STO for multiple plants
Hi,
I need a help on one issue.
I have 4 plants say A,B,C,D.(Under 1 Co code)
I want to configure STO process.I have done it for 2 plants in the past.
We have to crete internal customer & vendor (acct grp 0007).
Now in SPRO,I have to do the set up for STO.
For plant A, cusromers will be B,C,D & similarthing will be for plant B,C,D.
I can assign only one customer in the STO set up.
How to do this in case of multiple plants?? I 'm doing this STO with delivery.
Similarly, how the subcontracting scenario will be there in plant to plant?
Please throw some light.
Thanks in advance,
Piyush
Dear,
I think ur confused,
be clear that u have to maintain in customising that
the plant u r setting up is which customer code for u.
say plant XYZ .And u have created the plant XYZ as a customer ABC and Vendor as PQR
so in Customising u r settings as
XYZ is my plant which is customer as ABC and selling through the mentioned sales area.
in vendor master u are maintaining that this vendor PQR is my plant XYZ.
and in customer master ur maintaining that this customer ABC is my plant XYZ
regards,
sujit
Similar Messages
-
Intracompany STO between multiple plants
Hi Experts,
What should be the easy way of setting up STO between multiple plants via delivery. I've 15 plants defined here under a single company code and any plant can transfer goods to all plants. So should I maintain this settings at "Assign document type" factorial 15 times i.e., xxxxxxxxxxxxxxxxx times?
Please help. what should be the easiest way?
Thanks,
RajooDo you want to create STO po between all 15 plants? Every time you create STO? Why don't you go for MB1b with movement type 301 or 303 and 305. Alternatively you can think about using special procurement key in MRP-2 view for direct withdrawel from the alternate plant.
But if you want to do STO between all plants then you need to give all possible combination with document type in config, you have no other alternate
regards
Antony -
Creating a PO Using BAPI For Multiple PLants Or Multiple Line Items
Hi All
Can you please suggest me how to create a Purchase Order Using BAPI_PO_Create1 for Multiple Plants Or for Multiple Line items. The Requirement is like the PO is for single material for single vendor but for mulple stores i.e plants
NOte: Suggest me the Creation of PO for MUltiple Line items or for multiple plants Using BAPI . Hope you people will give me the needful.
Regards
Shivakumar BandariHi,
Here is the sample code to do that...
*---> po header data
wa_poheader-vendor = your vendor..
wa_poheader-doc_type = Your doc type..check with Functional contact....
wa_poheader-purch_org = Purchasing Org..
wa_poheader-pur_group = Purchasing Group
*---> po header data (change toolbar)
wa_poheaderx-vendor = 'X'.
wa_poheaderx-doc_type = 'X'.
wa_poheaderx-purch_org = 'X'.
wa_poheaderx-pur_group = 'X'.
*---> poitem data
data: item like ekpo-ebelp.
item = '0010'.
loop at t_parts.
it_poitem-po_item = '00010'.
IT_POITEM-PLANT = Plant..
IT_POITEM-STGE_LOC = Sloc...
*---> poitemx (item data change toolbar)
it_poitemx-po_item = '0010'.
it_poitemx-po_itemx = 'X'.
IT_POITEMX-PLANT = 'X'.
IT_POITEMX-STGE_LOC = 'X'.
*---> add record's to internal table
APPEND: it_poitem,
it_poitemx.
endloop.
*call bapi_po_create1
CLEAR v_ebeln.
CALL FUNCTION 'BAPI_PO_CREATE1'
EXPORTING
poheader = wa_poheader
poheaderx = wa_poheaderx
IMPORTING
exppurchaseorder = v_ebeln
TABLES
return = it_return
poitem = it_poitem
poitemx = it_poitemx.
*---> check the return table for error message
READ TABLE it_return WITH KEY type = 'E'.
IF sy-subrc NE 0.
CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
EXPORTING
wait = 'X'.
endif.
Thanks,
Murali -
Restrict PO creation for multiple plants for same company code
Hi Gurus,
We want to restrict PO creation for multiple plants in the same company code. Based on Standard SAP settings for Purchasing organization assignment with multiple Plant and multiple Plant assignment with single company code, this is happening. Is there a way that we can restrict by doing some customization change.
Any thoughts or ideas will be highly appreciating.
Thanks and Best regards,
Karun KumarHi,
Said functionality is not available in SAP standard.
To avoid the same ,i can suggest implement release strategy for PO,and then higher authority / commercial team can check created PO,if multiple plants available in single po then they have the option of rejection for the same.
Or else check BADI-ME_PROCESS_PO_CUST,take the help from abapor and apply the restriction to select multiple plant in PO.
Hope this will resolve your query,
Thanks & Regards,
Sandesh Sawant -
Release strategy is not getting Trigerred for Multiple Plants in PO.
Dear gurus,
I have a Release strategy which is working Fine when I create a PO with Same Plant in line items.
