STO for Sloc to Sloc

Hi,
In our present project client is contemplating with the idae of using STO for storage location to storage location. with reference to this STO I have the following questions
a) Is it possible to capture the freight cost in the STO?
b) If possible to capture the freight costs then can we add this cost to the inventory? or we need to expense it?
Thanks in advance.
P.S. Both the storage locations belong to the same plant.
Edited by: Muttu Koti on Nov 2, 2011 8:16 PM

Hi,
Yes it is possible to capture the freight cost in case of storage location to storage location STO,
follow the below steps.
1: Creat one vendor and assign to your plant in purchasing view -> EXTRAS -> add purchasing data
2: Assign customer to plant
    IMG -> MM -> Purchasing - >Purchase Order -> Set up Stock Transport Order > Define Shipping Data for Plants
3: Assign Delivery Type and Checking Rule
    IMG -> MM -> Purchasing - >Purchase Order -> Set up Stock Transport Order > Assign Delivery Type and Checking Rule
4: Set Up Stock Transfer Between Storage Locations:
     IMG -> MM -> Purchasing - >Purchase Order -> Set up Stock Transport Order -> Set up Stock Transfer between Storage    
      Locations.
5: Assign Delivery Type and Checking Rule According to Storage Location:
6: Define Shipping Data for Stock Transfers between Storage Locations
7:  STO - P.O Pricing Procedure: 
   SPRO > MM > Purchasing -> Conditions-> Define Price Determination Process -> Define Schema Determination - > Determine Schema for Stock Transport Orders - assign Document type to your STO pricing procedure.
   Double click on Determine schema for STO
make new entry as per your requirement assign the pricing procedure.
do all the above setting then do the user trnsaction  ME21N, ME28, VL10B, VL02N, GR for outbond delivery.
regards,
zafar

Similar Messages

  • Mvt 301 - How does system allow to use this MVT for sloc to sloc posting

    Hi,
    Using MVT 301 one can post goods from sloc to sloc withing the same plant. Why is SAP not preventing this, when there is 311 available specifically for sloc to sloc transfer?
    Regards

    MVT type 311 is used many transactions . Depend on application Mvt types used In your case your looking material transfer one case only.
    311     CIP5     CC5: Update PDC messages
    311     CIPV     Posting PDC records
    311     HU02     Creating and Changing Handling Units
    311     HUMO     HU Monitor
    311     MB11     Goods Movement
    311     MB1B     Transfer Posting
    311     MB21     Create Reservation
    311     MB26     Picking list
    311     MF60     Pull List
    311     MF65     Stock Transfer for Reservation
    311     PK13     Kanban Board: Demand Source View
    311     PK21     Change Kanban Container Status
    311     PK31     Container Correction
    311     PKBC     Chnge Container Status With Bar Code
    311     QA11     Record usage decision
    311     QA12     Change usage decision with history
    311     QA14     Change UD without history
    311     QA16     Collective UD for accepted lots
    311     QAC2     Transfer stock to insp. lot
    311     VL02N     Change Outbound Delivery
    311     VL32N     Change Inbound Delivery
    311     VLMOVE     HU Goods Movements
    If you can see 301
    301     HUMO     HU Monitor
    301     MB11     Goods Movement
    301     MB1B     Transfer Posting
    301     MB21     Create Reservation
    301     MB26     Picking list
    301     QAC2     Transfer stock to insp. lot
    301     VL02N     Change Outbound Delivery
    301     VL32N     Change Inbound Delivery
    301     VLMOVE     HU Goods Movement.

