Hi All,
Can any one please provide me with the actual steps towards Period end Closing and year end closing for Financial Closing.By step I mean steps in order i.e which step will be followed by which one.
This is urgent
Pinee
Hi
http://www.sap-basis-abap.com/fico/sap-fi-month-end-and-year-end-activities.htm
First you will have to close the Posting period in the Materials Management side. To do this use the T.Code MMPV and give the period that needs to be Opened. Once this is done you will not be able to Post any Material Documents in the previous period.
Now at the Financial side you need to open the next period and at the same time you need to close the Previous period. This can be done in T.Code OB52
here is the list for FI/CO year end closing check list:
now i am sending one document with T.codes
CLOSING ACTIVITIES
1 Execute Report for Inter Company Activity & Journal Entries
2 Open posting period for next yr (T.Code: OB52)
3 Run Business Area's Assignment report. (T.Code: F.50)
4 Review list of recurring journal entries (T.Code: FBD3)
5 Execute Recurring Entries for A/R, A/P, G/L (T. Code: F.14)
6 Process Parked A/R, A/P, G/L accounting documents (T.Code: FBV0)
7 Final Cutoff for the Maintenance of Fixed Asset- Add Transfer and Retire (T.Code: ABUMN)
8 Run Depreciation in Test Run and post (T.Code: AFAB)
9 Verify Display Log for Depreciation Test Run (T.Code: AFBP)
10 Capitalize AUC Assets if needed (T.Code: AIAB, AIBU)
11 Enter Payroll Data to SAP (T.Code: CAT2)
12 Verify Depreciation Balances with GL balances (T.Code: ABST2)
13 Post Depreciation (T.Code: AFAB)
14 Execute Asset History Report, and retire assets if needed (T.Code: S_ALR_87011963, ABAVN)
15 Adjust specific depreciation areas if necessary (T.Code: ABCO)
16 Reconcile AM sub ledger with GL (T.Code: ABST2)
17 Check Bank Data (T.Code: S_P99_41000212)
18 Review AR Open Items (T.Code: FBL5N)
19 Review AP Open Items (FBL1N)
20 Execute Pending Invoices(T.Code: MRBP)
21 Clear Open Item for GRIR, freight (T.Code: F.13)
22 Reconciliation of Financial Documents and transactional figures (F.03)
23 Open new CO Posting Period: (T.Code: OKP1)
24 Compare current (cost estimates) with last current price (Moving Avg) (T.Code: OKBH)
25 Update current cost price to material master price field (T.Code: CK11N, CK24)
26 Process Freight charges, Match SD freight to actual (T.Code: V-31)
27 Review Internal Order Postings(T.Code: OKSA)
28 Settle All Orders (T.Code: KO88)
29 Verify All Post Goods Issue have been Invoiced (Billing Due List) (T.Code: VF04)
30 Review SD Billing Doc from prior month that have not yet been released to accounting (T.Code: F.2D)
31 Reconciliation of MM movements in Transit Intra-SAP to Non SAP
32 Reconcile PI Inventory with SAP (T.Code: MI07)
33 Perform Manual Adjustment if needed (T.Code: F-02, FB50)
34 Verify balance of the GR/IR account (T.Code: MB5S)
35 Post Accruals and Deferrals (T.Code: FBS1)
36 Clearing of Cancelled Documents (T.Code: F-03, F-32, F-44)
37 Check Profitability Segment Adjustment (T.Code: KISR)
38 Aging Report-Reconcile GL balances with sub ledger balances AP (T.code: FBL1N, FBL5N, FBL3N)
39 Check the check run numbers (T.Code: FCH1, FCHI)
40 Bank reconciliation Data (T.Code: FF67 & FEBA)
41 Enter Tax Journal Entry (T.Code: FB41)
42 Reconcile GL balances with sub ledger balances AR/MM/AP (T.Code: F.03)
43 Display Balance Sheet Adjustments (T.Code: F.5F)
44 Post Balance Sheet Adjustments (T.Code: F.5E)
45 Post Foreign Currency Valuation (foreign exchange) (T.Code: F.05)
46 Check generic cost centers for posting with wrong accounts
47 Correct wrong postings on generic cost centers
48 Check Validation dates for Cost Centers, Cost Elements, CO area (T.Code: GGB0)
49 Check COGI--for both month end and year end
50 Doubtful receivables (T.Code: F104)
51 Verify In-transit Inventory
52 Reconcile PA to G/L (T.Code: KE5U)
53 Post Cost Center Assessments and Distributions (T.Code: KSU5 & KSV5)
54 Run CO-FI Reconciliation to balance (T.Code: KALC)
55 Run BW reports P&L and Balance Sheet
56 Maintain CO yr variant (T.Code: KCRQ)
57 Fiscal Yr Balance carry forward AP/AR/AM (T.Code: F.07,
58 Fiscal Yr Balance carry forward CO (T.Code: CXS1)
59 Fiscal Yr balance carry forward FI (T.Code: F.16)
60 Fiscal Yr balance carry forward PCA (T.Code: 2KES)
