STO from Plant to Plant in same Company Code
Dear All ,
Please give me brief idea about STO(with screen ) from Plant to Plant in same Company Code
ganga
Dear Ganga Mukerjee
Welcome to SDN
There are plenty of threads available on this topic in both SD general,Sales and MM forums
Please make a search
As this is your first qn i am giving here with some simple steps for STO from Plant to Plant in same Company Code via SD route
INTRA COMPANY STO.
1. There should be two plants in the given company code for intra STO to
happen.
2. Assign Purchasing org of the ordering to the supplying plant.
3. Create a customer in the supplying sales area.
4. Assign the customer to the ordering sales area.
5. IMG > MM > Purchasing > PO > Setup STO > Define shipping data for plants
here go to supplying plant and mention its own sales area.
6. In the ordering plant assign the customer created in the supplying sales area
and also the supplying sales area.
7. Maintain checking rule as 01.
8. Assign the delivery type NL supplying plant checking rule and PO Doc type
UB.
9. Assign document type UB supplying plant and ordering plant then decide up
on either 1 step or 2 steps.
10. Create PO with doc type UB.
11. Go to VL10B give the PO No. and enter, select the line item and click back
ground. (Where Del. Will be created in the back ground)
12. Go to VL02N for picking and PGI.
13. If 1 step no need of doing MIGO else for 2 steps do MIGO.
Hence forth make search
Regards
Raja
Similar Messages
-
External processing in the plant as vendor under same company code
Hi friends,
In our project under implementation we have following scenario.
we have 4 plants under one company code. one of the plant does powder coating as manufacturing activity. Other 3 plants sends components to the powder coating plant for coating purpose.
In IDES Standard scenario of external processing, a purchase requisition is raised thro info record maintained for the external operation. This scenarion works if the vendor is external.
In our case, the vendor is one of the other plant under same company code/client. Also the powder coating needs to be done without any profit margin for internal customers.
Our FICO guys have the opinion that, intra plant can't be a vendor; because raising invoices among plants under the same company codes is against accounting standars.
If anybody has faced this type of scenario nd found the solution, Please share it here.
Thanx in advanceHi Shiva
STO scenario
You can not create only STO as you need to send the unpainted components to another plant through SAP & have them painted back with only payment of paining charges without margin.
Subcontracting scenario
You can not create the Subcontracting PO as this is not your external vendor.
Does this involves excise?
Then the PR/PO ctreated should be of combination of STO and subcontracting. If so this is not possible, as item category is the only field in PR/PO that identifies it as STO and subcontracting. obiviously it cann't have 2 values.
My suggesion on this as...
Create a BOM for painted component with sp procurement key as produced in another plant(paining plant). this will have STO cretaed for paining plant. This will inturn cretae a production order in painitng plant.
The BOM in painting plant will have the unpainted component with sp procurement key as produced in another plant ( fabricated plant) this will have STO created for unpainted components.
I hope I am clear & not confused you much.
Regards
Mahesh
Regards
Mahesh -
Plant to plant stock transfer in same company code
Hi everyone,
I want to know the process for stock transfer between plant to plant in same company code.
Regards
Prabudhhttp://help.sap.com/bp_bblibrary/500/html/J51_IntProcSTwD_EN_IN.htm
In a company, goods movements do not only occur in the form of goods receipts and goods issues. Depending on the organization of the company (for example, decentralized storage) and its sales policy, internal stock transfers might also be necessary.
The stock transfer with delivery is a plant to plant scenario. You are posting a goods issue in plant BP02 and a goods receipt in plant BP01.
This type of stock transfer can only be carried out from unrestricted-use stock of the issuing plant to unrestricted-use stock of the receiving plant.
You post the placement into storage at the receiving plant in a second step. Only then is the event completed and the transferred quantity part of unrestricted-use stock.
Function List
The following functions are provided to support the J51 building block:
Creating a Planned Independent Requirement
Creating a stock transport order in plant BP01
Generating a delivery in plant BP02
Picking of the material and posting the goods issue in the delivering plant
Posting the goods receipt in the receiving plant
Key Points
The quantity posted from stock is first of all managed as stock in transit of the receiving plant. Only once the goods receipt has been posted is the quantity posted to the unrestricted-use stock of the receiving plant. This enables the quantity "on the road" to be monitored.
The transfer posting is valuated at the valuation price of the material in the issuing plant.
Delivery costs can be entered in the stock transport order.
Regards,
Rajesh Banka
Reward suitable points. -
Stock transfer between two plants under the same company code at profit
Hello,
Hello,
I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
How can I map this scenario in SAP?
What will be the cost of my part in these two plants?
