HI There,
I'm new to SAP BI, can anyone pleas explain me why we need to use Process Chains in a simpler way?
Also it would be great if someone can give me step by step description for creating process chain. I've seen couple of PDF files but they confusing me more then clearing my doubts. Appreciate your time and thanks in advance.
Vandana
Please search the forum before posting a thread
Edited by: Pravender on May 4, 2011 3:57 PM

Hi Vandana,
1.Go to RSPC tcode ->(F5) create ->It will ask for process chain name ->then it will ask for start variant
2.If you have no start variant pre created then create new one (at right side there will be a paper symbol for that ).Every process chain has one and only one start variant that is to set scheduling option etc .When you will create a new one you will go to a screen where you have scheduling option .
3.a) Direct scheduling ->to start execution immediately 
   b) start using meta chain or API ->chains which run at specific time (day ,month etc or after some specific event ). save your settings and go back .click check symbol for final creation of start variant.
4.Now at left screen you  have chain symbol (process types) .when you will click on that you will have all the process lists .
5.You can select process as per your requirement and connect different processes together.Each process is a different event (ex : load DTP ,Infopackage ,ABAP program ,AND ,Interrupt ).You cna do detailed study for that .
6.After adding all processes activate (ctrl+F3) and execute .
7.After that you can check logs (shift+F1) .you can see todays log ,yesterday and today etc .For details of every process execution right click on process and see display variant .
Hope this will be helpful for basic startup.you can further read thoroughly on each process .
Regards,
Jaya

Similar Messages

  • Error while creating a process chain

    Hello BI Gurus,
    I have activated the Business Content Scenario in Plant Maintenance for Infocube 0PM_C08(Measurement Results).
    It provides a datasource -> infocube flow,through DSO with transfer and update rules.(3.X scenario)
    I have two questions -
    1.When I am trying to create a process chain for this scenario for regular delta loads(Loading from the datasource - > DSO - > infocube),
    Start - >Execute InfoPackage->Activate DSO Data ->
    Then  when i insert the Execute Infopackage for the load step from DSO to Infocube in the process chain and check it, it is giving an error saying "InfoPackage ZPAK_D50AJ26831X6L4IIOTZTSXWAE is generated; NOT able to be used as loading variant ".
    I got this infopackage by right clicking on the context menu and going to Additional Functions -> Update 3.x data to Data targets.
    Why am I getting this error and how to resolve it, bcos when i load it manually it is working fine?
    2.If the error is because I did not use a infopack created by me, then how to create a infopack for loading to the infocube from DSO in BI7, because when i select from the Context Menu for creating infopack, it is taking me to the already generated IP ?
    Also instead of using the 3.X mechanisms, if I decide to create a DTP,  will the transformation created with it automatically map all the rules in the "Update Rules" for all fields?
    Waiting for your guidance.
    With Warm Regards,
    Vineeth
    Edited by: VINEETH SUBRAMANIAN.B on Jan 31, 2009 12:11 PM

    Hi,
    Check in  SDN
    Problem with process chain
    Re: Updating Data from ODS to IC using Process chains
    Indirect Spend Analysis
    Thanks
    Reddy

  • I have a problem in creating a Process Chain(PC).

    Hi GURU's
    I have a problem in creating a Process Chain(PC). The PC should run on first 3 business days of the month for six times i,e 6am, 7am,8am, 9am,10am,11am.
    For this i have created 3 PC like BD1, BD2, BD3, and i selected the Factory calender provided workday 1, 2 , 3 and time for three chains.
    Now should i schedule it for 6times in a day.
    I tried creating a new job for one of PC's but i have to change the timings for  every month (this is not the proper solution).
    Please help me.
    Regds
    Lajwanth

    Hi Friend,
    For the days part, you can create a new factory calendar with first 3 business days of each month only as working days.
    Then in the scheduling -> Restrictions; you can mention that Factory Calendar id and select radio button for "Move job to next working day". Schedule the chain as Periodic "Hourly".
    Then for the Time part -> You can insert process type "Decision between multiple alternatives" after the start variant.
    After you insert this process type you can create a formula in it to check for system time. In the if condition check for system time i.e., whether it is between 6 - 11. If only the system time is between 6 AM to 11 AM only then the decision step would turn to green and go to the successor step in the process chain.
    Process chain would be like:
    Start variant -> Decision Step -> Rest of the chain.
    So in short the factory calendar will take care of which days the chain will run and decision step will take care of the timings.
    Regards
    Hemant Khemani