61 Set Document number ranges - FI - new year (T.Code: OBH2, OBA7)
62 Set Document number ranges AP/AR - new year (OBA7)
63 Generate Financial statement Reports (T.Code:OB58) OR (T.Code: FSE2)
64 Change Fiscal Year For Assets (T.Code: AJRW)
65 Year end Closing-- Asset Accounting--final for year end (T.Code: AJAB)
66 Close CO Posting Period : (T.Code: OKP1)
67 Close Prior A/R Posting Period (T.Code: OB52)
68 Close Prior A/P Posting Period (T.Code: OB52)
69 Close Prior MM Posting Period (T.Code: OMSY)
70 Reverse accruals and deferrals for the new month (T.Code: F.81)
71 Reconciliation of Financial Documents from old fiscal year and new fiscal year (T.Code: FNSL)
72 Load Balances, Budget Data for Cost centers, sales
73 Update Retained Earning Account , balance carry fwd (T.Code: F.16)
Month end closing Activities
1. All the expenses including amortization, prepaid expenses, Preliminary expenses and accruals have been booked.
2. Complete Bank Reconciliation (T.Code: FF67)
3. Make sure that Sum of Inter company balances is Zero
4. Suspense Accounts should be cleared regularly.
5. Ensure that all documents related to MM & SD have been entered in system. (T.Code:F-22 & F-43)
6. Ensure that all billing documents are released to accounting.
7. Calculate Overheads on all process Orders (CO43)
8. Technically complete all process orders which are fully processed (CORM).
9. Calculate Variance (KKS1)à (Relevant only if Standard cost is calculated).
10. Settle all process orders which are technically complete (CO88).
11. Close All settled Process Orders
12. Close MM period (Transaction Code: MMPV).
13. Carry out GR/IR clearing (F.13) transaction
14. Depreciation Run (AFAB) has been carried out for the month
15. Close FI Posting period after the month end closing activity is over (T.Code:OB52)
Year end closing Activities:
1. Calculate production work in progress on process orders which are not technically complete. (CO88).
2. Carry out Assessment cycle for Cost Centers.(T.Code: KSUB)
3. All month end closing Activities should be carried out.
4. Carry Forward Balances to next year
(With TC: F.16 we can carry forward the balance to next year.
With TC: OBH2 copy the number ranges to next year
Open next year periods by selecting the Posting Period Variant.
then test by posting the transaction in F-02)
Hope ths helps
Please reward points
Sunil
Similar Messages
-
Enhancement Request for Period End Closing
Hi All,
When using Segmented Chart of Accounts, the Period End Closing procedure does not allow you to select different GLs from various companies.
The Trial Balance for example, does allow you to select the different GL sets by pressing Find in the Selection Criteria.
In cases where there is a different Retained Earnings accounts for each company on the same Chart of Accounts, you are forced to perform the Period End Closing on a single Retained Earnings account for ALL the companies.
Please can this be enhanced much like the Trial Balance.
Kind Regards
TanveerTanveer,
you could try use more than one retained earning account. But in the report, there is expanded button where you can choose the posting various date. I also suggest to post your message to the other forum within business one forum as suggested in the note but I am not sure it will be fulfilled quickly. Maybe in the 2 or 3 or even 5 years later who knows.
Submit a ticket to SAP support to know the work around.
Rgds, -
SCHEDULE MANAGER FOR PERIOD END CLOSING
Hi experts
I need to configure Schedule manager for period end process.
can any one have configuration and some theory part documentation.
please send : [email protected]
great help
Thanks in advanceHi
Anybody have the documents mail to [email protected]
Thanks & Regards
Shammi -
Period end closing for FI and AA.
Hi,
pls. explain me in detail Configuration for period end closing for FI and AA.
thanks
jayHi
In FICO period end closings are
Monthly Posting periods
All park documents
Automatic Payment Program
GL A/cs
Vendor A/cs
Customer A/cs
Recuring Entries
Depreciation
BRS
Integration MM, SD
Withholding Tax etc.,
CCtrs
CElmts
Internal Activity Allocation
Internal Orders
Distribution Cycles
Assessment Cycles
COPA Reports etc.,
AA
Depreciation Run (AFAB)
Asset Under Construction (AUC) this is year end closing activity.