  • STO between Sloc to Sloc

    Hi All,
    I am trying to set up Stock Transport Order between Sloc to Sloc,
    Have made below settings:
    1. Activated stock transfer between sloc
    2. Assigned delivery type and checking rule, assigned doc type as Stock Transport Order - UB
    3. Assigned the delivery sloc for the plant & also the delivery type - NL
    4. The shipping data is not set up as it is not required in our process.
    In mtl master i have specified that SLoc will be planned independently, no special procurement key maintained. Now when i run MRP, the system does not generate a stock transfer request, even though the stock is below the ROP.
    Am i missing something? Also would like to know, is this possible only with MRP areas active?
    Vivek

    Hi Vivek,
    Please check settings required for your scenario:
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/f4/7d2d3344af11d182b40000e829fbfe/frameset.htm
    I set:
    - SLoc MRP indicator to "2" in MRP4 view of material master
    - reorder point (MRP4 view of material master)
    - replenishment quantity (MRP4 view of material master)
    After MRP run (MD01) I can see the stock transfer proposal ("Transf" MRP element) for the SLoc in the suitable segment of the MRP list (MD04), in the plant segment I can see order reservation.
    Regards,
    Csaba

  • Sto-sloc to sloc transfer

    I am doing sloc to sloc transfer,
    but this thing,I want to do it through STO.
    In this case I can put reciving sloc at the time of po(sto) creation.
    now where can I put suppling sloc. In VL02n the field sloc is appearing as greayed out.
    now suggest me how can I put both sloc(supplying and reciving) in the process of stoc transfer bw sloc to sloc
    through STO.

    Dear,
    Please go through the below link
    http://architectsap.com/blog/sap/how-to-setup-stock-transport-order-between-two-storage-locations/
    Regards,
    Gopala.S

  • MRP - Create STO for Stockk Transfer between Storage Locations

    Hi Everyone,
    I have a scenario where MRP run should create Planned Order as well as STO for a VSF Requirement. The reason is our Plant has got 2 Storage Locations. One is the Production Storage Location and the other is Warehouse Storage Location. The Planned Order should be for Production SLoc and STO should for Stock Transfer from Production to Warehouse Storage Location. Your suggestions are much appreciated to resolve this issue.
    Thanks,
    Jay.

    new releaes bring new features........
    not all new features can run in old environments.
    I know that companies did already Storage location to storage location STOs in 4.6c but they had z-tables to assign customer numbers at storage location level, and they had changed some  coding to make it happen.
    I am not sure if there is an OSS note that explains the steps and modifications needed......but try to search OSS.

  • Transfer posting from Sloc to Sloc

    Hi,
    We do TF from storage location to storgae location with in the palnt using 311 mov. type against Reservation.It is taking 3days for the stock to receive physically in the receiving storage location.
    Now the client wants the stock to be" in transit" till it reaches receiving storage location,for this we can use 313 and 315 movement types.
    But client wants to do transfer posting form one Sloc to other Sloc only using "Reservation"
    But the system is allowing to create reservation only using 311 but not with 313 movement type.
    Kindly suggest me how to do 2 step TF from Sloc to Sloc using Reservation.
    Thank you.

    Hi,
    Compare the configuration of movement type 311 & 313 will find two differences
    1)Reservation category is defined as U for 311 & it's blank for 313.
    2)Allowed transaction for movement type for both 311 & 313. For 311 MB21 is defined whereas for 313 MB21 is not defined.
    Because of these reason you are not able to create reservation against 313 movement type.
    If you want to create reservation against 313 movement type change configuration accordingly by comparing 311 movement type.
    Regards
    Ravi Shankar.

  • SLOC to SLOC feature missing from Ext Set 1.10

    We need some functionality for shipping point selection and capturing freight costs on a SLOC to SLOC movement within the same plant. We are told it was made available in Extension Set 2.0. Upgrading to that is not an option at this time. We are looking for a note that will give us this specific functionality without going through a full upgrade.
    Is anyone aware of a note that covers this issue?