But My release strategy is not getting trigerred when I have Different Plants in Line items.
I have Maintained all the Plants in the characteristic Values of Plant.
Why does the RS work for Single Plant & doesn't work for Multiple Plants in the same PO.
Is there any SAP Note applicable to this? Pl Suggest.
Thanks guys
SNi got your point but i will again say the same thing that for item level field system is not able to block the po if there are multiple line item in RS and that too with different values against same char as system picks only 1 value and it sends that value in RS to cross check wheteher this po needs to be blocked or not .
now in your case system is getting multiple values against 1 field that is plant so now system is not able to send 1 in backend and hence it sends blank value in back end so system dosent blocks the po
even if you use material group or any other item level field system is going to behave that way only that is it will not be blocking the po -
Setup one-step auto GR on consignment STO for sourcing plants
Hi MM experts,
Need to set up the auto GR process for some plants
Can any one please help me how to Setup one-step auto GR on consignment STO for sourcing plants?
Appriciate your help.
Thanks in advance.
Regards
Suresh Babu JHi,
According to my knowledge there is no standard functionality regarding automatic GR for STO. You need to go for enhancement in this regard. You can consignment PO during MIGO with required settings. Thanking you. -
Single Subcon Vendor for multiple Plants - CTM
Dear friends,
We are planning some materials with Subcontracting scenario using CTM
Facing issue when same vendor is executing sub-con process of same material for multiple plants
Total demand of lower level material is flowing to a single plant instead of flowing to the corresponding multiple plants
Because of which excess planning is happening in one unit & no planning is occuring at other units which is leading to a mess
In library, it is provided to proceed with 1050 Location type but not clear on how to proceed further
Kindly guide on this
Regards,
AntonyHi,
Now Planning has to happen at dummy location of type 1050 and not at 1011 to transfer demand to correct plant.
Please check following-:
1. If you are using PPm create product in new location of type 1050.
2. Also check whether Tlane is created for components from plant to this new location.
3. Suggest to retransfer all master data including your subcontracting inforecord post creation of location of type 1050.
If you are using PDS product should get created in new location automaticaly.
Regards,
Santosh -
Is ATP for Multiple Plants possible????
Hi Gurus,
I have requirement like this
we are having two SAP Systems in one Sales order is raised.. and tha will pass to 2nd system with ALE. in Second system actual Availability Check will run for the plant given in the line item of sale order.
but in second system there will be 6 plants containing the same material. here my requirement is system has to check all the stock lying in all the plans at it need to propose the plant at line item level in sales order.
I know that Avail.Check will run for single plant. Is there any way to run this for multiple plants. at present user is changeing sales order and splitting line item into 6 line Items and performing Availability check based on that he is abelt find the in which plant stock is availble it become cumbersome process.
is any User Exit can we give multiple plants for checking Stocks???.
if End User is doing any mistake in doing Avail.Check it leads to Dead Stock.
please provide your Inputs on this
-PradeepBC,
Well, I will assume that you have been diligent and have already determined that the material masters are comparable between your qual system and your production system (I don't know what pre-production means).
First thing I would check would be the differences between qual and prod in availability check configuration. OVZ2. Look especially at the 'accumul' settings. Actually, any difference between qual and prod should be reviewed. Differences are a no-no!
Best Regards,
DB49 -
EXIT_SAPLV50E_001 User Exit is not working for multiple plants case
Hi,
I have to update foreign trade data in Invoice during invoice creation using VF11. For that, I have written code in EXIT_SAPLV50E_001 and updated segal value. This functionality is working fine, if I have a single plant in an invoice. But customer has scenario where they can have multipl plants in an invoice.
For multiple plants in an invoice, this EXIT_SAPLV50E_001 is not called.
I am unable to find another better place where in I could place my code. Please help. Remember, case in multiple plants.
Will be rewarded.
Regards
ArpitHi Arpit,
Please use below mentioned user exit in T-code VF11
he following user exits are available for tcode VF11
Exit Name Description
SDVFX001 User exit header line in delivery to accounting
SDVFX002 User exit for A/R line in transfer to accounting
SDVFX003 User exit cash clearing in transfer to accounting
SDVFX004 User exit G/L line in transfer to accounting
SDVFX005 User exit reserves in transfer to accounting
SDVFX006 User exit tax line in transfer to accounting
SDVFX007 User exit: Billing plan during transfer to Accounting
SDVFX008 User exit: Processing of transfer structures SD-FI
SDVFX009 Billing doc. processing KIDONO (payment reference number)
SDVFX010 User exit item table for the customer lines
SDVFX011 Userexit for the komkcv- and kompcv-structures
V05I0001 User exits for billing index
V05N0001 User Exits for Printing Billing Docs. using POR Procedure
V60A0001 Customer functions in the billing document
V60P0001 Data provision for additional fields for display in lists
V61A0001 Customer enhancement: Pricing
J_3RSINV Customer enhancement: Pricing
or You can use BADI
BADI_SD_SALES_BASIC
BADI_SD_TO_FM
BADI_SD_BILLING
Regards,
Thangam.P -
Release Streatgy for multiple plants
Hi All,
I have one PO with multiple Item having different Plants.