Shammi
assign points if it is helpful -
Period End Closing in sap b1 8.8
Hi All Expert,
Pls. Provide me step of period end Closing. How we can execute previous year period (i.e 2010) in SAP business one.inform me with details.
ThanksHi Rashmi ,
Period-End Closing Checklist are :
Period-end activities take place at the end of the month or the end of the quarter, or both, depending on how your financial accounting processes work. In either case, the checklist at the end of the period is much the same.
Make sure that all transactions for the period were posted properly, including adjustments and accruals
Print trial balance (a balance of each account and a current status)
Print vendor liabilities aging and customer receivables aging reports to reconcile receivable accounts with the G/L
Print inventory audit report to reconcile inventory with the G/L
Print financial statements
Make a backup of your database and put it in an off-site storage location
Close or inactivate the fiscal period by locking it using the posting period window
You can Visit :
https://websmp201.sap-ag.de/~sapidb/011000358700001209192007E/EoP_YE_2007.pdf
https://websmp201.sap-ag.de/~sapidb/011000358700001196942007E/FIN_CW50_Year_end_closing.wrf
Thanks n Regs,
PAPIL -
Hi Experts
I have one doupt some customer or vendor bill wise balances
Examble:. Invoice No 1001, Dated 20-3-09, Amount = Rs.1000
Invoice No 1002, Dated 22-03-09, Amount = Rs.2000
That Customer invoices i should pay 20-04-09
After period end closing next financial year, whether the buisness partner opening balances like amount = 3000 or bill wise ?
If the opening balance amount = 3000 how can i found the bill wise details?Check these links for Period End Closing Documents
[https://websmp201.sap-ag.de/~sapidb/011000358700001196942007E/FIN_CW50_Year_end_closing.wrf]
[https://websmp201.sap-ag.de/~sapidb/011000358700001209192007E/EoP_YE_2007.pdf]
[https://websmp201.sap-ag.de/~sapdownload/011000358700001111052006E/Year_End_Closing_V20_EN.pdf] -
Improvement of Period-End Closing Utiltity
Hello.
Currently I've been trying to test and review SAP 8.8 Preview version.
The reason I create this message is that I hope There will be some improvement of Period-End Closing functionality.
in the case of Account Segmentation, Financial Reporting of B1 allows us to select account segement easily. so this can help us to apply IFRS reporting.
however, We also need to include this funtionality for Period-End Closing.
It is very simple functionality but It is very important for ERP Market in South Korea. Because currently many local ERP Vendors enhanced their IFRS functionality. We are fighting with them desperately. SAP still doesn't give us any idea about this. That's why We have made some functionalities of IFRS using SAP B1 Account Segmentation and Add-on.
Regarding our Configuration, This Account Segmentation covers IFRS and Local GAAP.
This is the issue of SBO competitiveness applying IFRS transition period. the requirement of the functionality is very simple but this function gives me strong competitiveness in the ERP market.
Is there any chance to improve this funciton?
Scenario
1. Main Menu > Administration > Utilities > Period-End Closing
2. Click Find.
Curent Status
There's no way to select each account segmentation automatically. That is why I need to select each account segmentation manually.
My Expectation
Hopefully SBO will help customers to select accounts by each account segment like financial reporting. Then SBO will satisfy Multi-GAAP and Multi Ledger (IFRS, Local GAAP) on the transition period.
Thanks and regards,Hello Seung-Kyoo Lee,
could you please provide some more detail example of the issue you described. In particular I would like to understand what is meant by "...I need to select each account segmentation manually". My understanding is that account segmentation should be selected at the begining of the use of the database before any transaction is posted.
On the other side End Year Closing provides a possibility to select accounts however the segmentation should be already selected in the setup of the company. Do you mean something like the following example:
Setup of account segmentation: account code: segment1-segment2-segment3.
Then selection in the End Year Closing functionality is:
when segment2 is selected then all accounts with segment2 are selected regardless what is in segment3. Is it something like this?
Best Regards,
Martin Slavik
SAP Business One Solution Manager -
Period-end closing process for product cost collectors
Hi Friends
Please explain me step s involved in period-end closing process for product cost collectors.
Regards
SandeepDear Mr.Sandeep,
Using CO88 - variance will be settled.
Please go through this link.
<u>http://help.sap.com/saphelp_470/helpdata/en/5f/1faba54aee11d189740000e8322d00/frameset.htm</u>
If useful reward points and close this thread.
Regards
Mangal -
Period end closing for production orders
Dear all,
what is period end closing???