  • Problem in creating a Process Chain

    Hi,
    I am using BI 7.0. I followed the following steps to create a process chain:
    1. Create Start Process
    2. Create Process Variant
    3. And once this is created and saved, I clicked on process types
    4. I dragged and dropped the Execute InfoPackage to the right side
    5. And here, when I click on F4, it says, No Data Selected.
    I have lot of infopackages that are created in my Datawarehousing Workbench.
    But I am unable to view them...please let me know, how do I go about solving them...would definitely assign points for the solution. Thanks in advance.
    Thanks & Regards.

    Hi Ganesh,
       just  go to  your administrative workbench and  select your info package  and copy the technical name... and now go to  your process chain.. now  click on Execute info package process type.. -> in that search help.. you can  choose find option and  give your info package  technical name..(which you copied ) and  press enter.. 
      you can  able to find that info package.. and  clcik on taht.. and press eneter..
    regards
    @jay

  • Create the process chain

    Hi all,
    Can someone tell me if my steps are correct for creating the process chain for uploading from ODS into the cube.
    Here are steps that I did:
    1. created the 'full load' infopackage in the infosource for uploading from the Infosource into the ODS.
    2. right click on ODS and select 'update ODS Data in Data Target' to upload into the cube (select 'init load').
    3. create another 'full load' infopackage in the infosource and use it to create the process chain by pressing the 'process chain maintenance'.
    Thank you.

    Hi Sriram,
    Thank you for resolving my doubt that the 'init load' and 'delta load' cannot be done in the same day.
    Can you also answer me these few qustions?
    1. If I have to create one infosource to assign the datasource 8xxxx,then how can I see it in the infosource list when I click on 'show generated ODS object before I create the infosource? Please explain.
    2.I did click on Setting-> Display generated Object -> Show generated ODS object in RSA1 but I still cannot see the infosource 8xxxxxx in the list. Why?
    3. How can I schedule the delta IP if I don't right click on and select "Update ODS to data targets "? Can you clarifiy it? ( not sure if you mean to select 'generate export datasourc')
    4.in you last sentence, you said: run the delta IP in chain; do you maean use the delta IP to create the process chain?
    Thank you.

  • Creating a Process Chain

    Hello
    Now I have a task like creating a Process Chain for loading data into ODS object.I came to know that directly we can'nt create/delete index for ods objects in Process chain.For that we should write Abap code itseems.
    Can any one help me out in this regard by writing a Abap code for this?
    I need it very badly.
    Regards
    Balaji

    Hi Balaji ,
    Creating a secondary index is very simple. u can create in the change mode of ODS . U have a folder INDEXES ,right click on it and create a new one . System will propose. To see whether your indexes are active , Just go and check in  SE11 ,give the active table name for ODS and in the screen u can find on the top tool bar INDEXES .Click on that and see your active indexes.
    Hope it helps you to some extent.
    Thanks,
    Krish

  • Creating a Process chain for hierarchy under 0Cust_Sales: Attrib? Text? too

    Hi,
    I have a standard hierarchy under 0Cust_Sales which I need to create a process chain for so that this hierarchy will be updated from R3 on a daily basis.
    What is normal to do in this case:
    Create a
    1. Create a process chain to load the Hierarchy under this 0Cust_Sales?
    Or,
    2. Create a process chain to load the Hierarchy and the Attrib?
    Or,
    3. Create a process chain to load the Hierarchy, the Attrib and Text?
    What is the pros and cons of each choice?
    Thanks

    Hi,
    Sorry for the confusion...yes I mean attributes by master data.
    Do you load with master data for 0cust_Sales separately, before loading the Attrib, Text and Hierarchy (in order)?
    attribute text and hieracrhy are the master data for 0cust_sales.
    You load attributes first and then text and then hierarchy.This is not a rule but for the better control and understanding.
    But keep a seperate chain for each along with the same grouping like all the attributes load together in same chain and text load together and hierarchy load together in other chains.
    Since attributes change frequently and you need to reload it everyday therefore keep it separate
    Hierachy may give you tough time with failures in process chains and will not change frequently so keep it separately in another chain.
    You need to use an attribte change run (change run) after any new master data is loaded.
    this is done to reallign the new SID'S created for the new master data object with that of cubes where they are used and affect these changes in the aggregates which are built on them.
    So better put it after the three chains have run or atleast after the master data chain has finished.
    Thanks
    Ajeet

  • How to change process chain in SAP APO, in RSCP tcode.

