Steps for discrete manufacturing  in production planning module

hi,
    my all dear sir, i am consused about the steps of discrete manufacturing in pp module. so please give me solution
      thank you sir

Hi
MM01 - make to stock with strategy 10 or 40
CS01-BOM craetion
CR01-workcentre creation
CA01-Routing cretion
MD61-Create PIR
MD04-check the requiremnt
MD02-Run theMRP against the FG
MD04 -check the planned order for the PIR
MD04-convert planned order to Production order and save the order
or you can create directly without PIR CO01
co02 -chnage order(release)
MB1A -gooda issue
CO11N-confirmation of order
MIGO -GR of order
CO02 -Teco(technical completion
CO03 -dispaly of order
-ashok

Similar Messages

  • How to implement the WIP in production planning module?

    Hi Gurus,
    Good afternoon! We are planning to Implement the WIP in Production Planning Module. Current set-up, we create production order and confirmed for all process in production transaction especially the consumption of raw materials and Goods receipt of FG from one Production order. We have two activity in production transaction. But we would like to separate the process per activity. Can we ask on how to separate the transaction or implementing the WIP? To create production order as semi-finished goods and one production order for final finished goods. We would like to ask for your expertise and advise on how to implement WIP in SAP PP that there is no duplication of manufacturing FG cost.
    We would like also to know all FI entries per transaction to make sure there is no double entries in manufacturing cost of FG.
    thank you,
    weldin angelo

    Hello  Angelo,
    Please refer this thread for your requirement
    Wip calculation in production Order
    WIP Settlement
    I hope this information helpful to you
    Regards
    Umesh Mali

  • SAP Best Practice for Discrete Manufacturing

    Hi colleagues,
    We are installing SAP BP for Discrete Manufacturing based on ECC 6.00. We have already installed the Baseline Layer 0. The problem we face now is that some of the building blocks required for Layer1 activation are not present amongst the ones already installed.
    How does one get these missing building blocks?
    Thank you.

    Dear,
    For detail information please refer the OSS notes,
    1040010 and 1223033 - SAP Best Practices for Discrete Manufacturing V1.603 CN
    Ensure that exactly the support package levels mentioned in the Quick Guide are implemented (not below and NOT HIGHER).
    Regards,
    R.rahmankar

  • The SAP Best Practices for Discrete Manufacturing V1.603

    Hai All,
    We are implementing SAP A1 for manufacturing company, so We selected SAP Best Practices for Discrete Manufacturing V1.603. Hear my question is after ecc 6.0 installation what level i need to update  the patches, because if i update all patches(up to date) it will give problem while building block updating.
    Thanks in Advance...
    Sushma Tatineni

    Dear,
    For detail information please refer the OSS notes,
    1040010 and 1223033 - SAP Best Practices for Discrete Manufacturing V1.603 CN
    Ensure that exactly the support package levels mentioned in the Quick Guide are implemented (not below and NOT HIGHER).
    Regards,
    R.rahmankar

  • SAP Best Practices for Discrete Manufacturing

    Hai All,
    We are implementing SAP A1 for manufacturing company, so We selected SAP Best Practices for Discrete Manufacturing V1.603. Hear my question is after ecc 6.0 installation what level i need to update the patches, because if i update all patches(up to date) it will give problem while building block updating.
    Thanks in Advance...
    Sushma Tatineni

    Dear,
    For detail information please refer the OSS notes,
    1040010 and 1223033 - SAP Best Practices for Discrete Manufacturing V1.603 CN
    Ensure that exactly the support package levels mentioned in the Quick Guide are implemented (not below and NOT HIGHER).
    Regards,
    R.rahmankar

  • Steps for creating a new BAPI function module

    Hello experts,
    Can any one send me steps for creating a new BAPI function module , I got a requirement to do like this,but I dont have any clue about how to create.
    Please help !!!