Pl. enlist all period end activities for product costing by order scenario.
what inventory adjustments are necessory.
what FI entries required to post??With respect to PP- Period end closing is the procedure to close all the production orders and see that cost is flowing from production order to material
During period end - we TECO all the orders and see that production is complete from PP angle. Then costing will calculate over head/variance and settle the difference to production material or price difference a/c depending on the production material price control.
Just see below the example of a production and costing entries. Thi8s may be helpful to understand the concept.
Planned price
Planned Material cost = 115.15USD
Planned Activity cost = 6 USD
Planned Over head = 25% of material cost+ 250% of activity cost = 28.79+15=43.79
Total cost = 164.94
Product cost as per S price = 1 USD (example)
After GR and confirmation
Actual Material cost = 7456.55 USD
Actual Activity cost = 2USD
Total cost = 7458.55
Actual O/H = 0
Production variance = 7293.61 USD
After o/h calculation
Actual Material cost = 7456.55 USD
Actual Activity cost = 2USD
Actual O/H = 25% of material cost+ 250% of activity cost = 1869.138
Total cost = 9327.69
Production variance = 9162.75
After settlement
Actual Material cost = 7456.55 USD
Actual Activity cost = 2USD
Actual O/H = 25% of material cost+ 250% of activity cost = 1869.138
Total cost = 9327.69
Production variance = 0
Variance will be settled to Price difference a/c.
When we do the GR the FI a/c will hit as below
Production order expense a/c -
stock a/c +
When we GI the following a/c will hit
Raw material a/c -
Production order expense a/c +
When we settle
Production order expense a/c + or -ve
variance a/c = + or -ve
I hope this will help you. -
Material ledger period-end closing - material selection based period status
Dear SAP Experts,
The OSS note 980475 describes functionality of excluding materials without inventory and postings from the period-end closing of the material ledger. The system assigns a new period status for materials without inventory and postings (05 "Period opened without inventory"). This period status is set by the dynamic period-closing program for the new period (instead of "Period opened") if the material does not have any inventory.
Could you clarify what is dynamic period-closing program for the new period?
In my system this note is implemented but still during costing closing materials are being selected even though no postings have been done on them in that period and no inventory exists.
Thankk you very much for advise.
Best regards,
RobertHi Robert, have you find out what this dynamic period closing is?is this just the option Check and close period in TCode MMPV? or is het one the CKMLCP steps?
thanx in advance,
Said Dahmaza. -
How to automate FI period end closing?
Hi,
Is there a way to automate FI period end closing?
Currently we have transaction recording for OB52, values are changed by macros in Excel and it run in batch input.
It works, but sometimes we have problem with it (eg mistake in Excel).
Is there a way to automate this procedure?
Our release is SAP R/3 Enterprise 4.70x200.
Thanks in advance,
PeterHi Peter,
With the help of ABAPer we have develop a Zprogram linked to a t.code. So at the start of the month we have schedule to run that t.code as a monthly job. the logic behind the programe is when run ar the start of the month it opens the posting period for the current month it has run & close the pervious month.
Hope this helps.
Please assign points as way to say thanks -
Period end closing procedure - B1
Hi,
Could any body clarify me on the below.
1. What is the difference between "Retained Earnings A/C" & "Period End Closing A/C".
2. When I opted both as Retained Earnings A/C, and excuted (given Due Date & Document Date as 31.3.08) it is throwing an error as ---"Posting period is not defined"
Please assist in solving the above problem.
Thanks & Regards,
VinayCheck this document on, Tips for Year End Closing 6.5, 2004, 2005, 2005 A SP01_EN
https://websmp201.sap-ag.de/~sapdownload/011000358700001111052006E/Year_End_Closing_V20_EN.pdf
You may also register for the EES on the same on 17 December, 2008.
Troubleshooting issues that may arise during the year-end closing process with SAP Business One
December 17, 2008; 10:00 am - 11:00 am CET
(GMT+01:00) Amsterdam,Berlin,Paris,Rome,Stockholm
Session held in English, Registration
Troubleshooting issues that may arise during the year-end closing process with SAP Business One
December 17, 2008; 5:00 pm - 6:00 pm CET
(GMT+01:00) Amsterdam,Berlin,Paris,Rome,Stockholm
Session held in English, Registration
Check this Thread for registration -
Xl reporter shows different result before and after Period-End Closing.
Hi SAP experts,
We have an issue with XL Reporter. When we ran Period-End closing and ran XL - PL Period & YTD (with the same parameters), XLR shows nil in the Actual YTD column and the monthly figures are out by a big difference (example pre-rollover it was $110K after rollover it shows negative $12M).