    Dear Ronald,
    Stock transportation orders between two storage locations of the same plant are indeed part of Extension 2.0. However, there are some OSS notes documenting the relevant coding changes that you might find interesting. Note no. 587383 is the first, it lists the other notes.
    Best regards,
    Christiane

  • Intra company STO for product under consigment from vendor

    Hi
    I know in 4.5 we were unable to transfer inventory under vendor consignment between plants using an STO. This was driven by the STO having item category U and consignment needing item category K. It looks like this also remains true in ECC 6.0 but does anyone know of a way of doing this there?
    Help appreciated. Answers rewarded.
    Thanks
    Duncan

    Hi
    I dont think there is any way to make STO for consignment in SAP. Please let me know the reason why you want to map the process as consignment STO and how you are doing it now. You can make a return delivery to vendor and can again receive the required quantity as consignment in other plant. For reporting you can create new reason code for mvt type 122.
    Regards
    Praful

  • Setup one-step auto GR on consignment STO for sourcing plants

    Hi MM experts,
    Need to set up the auto GR process for some plants
    Can any one please help me how to Setup one-step auto GR on consignment STO for sourcing plants?
    Appriciate your help.
    Thanks in advance.
    Regards
    Suresh Babu J

    Hi,
    According to my knowledge there is no standard functionality regarding automatic GR for STO. You need to go for enhancement in this regard. You can consignment PO during  MIGO with required settings. Thanking you.

  • STO for Plants with different excise registers

    Dear All,
    We have to transfer the materials within a company code. Two plants are different one for trading where we maintain RG23D register and other for manufacturing where we maintain RG23C register.
    Can we use STO for stock transfer between the Plants. And how to maintain proper excise register in both the Plants.
    Regards
    Vikas Sehra

    You can definitely have stock transfer between two plants: one a manufacturer and another a trader.
    Maintain the proper assignment of registers in the corresponding excise groups.
    The STO process followed is as for a depot transfer:
    1) STO, OBD, PGI, VF01 and J1IIN in the manufacturing plant where RG23A/RG23C gets updated
    2) GR, J1IG at trading plant, RG23D gets updated with the reference to the parent invoice from the manufacturer.
    3) VA01, OBD, J1IJ, VF01 during sales, here billing automatically picks up excise duty paid to government by the manufacturing plant
    Please note that though you can mark up during sales from the trading plant (sell as a higher price), excise will still be the same as that paid to the government by the manufacturing plant. In case, you want to charge higher excise as well, please look at my document: CIN: Capturing Additional Excise at Depots Due to Price Change – A Certificate

  • Can anyone explain me the procedure and initial settings to do sto for schedule lines?

    can anyone explain me the procedure and initial settings to do sto for schedule lines?
    Create a STO with new doc type for material M1 to ship from plant 1 to plant 2 with qty as 100. On pressing enter you should be able to see schedule lines in delivery schedule tab. In schedule line you should see the Material availability date, GI date, loading date etc.
    can anyone give the answer for this question..

    Hi Megha,
    Please find below links for Config STO with schedule lines.
    http://dhavalatsap.blogspot.sg/p/configuration-of-plant-to-plant-sto.html
    https://scn.sap.com/thread/1260375
    Thanks,
    Bala.

  • STO for sales order stock

    Hi All
    If I am not mistaken, one cannot do a STO for special stock using 2 step transfer, however it is possible in a one step process.
    I have made the setting in config to use a one step process, and it have been set up to use movement type 647.
    I am trying to move Sales order stock from one plant to another plant, and want to maintain it as special stock.
    I can get the process to create the delivery, however, when I try and post goods issue the delivery document, I get the following message.
    MSSA-SABWE exceeded by 2 EA: CISCO1402 ZA30 1000 SALEABLE E
    Cisco1402 is the material
    ZA30 is the plant
    1000 is the storage location
    Saleable is the split valuation we using
    E is the special stock indicator for sales order stock.
    If anyone could please give me some direction.
    Thanks