    BAPI stands for Business Application Programming Interface.
    There are 5 different steps in BAPI.
    - Create BAPI Structure  
    - Create BAPI Function Module or API Method.  
    - Create BAPI object  
    - Release BAPI Function Module.  
    - Release BAPI object.
    Step1. Creating BAPI Structure:  
    - Go to <SE11>. 
    - Select Data Type & Enter a name. 
    - Click on Create.
    - Note: Always BAPI should be in a development class with request number (Not Local Object).
    - Select Structure & hit ENTER.
    - Enter the fields from your database. Make sure that the first field is the Primary Key Field.
    - Then SAVE & ACTIVATE.
    Step 2. Creating BAPI module: 
    - Enter TR.CODE <SE37>.
    - Before entering any thing, from the present screen that you are in, select the menu
       Goto -> Function Groups -> Create Group.
       Enter a name (Note: This name Must start with ZBAPI)
       Let this screen be as it is and open another window and there, enter TR.CODE <SE80).
       Click on the Third ICON that says Inactive Objects. 
       Select the group that you just created and click on Activate. 
       Notice that the group you created will disappear from the list of inactive objects.
    - Go back to <SE37> screen and enter a name and hit <ENTER>. Then enter the group name that you just created and activated.
    NOTE: When you release a function module the respective group will be attached to that particular application. It cannot be used for any other application. NEVER include an already existing group that is attached to another module.
    Now click on the first Tab that says [ATTRIBUTES] and select the radio button that says remote-enabled module since we will be accessing this from any external system.
    Then click on the second tab that says [IMPORT].
    Enter a PARAMETER NAME, TYPE and the structure you created in the first step. Also select the check box ‘Pa’. All remotely enabled functional modules MUST be Pa enabled, where Pa means ‘Passed by Value’ and if you don’t select ‘Pa’, then that means it will be passed by reference..
    Then click on tab that says [EXPORT].
    Enter the following as is in the first three fields 
      RETURN        TYPE        BAPIRETURN (These 3 field values are always same)
      Here also select ‘Pa’ meaning Pass by value.
    Note: BAPIRETURN contains structure with message fields.
    Then SAVE and ACTIVATE.
    Step 3. Creating BAPI object: 
    - Enter Tr.Code <SWO1>   (Note. It is letter ‘O’ and not Zero).
    - Enter a name and then click on create. Enter details. 
    NOTE: Make sure that that Object Type and Program name are SAME.   
    - Enter Application ‘M’, if you are using standard table Mara. If you are using your own database then select ‘Z’ at the bottom. 
    - Then hit <ENTER>. 
    - Now we have to add ‘Methods’. High light METHODS and then select the following from the menu: 
    Goto Utilities -> API Methods -> Add Methods.
    - Enter function Module name and hit <ENTER>.
    - Select the second FORWARD ARROW button (>)to go to next step. 
    - Check if every thing looks ok and again click on FORWARD ARROW button (>).
    - Then select ‘YES’ and click on <SAVE>.
    -  Now on a different screen goto TR.CODE <SE37>.  Enter Function Module name and select from the top menu  Function Module -> Release -> Release.
    - Goback to TR.CODE <SWO1>.
    Here select the menu combination shown below in the same order.
    - Edit -> Change Release Status -> Object Type Component -> To Implemented.
    - Edit -> Change Release Status -> Object Type Component -> To Released.
    - Edit -> Change Release Status -> Object Type -> To Implemented.
    - Edit -> Change Release Status -> Object Type -> To Released.
    - Then click on <SAVE>.
    - Then click on Generate Button (4th button from left hand side looks like spinning wheel).
    - Then Click on the button that says ‘PROGRAM’ to see the source code.
    To check if this is present in work flow goto TR.CODE <BAPI>. 
    Here it shows business object repository.
    - First click on the middle button and then select “ALL” and hit ENTER.
    - Goto tab [ALPHABETICAL] and look for the object that you created. This shows that the BAPI object has been created successfully.
    regards,
    aswin

  • Scenario for Discrete Manufacturing..

    Dear All,
    Our client imports goods and then packages them at their site into different packages and boxes. After that those products are dispatched. The client wants to keep an eye on the status of packaging and for that they require a Manufacturing module.
    Can Process Manufacturing be implemented for this scenario or Discreet Manufacturing will be a better option?

    Hi,
    It basically boils down to how you track the status of your work orders, generally if you want to segregate by order then Discrete manufacturing is better, if you want to segregate by operational metrics in your plant irrespective of the number of goods you import then flow manufacturing is better.
    Thanks,
    karthik

  • X Steps in Discreet manufacturing in Production order scenario

    Hi
    XSTEPS guru's
    As i understand till now XSTEPS is posible in PP-PI however in one thread i saw it is mentioned its application for  Discreet manufactring too.I will like to know is it really possible to apply XSTPES in discreet production order scenarion and if yes how it can be achieved.
    Previous thread on this :
    Re: X-Steps for Discrete

    1. About the Compactability i Know you will have to check / wait for reply,
    2  benefits. -
    a. Generally it depends on how much functionality is required,if you arelooking for simple instructions then you need go for them, keep it simple, Dont use the funcationality just as it is available,
    b. Because these are new funcitnalities and you need to be clear enough on consulting what to give and what not to give.
    c.PP-PI vs Discrete has its own advantages over each one of them , Validating this is not basedon the Xsteps, it is one of the functionality added to make life simpler.
    3. Reg the customisation:
    IN SPRO>PROCESSINDUSTRIES>PROCESMANGEMENGE
    below this you will see the Xteps.
    4. Please look at this blog http://websha.de/xstepcafe/ the author has lot of info on that .
    Reg
    Dsk
    Edited by: Dsk on Jul 29, 2010 11:13 AM

  • Product costing without production planning module

    Is there any way to work with product costing module without production planning for service sector.