This happens on 2 different clients running 2 different SAP B1 (2007A PL 42 and 8.8 PL 13) on the same XL Reporter which is possibly the default XL report that comes with the installation.
I don't have any idea why the XLR is running 2 different figures altogether when running the same XLR using the same parameter before and after rolling the year over. The default SAP B1 P&L report stays the same before and after the rollover, I would have expect that the same would happen with the XLR.
Please advise.
Regards,
Didy ArfionoHi Julie,
Thanks for the reply. I'm not entirely sure what you mean by excluding a certain transaction for closing entries as this would defeat the whole purpose of PEC which as you stated was to transfer P&L balances to retained earnings account to be carried forward.
I've check at some guides including one from Orchestra Team (http://www.youtube.com/watch?v=e4tUo774eXg) and so far the process that I've done is exactly what it is.
Regards,
Didy -
Nested Kmat; Period-end closing
Hello,
In PP we are using Nested Kmat in a Material variant (fert):
Fert (material variant)
---Kmat as a bom sub-assembly)
Kmat
Halb...
and during variance calculation for a kmat sub-order in period end closing (KKS2) I'm getting an error message:
No suitable settlement rule found for object OR000100812538. Message number KV206. (the explanation doesn't ring a bell for me??)
I think I know why I'm getting this error message for a configurable material (KMAT) because there are no standards cost
What should I do?
Should I change the message from error to warning ?
Do I need to create a new PP order type with repetitive setting and product cost collectors???
What would be the better / good approach?
Thanks!
LucWe're not working with sales order stock... All sales orders are with FERTS that are MTS.
Kmats material are only used to reduce the amount of sub-assemblies created...
Variance calculation has to occurs for the top level (fert) but is there a way to exclude these kmat orders to enter in the run?
Otherwise i'm getting too many error message and analysis besome almost impossible..
Regards!
Luc -
Dear all,
Did anyone tell me the period end closing in CO?
i.e. what accounting entries required to pass for inventory valuation???
how variences are settled in FI etc???Hi Ranjeet,,
The period end closing activities:
Open new CO Posting Period: (T.Code: OKP1)
Settle All Orders (T.Code: KO88)
Review Internal Order Postings(T.Code: OKSA)
Compare current (cost estimates) with last current price (Moving Avg) (T.Code: OKBH)
Update current cost price to material master price field (T.Code: CK11N, CK24)
Check Profitability Segment Adjustment (T.Code: KISR)
Correct wrong postings on generic cost centers
Check Validation dates for Cost Centers, Cost Elements, CO area (T.Code: GGB0)
Calculate Overheads on all process Orders (CO43)
Technically complete all process orders which are fully processed (CORM).
Calculate Variance (KKS1)à (Relevant only if Standard cost is calculated).
Settle all process orders which are technically complete (CO88).
Close All settled Process Orders
Check COGI--for both month end and year end
Verify In-transit Inventory
Post Cost Center Assessments and Distributions (T.Code: KSU5 & KSV5)
Run CO-FI Reconciliation to balance (T.Code: KALC)
Maintain CO yr variant (T.Code: KCRQ)
Calculate production work in progress on process orders which are not technically complete. (CO88).
Carry out Assessment cycle for Cost Centers.(T.Code: KSUB)
Fiscal Yr Balance carry forward CO (T.Code: CXS1)
Fiscal Yr balance carry forward PCA (T.Code: 2KES)
Close CO Posting Period : (T.Code: OKP1)
For futher info; http://www.sap-img.com/sap-fi.htm
Thanks and regards,
Sri
Maybe you are looking for
-
Remote Log Targets not working in ACS
Dear all I have 2 x ACS boxes configured as Primary & secondary. In ACS1 - In monitoring and reports-> option I can see the User authentication, authorization and Accounting activities logs. I want to configure ACS2 as remote log server. For that in
-
I have a MacBook Classic that is unsupported and my Mac Pro is supported but I can't open App Store from it because there's no OS and I can't purchase from my classic because it's unsupported. Halp
-
Receiving Transaction Register
Hello Gurus, I need to make a change in "Receiving Transaction Register" (RCVTXRTR.rdf). Client does not want Deliver transaction type and its associated Correction transaction type in the report. He just want Receving and its correction transaction
-
Dear All, I have 2 databases one of them in Egypt and the other in USA. I want to transfer data of one schema between the 2 databases. I currently use export and import utility to do this action but the size of data is very large so I want an automat
-
SAP Utilities Customers E-Services (SAP-UCES) - Documentation?
Hi, I am trying to find SAP Help or full implimentation documentation for SAP Utilities Customers E-Services. Can someone please assist? Thanks, Adriaan