    HI SAP APO Experts
    I am from SAP ABAP background, I need to change a 'AND' operator in process chain in RSCP tranaaction in SAP APO.
    I dont have any idea how to change process chain.
    Could you please help me how to change process chain in SAP APO in RSCP tcode.
    Appreciate your help or comments.
    Sandeep..

    Hi Sandeep,
    The t-code RSCP does not exist in SAP APO.  The correct t-code is RSPC. 
    Step 1:- In RSPC t-code, select the process chain which you need to change. 
    Step 2:- Double click on it. 
    Step 3:- It will display the various programmes attached to the process chain.  Go to change mode by clicking on the change indicator (Control + F9)
    Step 4:- Select the programme area where you need to do the correction or change.  Double click on it.
    Step 5:- It will take you to the programme and its selection contents.  Make the relevant changes.  You can directly carry out the change in se38 also if there is variant kind of changes for that particular programme.
    Step 6:- Once the changes are done, save the changes and press F3 button which will take you to the home page of the process chain
    Step 7:- Save again so that the change in the programme alongwith the process chain will get saved.
    Regards
    R. Senthil Mareeswaran.

  • HOW TO STOP A SCHEDULING A PROCESS CHAIN IN SAP BPC

    Hello Expert,
    Can Any 1 tell me  how to stop a scheduling of a process chain in sap bpc ??

    Hi Neeraj,
    Your question is not clear.
    If you are asking - How to delete a schedule which runs a process chain/DM package from EPM, then please go to Data Manager -> click View Status arrow -> select view schedule status -> select the schedule, right click and choose delete schedule.
    Neha

  • Error in Step Copy Plan version in Process Chain

    Hi all,
    We have  step in Process Chain called 'Copy Plan version'.This stet is getting failed quite frequently. I just repeat it and the error is getting solved. I just wanted to know that is there any permanent solution for that. We cant afford to getting it failed that frequently.
    I dont have any idea about this step. Can you please provide me information about this step and a possible remedy aw well.
    The error messaage is :
    Selection accesses data that is currently locked; user     
    Job cancelled after system exception ERROR_MESSAGE.
    Please suggest.
    Regards
    sunny

    This is due to "Selection accesses data that is currently locked; user" , there is another process from another process chain which locked the object at the same time frame , so due to that this step is failing
    you can increase waittime 30mins(example)before this Step Copy Plan version executes in the process chain.
    OR, change the schedule time for this process chain

  • Steps to added RDA in Process chain

    Hi Experts,
    I have created DSO for RDA using DAEMON im able to get records to active table.
    Now i wabt to load data into infocube by using Process Chain.
    How to added this DAEMON in Process Chian.
    Regards,
    Venu Gopal.K

    Hi ,
    Please go through below link
    /thread/297461 [original link is broken]
    Hope this will help u
    Thanks

  • Help me to Create this Process Chain

    Hi Gurus,
    We have 3 Process chains,
    1) Region 1
    2) Region 2
    3) Region 3
    These three process chains were start at differt times and end time will depends upon the load of data. Now i want to do some manual calculations after the successful execution of this chains. So i have written three ABAP programs to do that calculations for 3 chains.
    My scenerio is to create a new chain only so I have created a new chain with Start variant -> Decision variant -> 3 Program variants (For 3 chains)
    Now i want to write the condition in decision variant to attach the respective program variants below it. ie,
    Start -> Decision (Condition for successful execution of Chain Region 1) -> Program Variant 1
                 Decision (Condition for successful execution of Chain Region 2) -> Program Variant 2
                 Decision (Condition for successful execution of Chain Region 3) -> Program Variant 3
    So i don know what exact logic to write in Decision variant...Please help me here...
    Thanks & Regards,
    Balaji.S
    Edited by: sbalajigupta85 on Aug 26, 2010 7:47 AM