    Hello
    You may use the product costing without quantity structure. This is useful if you do not have PP module but have materials and you need to calculate the standard cost of the materials.
    In case you do not have materials and only have kinds of services then these can be created as activities for a cost center like a FICO consulting activity for SAP cost center. You may then calculate a price per hour of the activity and may charge it to the service order/ internal order.
    Sangram

  • Reg.,consumption details for Discrete manufacturing

    Dear Guru,
    can any body help me in this regard to FS for dicrete manufacturing.
    Am taking MSEG table but here unable to see particular order consumption/for which material consumed for which product.am putting 261 movement for the particular plant nd values also flowing.plz suggest me
    Reagrds

    Hi,
    Check table: RESB.
    Regards,
    Alok Tiwari

  • What are the front to backend steps for redeploying a live EPMA Planning ap

    Hello All,
    Can anyone outline considerations/steps for redeploying an EPMA Planning application in a live environment? Do users have to be logged off of the system? Does the Planning app have to be put into Administration mode? Does the Planning Essbase DB have to be put into standby mode or users logged out of it first? Do I have to restart Planning afterward? Thank you in advance for any information that you can provide.

    Hello John,
    Thank you very much for your quick response. We currently try to do this after hours but it seems invariably that there were some users still in or had some processes running that seemingly hang when we try to redeploy EPMA/Planning (the users are not able to log back in after the EPMA Planning re-deployment). Is there a sure fire way to ensure that users are out of the system before redeploying so that this doesn't happen? Please advise, thank you sir.
    Edited by: 859885 on May 18, 2011 2:51 PM

  • Basic functionality and few steps for how to integrate with PS module

    HI Experts,
    I am very new to C-projects .
    So cn anybody put some light on what c-project is and how cn we integrate wth PS module step by step.
    Thanks In adv.
    Regards
    Ashis

    Hi,
    Please find some details about cProject below.
    Collaboration Projects (cProjects):
    SAP offers SAP Collaborative Project Management (cProjects). cProjects covers the entire range of project management activities in development and consultancy projects, from planning to implementation to project completion.
    Value Proposition
    cProjects supports organizations to grow their project management excellence by
    a) providing solid standalone project management core support
    b) offering a wide range of integration options
    Key Benefits Include:
    a) As single source of truth cProjects provides company-wide transparency of all projects.
    b) Complete functional support for project planning, execution and controlling
    c) Project structuring and scheduling
    d) Clear responsibilities based on project roles
    e) Well-defined handovers through approval protected phase gates
    f)  Effective Collaboration for all project stakeholders through web interface
    g) Effective use of resources through cProjects enterprise resource planning and tracking.
    h) Reduce project time to market and costs by implementing project templates
    i)  Timely and consistent status information based on dashboards, evaluations and alerts
    j)  Rapid access to all project related information in the entire SAP Business Suite.
    k) Governance through comprehensive authorizations
    l)  Tracking project history through status reports and versions
    Integration by Evolution
    cProjects supports organizations in evolving their project management maturity by constantly adding enterprise integration capabilities to their project management solutions. Many customers start with cProjects by deploying it in a stand-alone scenario with limited integration. cProjects offers a wide range of integration scenarios to increase project reach and effectiveness. A cProjects implementation growths with our customers.
    Integration Functions Include:
    1)Cross project reporting with SAP NetWeaver Business Intelligence
    2)Detailed Project Costing with SAP ERP Financials and Project System
    3)Enterprise Resource Management based on SAP ERP Human Capital Management
    4)Business object integration to the SAP Business Suite for example materials or sales orders
    5)Portfolio integration including strategic resource management with SAP xApp Resource and Portfolio Management
    6)Partner collaboration with SAP Collaboration Folders
    7)Enterprise Portal Deployment and Collaboration Room integration
    8)Confirmation of time and travel costs with SAP ERP Time and Travel
    9)SAP CRM opportunity management integration
    10)Powerful document management with SAP Document Management and SAP easyDMS.
    11)Early Project Costing with SAP ERP Easy Cost Planning
    Positioning
    Since cProjects birth as development project management for the automotive industry it has emerged to a flexible project management solution for all industries and focused on various project types, including
    new product development and introduction,consulting projects and IT projects.
    SAP cProjects and SAP Project System (SAP PS) are both part of SAP's offering for Project Management. Customers can use them independently or integrated depending on project requirements. If both are used integrated for the same projects cProjects manages project schedule and resources while cost and budget are managed in SAP PS.
    cProject integration with PS module
    With cProjects 4.0 multilevel controlling is possible. For the project type multilevel controlling (either automatic or manual) could be chosen. It can be either for the project elements or the for the project roles. Once you are on the accounting tab and by choosing account assignment you may notice that for every cProjects element a corresponding WBS element getting created in the Project system. We can do costing thereafter for the WBS elements in the Project systems
    Regards
    Award points for useful answer
    Edited by: Yogesh  Pande on Dec 9, 2008 2:02 PM