For Each plant i have a release streatgy with different release codes for each plant and in release streatgy i put characterstics like
1. Plant
2. Value
3. Purchase Organisation
4. Document Type.
Now my Question is that when i use mutliple plants for different line items of one PO.
How will my release streagty will work ? and how it should be configured ?
Regards,
Pardeep MalikHi,
Your Release strategy will not work.
In you want to get the release strategy for multiple plant then you have to define another strategy in OMGS u2013 say 01 u2013 07 as Multiple plant and for that strategy in CL24n mating all the characteristics and donu2019t maintain any value for your characteristics plant and then check.
Try it its very helpful -
Creating Authorization for multiple plants
Hi,
I have one requirement that, Creating Authorization for multiple plants
SELECT-OPTIONS: s_werks FOR mseg-werks.
AUTHORITY-CHECK OBJECT 'M_MSEG_WMB'
ID 'ACTVT' FIELD '03'
ID 'WERKS' FIELD s_werks.
1. If have no of plants in s_werks then how to authorize the plants?
2.if i dont enter any plant in my selection screen how to authorize that?
3. if i have 5 plant only then how i can authorize those perticular plants only?
Thanks in advance,
Thanks,
DP.S_WERKS is not a field; it's a set of fields. Use simple ABAP to select your plants and loop at the selection(s) to check...
-
Single inspection lot for multiple plant
Dear Experts,
I am from pharma industry, my requirement is, there is any possibility to create single inspection lot
for multiple plant.
please guide.
Thanks in advance.
Yuvraj S. DhotreDon't open multiple threads for same query. It makes the solutions to be scattered.
-
Hi
Please inform, How to get report similar to CS15 output for multiple plants?Hi Bhurke,
If you want to search Material Where-used list for multiple plants, then in CS15 first screen enter where used material number and in second screen under Plant give * ( Star symbol) and execute. System will display the Material where used details across multiple plants.
Thanks & Regards,
Ramagiri -
Hi All
My requirement is to make MB56 run for multiple plants and plant should not be a mandatory field as currently is in MB56.
Kindly let me know if there is any way i can do it.
Thanks and Regards
ShilpaAs this tcode is an Module pool.. so the only way to do is.. copy these 2 programs RVBBWULS and RVBBWULS0100 to ZRVBBWULS and ZRVBBWULS0100. the Rest of the programs in this need to be the same (don't copy the other's) now go head & comment the line of PA_WERKS
as below..
PARAMETERS: pa_matnr LIKE mcha-matnr MEMORY ID mat.
pa_werks LIKE mcha-werks MEMORY ID wrk.
select-options pa_werks LIKE mcha-werks MEMORY ID wrk.
I think this might work... -
Product Costing Period end processing - for multiple plants at a time
Hello SAP gurus,
Does any one knows how to handle the Product Costing Period End operations like WIP calculation, Variant calculation and Settlements for multiple plants (but not all). Even if knows how to do it as a period end batch job, that would be nice.
I know that we can handle this with Closing Cockpit. But i am looking for anything other than Closing Cockpit
Thanks in advance
SuryaHi
Apart from CO Closing cockpit, you can use the following programs to schedule the background jobs
T codes - Program names
CPTD - RKWTP_CPTD
KKS1 - RKKKS1N0
CON2 - RKAZCON2
KKAO - SAPKKA07
CO88 - RKO7CO88
Regards
Ajay M
Maybe you are looking for
-
How to suppress status message in session method in a BDC?
Hi experts, I am upadting condition records in VK12 by creating BDC sessions.I am getting a warning message which is stopping the processing.When I press Enter the processing continues but this is not replicated while processing th
-
I have an update for 'Pages', however, when I put in my yser ID and password and click update I get routed back to the enter user ID and password screen. It;s just a loop each time. Any suggestions?
-
Gdm locale problem..
Default locale is en_US.UTF-8 and I need to input Korean Language.. So LC_CTYPE is setted ko_KR.UTF-8 in .xinitrc But only when loggin in gdm, locale LC_CTYPE doesn't work., .profile and .xprofile file is no useful.... In my experence, .xprofile affe
-
Role based authorization in initiative
Hi, We can assign default authorization for role types in Projects. For example a the role PM can be assigned Admin auth and the person assigned to PM role gets admin role. We want the same functionality in initiatives but it is not working. Has anyo
-
Additional transistions, effects and PlugIns???
Anywhere to get some additional video transistions/effects for free that people have created? I figured there must be an open source community where people share the transistions and effects they have created for FCP. I have a few to share and would