ing into the mountpoint doesn't work since access is denied
    Post the exact commands that you are using and the exact error messages that you receive.
    For mounting windows shares I use variations of the following command:
    mount -t cifs //<windows ip address or host name>/<windows share name> /mnt/foo -o nosetuids,uid=<your local user id>,gid=<your local group id>,user=<windows user name>,workgroup=<windows workgroup>
    Have you tried something similar? It should "just work".

  • PO with Account Assignment P and NON Valuated Material

    Hi ,
    As per my undersatnding if I create a PO with Account Assignment "P" , system consumes it immediately and stock doesn;t get updated in any storage location.
    But
    If I use Account Assignment "P" with "NON valuated" stock , system is asking for Slocation at the time of MIGO and also updates Qtys in Storage location , although cost is being booked to consumption account.
    Could u pls help to understand the logic for this ?
    Regards
    Shrey

    Hi,
    PLease read this para from SAP help .. it is useful to undestand your scenarion
    Goods Receipt of Non-Valuated Materials  
    Use
    If the stock of a given material is only managed on a quantity basis, an account assignment must be defined in the purchase order. However, this account assignment does not result in the goods receipt being posted to consumption/usage. Instead, it results in the costs being debited to the account assignment object.
    The goods receipt is posted to the warehouse stock, thus increasing the unrestricted-use stock of the material.
    *It is not possible to post goods receipts of non-valuated materials directly into consumption/usage. You have to post the goods receipt into the warehouse first and then enter a goods issue.*
    Regards
    Krishna

  • Assign Source of supply is not working for contract with material group

    Dear Experts,
    I have searched all the threads and gone through before posting my query. So i would ask moderators to go through the thread properly before rejecting this.
    We have value contracts with respect to a particular material group without material and with item category W in the contract item, Please note that for the materials with this material group, the source determination is not set and source list is also not maintained.
    When we create PR for the material with this contract, and when we click on assign source of supply contracts used to get popped up, but recently from few days, when we click on assign source of supply we are getting an error " no source found for this item ".
    Can anybody help on this.
    Regards

    @ Biju,
    As mentioned earlier, we are not creating PR with reference to contract.
    first we are creating contract with item category W (material group), without material and plant details.
    we create PR with or without material with account assignment K and with the material group in the transaction ME51N, and after inputting all the fields, we click on assign source of supply, it was proposing the existing contracts with respect to material group earlier, but it is not happening for particular material group(it is working for all other material groups)
    Hope it is clear.
    @ Dev Patra,
    we are using DIEN-Service material types and we assign that particular material group to only service material type.
    we have not ticked, source list in the material master, we donot have any source list for the materials under that material group.( please check the note 457110- question number 14.)
    Regards

  • Print of GR without material no and with Account assignement K / Q

    Dear Freinds,
    I want make Print out of Material Document with Material text (without  Material code with account assignement K or Q Project). I made out put setting for WE03, Transaction event type WE Print version 3 and Print Item 1, Material document.
    But i am not able to print in after MIGO. In MIGO Disply, it is showing error as "The system could not create any outputs"
    But I can able to make print out for Material document with material no. i am facing this problem only for text without material no with account assignement like K and Project refernce.
    Please guide me.
    Rgds
    Madhavan

    Hi Madhavan
    Go to MN22 , put WE03 , prsee enter , if u r alrady created any condition record , that will be diplayed , now select one line item , and clik communication . then after going in second screen , u will find box as " LOGICAL DESTINATION " ,  put the logical destination ( LP01 ) and check the tick box " print immediately , and save the condition record ...
    after donig these things ur problem will be solved , as i was also facing same problem , after doing this i got solution

  • Assignment of GL Accounts with Material Groups

    Hi Gurus,
    Please tell me how can we assign GL accounts with material groups and what are the different options in this assignment.
    Please revert asap.
    Thank You

    Hi,
    In IMG settings
    SPRO MMPurchasing --Material master --Entry Aids for Items Without a Material Master
    Here with respect to your material group you will assign the Valuation classes.
    For this valuation classed in OBYC settings you need to assign the G/L accounts for the Transaction key "GBB" or etc which ever you want.
    take a help of FI consultant for this assignment in OBYC
    rgds
    gsc

  • Material No. Mandatory with account assignment category K

    Dear,
    Can i make Material No. Mandatory with account assignment category K
    Please advise
    Rami

    Hi,
    It is not possible to make material number mandatory for Account Assignment Category.
    But you can make Account Assignment mandatory for a material if material is non-valuated (Mat Type - UNBW) or Non-stock (Mat Type - NLAG)