    Hi 
    We are not using blocked stock at all in any of our processes.
    My understanding is that movement type 647 will not look or put stock into blocked stock.
    If I look at table MSSA, for that Sales order number and material number, it comes up with one entry.  It has a quantity of 2 in unrestricted, Val. GR Blocked Stck is 0.
    Should the quantity of 2 be appearing in there? 
    So the process followed thus far is:
    Sales order raised
    Preq auto created from SO
    Preq converted to PO
    GR for PO
    STO created to move sales order stock from one plant to another
    Delivery created,
    cannot post goods issue.
    Thanks

  • Error on STO for transfering FERT material

    Dear all guru's
    i am facing problame for making STO for FERT material...i am able to do it for other means ROH or HAWA material type and able to whole cycle for STO.
    jst for trail i activated purchasing view for FERT material type. and tried to do it but still not working well.
    Pl suggest, and in addtion please tell me is there any bad implication if i maintain pur view for FERT material type.
    Regards,
    Vimlesh

    Hi,
    Using sto, we can transfer FERT also. I think u might have missed some configuration settings. Kindly check that.
    Regards,
    Prasath

  • SETTINGS STO FOR STORAGE LOCATIONS

    Hi all,
    am new to this community.plz explain me is it necessary to do the settings in spro for sto for storage loacations and why??????

    Hi Amrita,
    First, Wel Come to SAP Community...........
    Plz go through below STO config..........
    Follow the below steps to to make STO between two plants belongs to different company company codes.It is also called as Inter Company STO.....
    1)Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME->PO-> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure,In Customer Master,sales Area Tab: you are maintaining shipping condition)
    2) For Receiving Plant Pur. Org and Co.Code Combination create Vendor master in XK01 and in this vendor master assign the Supplying plant in Pur.Org.Data screen->Extras--> Add.Pur.data
    3) OLME->PO-> Set up STO------>For your supplying plant assign document type NB, Delivery type NLCC and Checking Rule RP
    4)then For your supplying Plant and receiving Plant assign Document type NB
    5)Make sure you are maintaining Sales View for the material at supplying Plant and in Sales /Gen plant Data view maintain Availability check, Loading group and Transportation group.
    6) In SPRo-->Logistics execution> Shipping->Basic shipping functions->Shipping point Determination>assign shipping points-> For your Loading group,Shipping Condition and Supplying plant combination,Assign shipping point
    these are the configuration settings you have to do in background.
    Then Create STO from Receing Plant in ME21N with document type NB.
    Based on that STO, Create Delivery in VL10B from supplying Plant
    Do PGI in VL02N from Supplying plant
    Do GR in MIGO at Receiving Plant keeping Outbound delivery as a ref. document.
    Now your STO bet. two plants belongs to diff. Co.Codes will be completed.
    For Intra-Company STO: ie)STO bet. Plants belongs to same Co.Code
    1)Create one Customer for Supplying Plant Sales area and assign this Customer no with Receiving Plant in OLME---> PO -
    > Set up STO -
    > define Shipping Data for plants. and maintain the same sales area in your Supplying plant.
    2) In OLME---> PO -
    > Set up STO.....for your Document Type: UB and Suppying plant Combination assign Del. Type NL and Checking rule RP
    3) In OLME---> PO -
    > Set up STO...for your Supplying Plant and Receiving Plant combination Maintain Doc. Type : UB
    Make sure you are maintaining Sales View for your Material at Supplying Plant.
    4) Maintain Shipping point at, SPRO----> Logistics Execution -
    > Shipping -
    > Basic Shipping Functions -
    > Shipping Point Determination for Plants.....there for your Loading group,Shipping Condition, Shipping Plant combination maintain Shipping plant..
    Now Create STO in ME21N with Doc.type: UB at Receiving Plant.
    Then Create Delivery in VL10B from Supplying Plant...
    Then Do PGI in VL02N from supplying Plant.
    Then do GR at Receiving Plant based on Outbound Delivery at Receiving Plant...
    For Intra-Company STO:
    1)Create one Customer for Supplying Plant Sales area and assign this Customer no with Receiving Plant in OLME---> PO -
    > Set up STO -
    > define Shipping Data for plants. and maintain the same sales area in your Supplying plant.
    2) In OLME---> PO -
    > Set up STO.....for your Document Type: UB and Suppying plant Combination assign Del. Type NL and Checking rule RP
    3) In OLME---> PO -
    > Set up STO...for your Supplying Plant and Receiving Plant combination Maintain Doc. Type : UB
    Make sure you are maintaining Sales View for your Material at Supplying Plant.
    4) Maintain Shipping point at, SPRO----> Logistics Execution -
    > Shipping -
    > Basic Shipping Functions -
    > Shipping Point Determination for Plants.....there for your Loading group,Shipping Condition, Shipping Plant combination maintain Shipping plant..
    Now Create STO in ME21N with Doc.type: UB at Receiving Plant.
    Then Create Delivery in VL10B from Supplying Plant...
    Then Do PGI in VL02N from supplying Plant.
    Then do GR at Receiving Plant based on Outbound Delivery at Receiving Plant...
    Follow the below steps to to make STO between two plants ( different company company codes).It is also called as Inter Company STO.....
    1)Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME->PO-> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure,In Customer Master,sales Area Tab: you are maintaining shipping condition)
    2) For Receiving Plant Pur. Org and Co.Code Combination create Vendor master in XK01 and in this vendor master assign the Supplying plant in Pur.Org.Data screen->Extras--> Add.Pur.data
    3) OLME->PO-> Set up STO------>For your supplying plant assign document type NB, Delivery type NLCC and Checking Rule RP
    4)then For your supplying Plant and receiving Plant assign Document type NB
    5)Make sure you are maintaining Sales View for the material at supplying Plant and in Sales /Gen plant Data view maintain Availability check, Loading group and Transportation group.
    6) In SPRo-->Logistics execution> Shipping->Basic shipping functions->Shipping point Determination>assign shipping points-> For your Loading group,Shipping Condition and Supplying plant combination,Assign shipping point
    these are the configuration settings you have to do in background.
    Then Create STO from Receing Plant in ME21N with document type NB.
    Based on that STO, Create Delivery in VL10B from supplying Plant
    Do PGI in VL02N from Supplying plant
    Do GR in MIGO at Receiving Plant keeping Outbound delivery as a ref. document.
    Regards,
    Raghunath

