Step wise config data for schedule line agreements

DEar All,
I need urgently one the foolowing doc:
step wise config data for schedule line agreements.
thanks
regards,
s KUMAR

Hi,
1) Scheduling Agreement is a long term agreement and PO is normally a one-off. When you have long term relation with supplier you will go with SA.
2) SA need not have delivery schedules at the time of ordering. It's like a contract with vendor for all basic prices, quantities & terms. You will release schedules as & when required. This method is very popular with manufacturing ind (e.g. automotive) where they negotiate prices but delivery schedules are given periodically based on their actual production/sales demands.
3) In a PO, you must give schedules in PO itself.
4) If you know contract & release order (or call-off) concept, then SA is like contract and SA schedule is like release order. PO is release order.
or
While using schedule agreement, you will create delivery schedule, when ever you require materials.
Firm and trade off zone in delivery schedule details will be forwarded to your vendor. you can create daily , weekly , monthly schedule lines
Example : if you have created a schedule agreement for product " A " for quantity 1000, and you require material of 100 nos in the first month, you can create schedule line for this 100 only and this will be transmitted to vendor( if you are using LPA you have to release schedule line). when ever you require further qty based on your requirement you will create another delivery schedule line, then it will be transmited to vendor.
In case of PO if you are ordering 1000 qty , you need to specify the delivery date in Purchase order it self, and all the dates are immediately transmited to vendor along with Purchase order.
For configuration steps please follow
http://help.sap.com/saphelp_47x200/helpdata/en/93/7439fb546011d1a7020000e829fd11/frameset.htm
Hope this will help.
Thanks,
Raja

Similar Messages

  • How to get GR posting date for schedule line of scheduling agreement?

    I had hard time to tie the GR date to schedule lines. I need this information to generate vendor performance report. However, the GR date is tied to scheduling agreement item level only. One item line can have multiple schedule lines. Is there a way to link the GR date to actual schedule line? Thanks in advance!

    Hi,
    There will be icon called PO history in the over view screen of SA.Select the item and press it.May be this will be some what useful to you.
    Regards,

  • Creation date for schedule line

    Hi All,
    I have a scheduling agreement. MRP is generating the schedule lines properly. I want to know any table or any other way by which I can check the creation date for those MRP generated schedule lines.
    Regards,
    MHP.

    Dear Manish,
    As per my understanding from your question, you can use 'MD04-Stock/Requirement List' transaction for checking all the dates for planned order generated from MRP run.
    Regards,
    Hiren Ramani

  • How to back date for schedule line date of Consignment Fill-Up

    Hi,
    There are available stock for the material used. In VA01 of order type KB - Consignment Fill-up, I put in a backdated schedule line date (example: 09.09.2008). However, the system automatically proposed a new schedule line date of today's date (example: 13.10.2008).
    How can I remain the backdated date with confirmed qty instead of today's date?
    Thanks.

    Hi Wooi Ling
    when system is not able to confirm the schedule lines, the system would give a proposal date on which the requirement can be met.
    in this case ,you can do one thing , you can set the indicator " Fix date and quantity " in the item schedule line. this would fix the date and the quantity for delivery and the schedules lines.
    this would also mean the customer accepts the delivery and quantity confirmed by the system, The system then passes on MRP requirements so that the confirmed date and quantity can be met.
    hope this helps
    thanks
    akasha

  • BAPI_SAG_CREATE - time indepenedent condition  for schdule line agreement

    Hi all,
    i have nade a BAPI -BAPI_SAG_CREATE for schedule line agreement. it is running okay for time dependent condition.
    but it is giving error " schedule line fortime independent condition is not asllowed"when i am running for the same bapi for time independent condition whereas it is our requiirement.
    kindly help.
    Regards,
    Santosh

    Hello Santosh,
    I think you have no chance, this time you found a missing funcionality, BAPI_SAG_CHANGE (and BAPI_SAG_CREATE) can only treat scheduling  agreements with time-dependent conditions. Document conditions are not  supported. Therefore, this kind of scheduling agreements cannot be           
    processed and you receive error message MEOUT019.   
    Regards,
    Mauro