    HAI ,
    A process chain is a sequence of processes that are scheduled to wait in the background for an event. Some of these processes trigger a separate event that can, in turn, start other processes. It looks similar to a flow chart. You define the list of Infopackages / DTPs that is needed to load the data, say delta or Full load. Then you schedule the Process chain as hourly, daily, monthly, etc, depending on the requirement 
    process chains for which info providers ?? i mean to say... for cube or? DSO?
    ok now below i explained for DSO... try it out it will work.. 100%
    Step 1: Go to RSPC transaction. Click on Create. Give Process chain name and Description.  
    Step 2:  Give the Start process name and description and click on Enter  
    Note: Each process chain should start with a Start Process  
    Step 3: The next screen will show the Scheduling options.  
    There are two options:
    Direct Scheduling:
    Start Using Meta Chain or API  
    In my example I have chosen Direct Scheduling as I am processing only one chain i.e DSO. Click on u201CChange Selectionsu201D  
    In the below screen shot, you can give the scheduling details i.e the Immediate, Date& time etc. and click on SAVE  
    The Screen shot below indicates that we have started the process. 
    Step 4:
    Click on the icon process types as shown in the below figure. You will get a list of options.
    In my example I am scheduling for DSO. To process we need to have InfoPackage, DTPu2019s for the corresponding DSO
    Open the tree Load Process and Post Processing, We need to drag and drop u201CExecute InfoPackageu201D  
    Step 5: Once you drag and drop the u201CExecute infopackageu201D we get the below Popup. We need to keyin the Infopackage name. To do this click on F4 and chose your Infopackage and click on ENTER
    Step 6: Save + Activate and Execute the Process.

  • Creating a Process Chain for a Broadcasting Precalc

    Friends -
    Can a process chain be created for a Broadcasting Precalc?  If yes, does anyone have any steps on how to do this?
    Thanks!

    Please disregard. I figured this out.

  • Problem in creating the Process Chain

    hi Guru's
    my client want to run a process chain for first 3 business days of the month for every hour.
    then i created a 3 Process chains say ex. A B C.
    Now i use the conditions for Process Chain A  is Date and Time
    i have given the date and time,
    Selected Periodic Job Option
    -> From Period Values button selected other period and given 1 for every month, 1 for every hour,
    -> Selected the Restrictions Button and given the factory calender and selected " Job not to run on holiday and sundays "
    therefore the chain can run on every month for whole day based on Factory calender.
    the same options used for PC's B & C
    The problem is the process Chain A has ran only once it didnt ran for every hour.
    In released job i can see the job frequency for every month and every hour...
    Request you gurus to suggest.
    Regards,
    Lajvanth
    Edited by: Gali Kling Schneider on Dec 16, 2010 1:28 PM

    Go through the below link which can give u some idea.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/business-intelligence/s-u/triggering%20%20the%20process%20chains%20at%20particular%20date%20using%20events.pdf

  • Instance not created in process chain

    Hi,
    we running a process chain in that 1 local chain failing due to instance not creating.
    in job log it was showing "perivous job not at finished" But pervious chain completed.
    it is the meta chain.
    how to trigger next chain?
    thnaks

    thnak

Maybe you are looking for

  • How to close a form within script

    Hello, I'm using Adobe LiveCycle Designer v 8.2 to develop an Order form. I'm fairly new to developing in LiveCycle, and would like to ask the following question that I couldn't find an answer to elsewhere. I'd like to know if it is possible to close

  • Photo Management for old (import) & new pictures

    Below is a proposal for organising my photo management system. I'm a hobbiest photographer with over 30 years of pictures to file. I have read extensively, including this forum and sort best practice to developed a plan to do achieve an organised sca

  • Message transmission medium

    Hello Friends, Can you please tell me the procedure to achieve this. How can you determine the message transmission medium while the requirement subroutine (Requirements Output Control T-Code VOFM ) is running. FORM KOBED_601. get message transmissio

  • Pm-utils-1.4.0-1: aggressive hard drive power saving (often spin-up)

    [sorry, misplaced post. this issue is for package from extra repo] Hi all, after upgrading from pm-utils-1.3.0-2 to pm-utils-1.4.0-1 I noticed that hard drive on my laptop is stopped and spinned up again too often. The reason for this is script intro

  • Cairngorm value object doesn't match cfc object?

    I have built a cfc vo class and flex vo class PersonVO.as package com.abc.CESF.Bursary.vo import com.adobe.cairngorm.vo.IValueObject; [RemoteClass(alias="Bursary.cfcs.PersonVO")] public class PersonVO implements IValueObject public var firstname:Stri