  • BAPI to change material assignment with serial number (IQ02)

    Hi Experts,
    Please let me know the BAPI to change material assignment with serial number in IQ02. I am using BAPI_EQUI_CHANGE, but this does not work. Waiting for Your valuable inputs...
    Thanks in advance,
    Birendra

    Hello Birendra,
    Honestly, I do not have good experience with the BAPI for serialnumber change...
    would suggest to explore function module:
    SERIALNUMBER_LIST_UPDATE
    or
    SERIALNUMBER_LIST_SAVE
    Also run ST05 to trace what kind of data it passed to these function modules by running IQ02!
    Cheers
    Krish

  • PR: Procurement w/o material from vendor with plant assignment not defined

    Hi,
    Getting the error message:  06806 - Procurement w/o material from vendor with plant assignment not defined
    while creating the PR with account assingment (P- project) & without material no. instead entering the short text in the PR.
    this issue (Error message) is getting to only one user.
    question-1:  Is it possible to set the Error messages to the user specific. Because other users are able to create the PR with the above inputs, but the one user is not able to create instead getting the above E- Msg.
    question-2: Is it possible to set the messages to Plant specific instead quesiton -1 or both
    Or else, please let me know how to deactivate the above E-msg to the specific user.
    Please do the needful asap.
    Regards,
    Sapsrin

    Hi,
    As you noticed, note 856962 has changed the system behaviour
    when you are working with procurement w/o material from vendor with
    plant assignment.
    Items without a material master record can only be ordered from vendors
    without a plant assignment.
    This note will stop your users from creating service purchase orders
    for a vendor who has a Plant assigned in the vendor master, issuing
    the error message 06 806.
    you can check the below code:-
    LMEPOF23
      IF ekpo-ematn IS INITIAL AND
          (  aktyp EQ hin OR ekko-reswk NE oekko-reswk  OR      "856962
         (  aktyp EQ hin OR NOT ekko-reswk IS INITIAL OR        "856962
            ekko-bsakz NE oekko-bsakz OR
            gf_extended_check NE space ).
        PERFORM enaco_2(sapfmmex) USING '06' '806'.
    regards,
    Lalita

  • Procurement w/o material from vendor with plant assignment not defined

    While creating  standard Framework Order (FO)   asset  PO  I am getting the below error
    "procurement w/o material from vendor with plant assignment not defined"
    Plz Help
    Regards

    Dear INDRANIL BHATTA ,
         Thanks for your reply and your soluation ,
    Finally , I found Vendor Master assignment to plant so it can't create FO PO .
    ->  XK02 -> selecting "purchasing data" >Extras>Add.Purchasing data.

  • Network Activity with material attachment Blocked

    I have a requirement as below:
    I need to create a network with standard set of activities (internal). But it should not be possible for users to do material attachment to the activities. Is it feasible ?
    Thanks is advance .
    regards
    Muraleedharan.R

    Hi
    You can think of using BADI Workorder_Update which would stop addition of material to network or WBS element. You can hardcode the WBS element number type or network order type.
    Regards
    Srikrishna

  • Table to check WBS-Network-Material assigned to this network

    Hi All,
    Plz advice. What table should i refer ,to check WBS element, network assigned to this WBS, and material assigned to this network.
    Thank you.
    Best Regards,
    Nies

    Hi Nies,
    Tables are as below:
    WBS elements - PRPS
    Network -CAUFV or AUFK - Pass the WBS element as PSPEL
    Material - RESB .
    Pass the reservation number into RESB. Obtain the reservation number from CAUFV table. You can pass WBSE ot Network number also. But RESB being a huge table, it is advisable to pass the key field "Reservation".
    Muraleedharan.R

  • Sales order with material & plan cost

    Hi,
    A sales order with material and assign WBS can display the plan revenue which equal sales revenue. How can I make the material cost also be display as plan cost? This material cost should equal standard price of material master.

    It is not possible to copy material cost from sales order to project. Please activate network cost planning, and assign the same material in the project structure, so system will take the material cost in plan cost.

  • Network - subnetwork hierarchy using std networks.

    I want to create network / subnetwork hierarchy using std. networks.
    How is it done in PS.

    Create standard Network > Create Activities in Standard Network > Assign Milestone in Std NW > Define Milestone functions/Parameters  > Now with the help of this Std network number you can create Sub Network as you wants [In CN21 Transaction code input Std NW number then automatically system will create all subnetwork from that Std Network
    Swapnil Kharul