  • How to handel this calculation in BI for the Mod. Production Planning ????

    Hi All,
    I have a scenario like this :
    Look into the follwing Data.
    PLANT |    RUNDATE|    WORK_CENTER|   SHIFT|  PRODUCT_TYPE|    ALLOWED_TIME|   LINEHOUR1  
    1010--10/01/2007D0001A400--
    0.114
    1010--10/01/2007D0001B500--
    0.142
    1010--10/01/2007D0001C100--
    0.028
    1010--10/01/2007D0001D1100--
    0.314
    1010--10/01/2007D0001E600--
    0.171
    1010--10/01/2007D0001F800--
    0.228            
    TOTAL ALLOWED_TIEM------       3500
    1010--10/01/2007D0011A1400--
    0.334
    1010--10/01/2007D0011B500--
    0.142
    1010--10/01/2007D0011C100--
    0.028
    1010--10/01/2007D0011D1100--
    0.314
    1010--10/01/2007D0011E600--
    0.171
    1010--10/01/2007D0011F800--
    0.228            
    TOTAL ALLOWED_TIEM------       4500
    I have to calculate the Production Line Hours, based on the following calculation.
    Now i have to input the  value in the INFOOBJECT LINEHOUR1 based on the following calculation.
    400 / 3500 = 0.114  (ALLOWED_TIME of every line item has to be divided with TOTAL ALLOWED_TIME)
    500 / 3500 = 0.142
    100 / 3500 = 0.028
    1100 / 3500 = 0.314
    .........so on
    The workcenter is different is two blocks of example data, and  hence to be calculated differently.
    Now how to achive this,
    I appriciate your insite on this problem.
    Regards
    Shaan.

    Hi Philips,
    Thanks for your response.
    I want to make you more clear about the problem.
    We are calculating based on the following combinations.
    PLANT--RUNDATE-WORKCENTER-SHIFT-----PRODUCTTYPE
    We have three different Plants.
    Rundate is assume as the Calday.
    We have 18 Workcenters.
    Each Workcenter can have 3 shifts maximum.
    And in every sift there would be 3 to 4 product types produced.
    So what i mean to let you know is, the calculation is not based on WORKCENTER, where as it is based on all the five(5)
    characteristics combination.
    The total allowed time will be calculated based on PLANT......RUNDATE......WORKCENTER....SHIFT.
    We normally calculate the linehour with the below formula...
    (ALLOWED TIME/ TOTAL ALLOWED TIME) * (SHIFTTIME - DOWN TIME - BREAK TIME).
    So i have all the information in the line item level except the TOTAL ALLOWED TIME.
    Now i want to insert a new column in the CUBE and wanted to have the TOTAL ALLOWED TIME in every line item,
    might not seem to be a good idea, but just let me know how to do it.
    If it is not clear, you can ask me for further questions.
    THANK  YOU PHILIPS.
    Regards
    Shaan

  • Product Costing without PP ( Production Planning ) Module.

    Is it possible to implement product costing without PP being implemented ? If yes then how and what steps and if no then why is it not possible ?
    Edited by: sapr3india on Mar 25, 2010 11:42 PM

    HI,
    Yes, It can be done using the CO Production order.
    Regards

  • List of STandrad reports relevant for Discrete Manufacturing

    Hello Gurus,
    Can somebody help me with the list of Standard SAP reports other than COOis
    Thnx in Advance
    HKR

    Dear HKR,
    Best way is use t-code
    SAP1 or SAP2
    it will list Std Reports
    Regards
    Madhu