  • BAPI for Maintain Scheduling line agreement

    Dear ABAPer,
    I am using SAP version ECC 5.0. I want to develop Change Scheduling line agreement  enhancement.
    my requirement is, any BAPI is there for the same.
    if you have any idea, please help me.
    thanx.
    with best regards,
    Velmurugan.S

    Hi ,
          Hope it helps.
    Maintenance of Scheduling Agreement Delivery Schedule Lines
    BAPI_SCHEDULE_MAINTAIN
    The BAPI_SCHEDULE_MAINTAIN is used to create or change scheduling agreement delivery schedule lines.
    The parameter PURCHASEDOCUMENT and the scheduling (delivery schedule line) data in POSCHEDULE and POSCHEDULEX are to be passed on to the interface. These three parameters are defined as mandatory.
    IMPORT
    Extensionin
    ScComponentX
    ScheduleX
    TechnicalData
    TestRun
    EXPORT
    ExpHeader
    Extensionout
    return
    Changing
    ScComponent
    Schedule
    CALL FUNCTION 'BAPI_SCHEDULE_MAINTAIN'
      EXPORTING
        PURCHASINGDOCUMENT       =
    "   TESTRUN                  =
    "   TECHNICAL_DATA           =
    " IMPORTING
    "   EXP_HEADER               =
      TABLES
        SCHEDULE                 =
        SCHEDULEX                =
    "   SC_COMPONENT             =
    "   SC_COMPONENTX            =
    "   EXTENSIONIN              =
    "   EXTENSIONOUT             =
    "   RETURN                   =
    Thanks,
    Rajesh

  • GRs created for schedule line of future date

    While making Goods Receipts using MIGO transaction, we are seeing tha GRs can be done for scheduling agreements having schedule line of future dates. Is there some way of restricting the GR upto to current date only. Meaning suppose if I have the following schedule lines:
    category of delivery date         delivery-date           schedule quantity
    M                                               01.2010                   100
    M                                               02.2010                    200
    M                                               03.2010                    150
    Currently the system is allowing to do GRs of quantity = 450 (100 + 200 + 150) in the month of February, 2010.
    But I want that while doing a GR in February, 2010 the system should allow to do GR of quantity 300 only (100 + 200). Please let me know how we can do so in the system.
    Regards,
    Pratima.

    Dear Veer,
    Your answer has helped in the MIGO transaction. Please let me know if something similar is possible for inbound deliveries also. Meaning like in MIGO transaction, I should not be able to make inbound deliveries (in xns VL31N) for schedule lines of future dates / months.
    Regards,
    Pratima.

  • Inbound Delivery for Schedule Lines of future date

    We have a requirement where in we want to disallow inbound creation for scheduling agreements for schedule lines of the future. For example if we have the following schedule line for a scheduling agreement
           Month        Quantity
    M    01.2010     100
    M    02.2010     200
    M    03.2010     150
    Currently the system is allowing inbound delivery creation of quantity = 450 (100 + 200 + 150) in the month of February, 2010.
    But I want that the system should allow inbound delivery creation in February, 2010 for quantity 300 only (100 + 200). Please let me know how we can do so in the system.
    Regards,
    Pratima.

    Hi Rami ,
    Maintain different schedule lines in PO - Item Details - Delviery Schedule tab.
    This would allow only those qty that is due on that date when creating inbound delivery.
    Regards
    Ramesh Ch

  • Need BAPI Name for updation of Subcontracting scheduling line agreement

    Hi All,
            Can anybody please tell me BAPI Name for updation of Subcontracting scheduling line agreement from EKET table?
    Note: BAPI_PO_CHANGE is not useful for me.
    Thanks and Regards,
    Atul.