  • How to find  open sto for any material in a Plant

    hello Guru's
    I want to find a list of open stos for any material in a plant.Is there any transaction for this,or any procedure

    Hy,
    Use t.Code MB5T (Stock In Transist).
    Regards,
    Dhaval

Maybe you are looking for

  • Things to do in BW Production for SAP BI7.0 upgrade

    Dear Experts, If somebody is aware for the things to do in BW Prod. before starting BI7.0 upgrade i.e. (before client copy to new dev. , renaming system by BDLS etc.) , pl help urgently. Thanks in advance. Points will be rewarded instantly ..........

  • Pass parametrs between pages

    Hi, how can I pass parameters between pages, WITHOUT using a Session bean? I mean: I need to use a Link Action component to pass control to another page (using the page navigation feature) and, along with the request, also pass the Id of the clicked

  • HT4098 I am unable to find the main account page so that I can manage my subscriptions. Can somebody help me?

    I'm trying to manage my subscriptions but can't seem to navigate my way around and find the page on my iPhone. Somebody please help?

  • SharpZipLib : PathTooLong exception

    0 Hey, Is there any sample code for unzipping a zip file using SharpZipLib? I tried few samples. But seems that for longer paths it throws PathTooLong exception. I think there is a solution for this using SharpZipLib. Can someone provide me an exampl

  • Macbook Pro Retina 15 + iPad 3

    Dear forum users, Usually when I plug in my iPad 3 into the left USB port of my Macbook Pro Retina 15 inch the iPad keeps jumping between connected and disconnected. Weirdly enough this doesn't happen in the right USB port. It also happens inconsiste