    Hi Muralidhara,
    Can you please give some more details for this BAPI..
    I tried using it , but getting an error "No instance of object type PurchSchedAgreement has been created. External reference:"
    and "Enter G/L Account" (Infact I did specify G/L account in account assignment table)
    with regards,
    Kirti

  • Open quantity for scheduling lines

    Hi,
    I need calculate open quantity from scheduling lines(based on date) for Scheduling Agreement (similar like VL10I works). I noticed that open quantity is not maintain in VBEP. So could you help me?
    BR,
    Z

    Hi,
    For calculating open quantity for scheduling lines ,u need to query the sales order number in table VBUK and check the field GBSTK , it will be an open order .
    You can look in table VBAKUK for this .
    This is Join of VBAK and VBUK entries. You can eliminate a join if you fetch it from VbakUk
    Now once it is confirmed that it is open then fetch the entries from VBAP.
    Hope it helps you.
    Thanks,
    Sarita Singh

  • Can anyone explain me the procedure and initial settings to do sto for schedule lines?

    can anyone explain me the procedure and initial settings to do sto for schedule lines?
    Create a STO with new doc type for material M1 to ship from plant 1 to plant 2 with qty as 100. On pressing enter you should be able to see schedule lines in delivery schedule tab. In schedule line you should see the Material availability date, GI date, loading date etc.
    can anyone give the answer for this question..

    Hi Megha,
    Please find below links for Config STO with schedule lines.
    http://dhavalatsap.blogspot.sg/p/configuration-of-plant-to-plant-sto.html
    https://scn.sap.com/thread/1260375
    Thanks,
    Bala.

  • Help on Configuration of Schedule Line agreement

    Hi friends
    please let  me to know the configuration steps of Schedule Line agreement
    Thanks for ur help
    Regards
    Krishna

    HI,
    Refer
    http://help.sap.com/saphelp_47x200/helpdata/en/75/ee1fa755c811d189900000e8322d00/frameset.htm
    It is the same as that of the value contracts for Schedulling agreement as well.
    Thanks & Regards,
    Kiran

  • Issue with delivery date in schedule line ??

    Dear Members,
    I have created a sales order on 05/18/2009.I am getting delv date on schedule line as 06/12/2009, due to this problem, I am unable to create a delv. What should I do now ?/
    I have checked the availbility of material and material is available on 05/18/2009.
    Also Checked on config of order type in V0V8 T-code, and lead time in not maintained.
    please let me know, where should I check.
    Thank you.
    Madhu

    hello, friend.
    on the schedule lines tab, try changing the date to the present and see if delivery can be confirmed.  another way is to run the "check item availability" functionality in the sales order.
    on the document header, check what date is being proposed for "Requested Delivery Date".  this date could be proposed based on settings for the document type.  but since you indicated that there was no lead time maintained, you will have to check lead times in:
    1.  the shipping point (deliveries processing, picking, packing, etc.)
    2.  in the MRP views of the material master
    3.  transportation lead times (routes, etc.)
    4.  if externally procured, purchasing lead times
    hope this helped you.
    regards.

  • How to compare delivery date in schedule lines and PGI in outbound delivery

    Hi,
    I want to create a report to monitor and compare different dates in sales and delivery process.
    One of my key figure is the comparison between date confirmed to the customer, that I can find in the schedule line of the sales order, and the actual goods issue date from the outbound delivery.
    But I can't succeed in making the link between delivery and schedule lines, means between LIKP and VBEP.
    Would you have any idea?
    Thank you.

    It seems there's no exact (table) connection / link between delivery item and schedule line item.
    Those who were searching for this thing (link / connection between delivery item and schedule line) were recommended to use FM "RV_SCHEDULE_CHECK_DELIVERIES".
    This FM calculates the delivered quantity for each schedule line, so it makes link between the delivery item and schedule lines - however if you check the code it's quite sophisticated...
    (if you put a breakpoint in the FM and display a SO in VA03, you can check how the parameters have to be populated with data).
    Schedule Line and Delivery Link
    Edited by: Csaba Szommer on Aug 5, 2011 12:03 AM

  • Release strategy for Schedule lines in SD

    Hello All
    Can we create a release strategy for Schedule Lines in Scheduling Agreement? If Yes How?
    I have already maintained a release strategy for Item Level... which I want to put it for Schedule line as well....
    Thanks in advance.

    Hello,
    I think you are in the wrong forum. Please choose the right forum category and post it there.
    Matthias