What mechanism I would use to transfer the stock from supplying plant to the buying plant?
Your urgent reply is appreciated.
Thanks,Hi
To map this scenario, you should use Profit Centre Accounting.
Example
Matl XYZ is to be transferred from Plant 1000 to Plant 2000 at a profit.
Value of Matl XYZ in Plant 1000 is $100
Transfer Price: $120
From FI view point, there would not be any Accounting document as both Plants belong to the same Company Code.
From PCA view:
Plant 1000:
Internal Revenues Dr. 120
Stock Cr. 100
Profit Margin Cr. 20
Plant 2000:
Stock Dr. 120
Delivery from Profit Centre Cr. 120
Effectively, the value of Matl XYZ in Plant 1000 remains at $100 and in Plant 2000, it is $120.
Hope this clarifies.
Thanks -
Can Equipment No same for 2 Equip in different Plants of same company code?
Hi Gurus,
Please tell me if there is any possibility of having same Equipment No for 2 Equipments in Different Plants.
The 2 plants are in the Same Company code.
e.g. Equip Plant Company Code
1) Equip_DIE Plant1 A
2) Equip_DIE Plant2 A
If it is possible how the Equipment histroy and Breakdown history is updated in the PMIS.
Also tell me the advantages and Disadvantages of keeping same Equipment no for 2 diiferernt Equipments or otherwise keeping different equipment no.
With best regards,
Narendra DereHi Pete ,
Thanks for your valuable reply.
Actually I am doing implementation for 5 plants within same Company Code.
They are geographically distant (say 50km from each Other.)
The Finish Product is same but the method is different.
They have already assigned some Equipment Numbers in the Plant for Regular Maintenance Activities.
Since Planning and Maintenance can be done at the different Plant and team of the MAintenance is different, they dont hv anyproblem if equipment number is same. Otherway they wll have the added advantage that they can continue with there own Equipment no which can be same in differnt Plant.
e.g 800TONPRESS - Plant1
800TONPRESS - Plant 2.
With best regards,
Narendra Dere -
Single excise registraction to two excise registration with same company code
Dear all,
Our customer is using single excise registraction now with three plants and one company code and doing STO between the plants with shipping (641/101). We have implemented SAP with the above scenario. (SAP ECC 6.4 implementation with TAXINN procedure)
Now, the excise registraction is splitted into two, out of three plants, two plant comes under one excise registration and remaining one plant comes under another registration.still all the three plants are under the same company code only.
Need your help on what are all the changes interms of process and configurations
Earlier response will be highly appriciated
Reg
SridharanHI Sridhar,
You have to define customer, vendor option but without account aspect.
Following are the steps in STO between a plant ( seperate Excisable units)
You will create an STO ( Purchase order from Receiving plant)
1: Create Delivery and excise invoice on the basis of performa invoice ( in performa invocie no accounting entry) Excise register will be updated on the basis of this not account entry would be as below:
Delivery: ( movement type 641)
Stock at receiving plant Dr to
Stock at Sending palnt
You would be following standard cost incase of SFG and FG. so materail valuation would on same basis and there may be valuation difference.
Excsie invoice generation:
Excise Clearing account Dr To
Excise Duty payable
Excise Duty Cess Payable
Excsie Duty hCess Payable
At receiving palnt you would receive material through MIGO no account entry will be generated only physical receepi of material.
Capture the excise in J1iex wrt to excsie challan.
Hope the process will help you.
Regards
Pankaj -
Transfer of Inventory from One Plant to another with in the same company code
Hello All,
Can you please let us the possible option's for transfer of Inventory from one plant to another plant in different geographical location with in the same state.PLANT TO PLANT TRANSFER IN THE DIFFERENT GEOGRAPHICAL LOCATION UNDER THE SAME COMPANY CODE
Assume - plant 1 - 1000 ; plant 2 - 2000.
From 1000 - 2000 u shall transfer the parts using 641 movement By creating a Stock transfer order with the following conditions.
1, Master & source list to be extended for both the plants vice versa. including accounting & excise view
2. Create an Sto po in ME21n for one time only /ME31N as scheduling agreement
3. Generate pick list and do Post goods issue in va02.
4. Create excise invoice & do the Gate entry in the other plant & stocks are up loaded.
5. In India excise rules are becoming stingent & you have to inform both the Excise ranges before starting the transactions -
MM STO between Plants under the same company code
Hi experts,
Please guide on the configuration steps for doing STO between Plants unders the same company code.
We have company code 100 in that Plants A B & C are theie. Each Plant can do STO to other Plant.
How to configure this scenario?Dear,
Please follow bellow path
1. Create a vendor for the Company code of the receiving plant using account group 0007 via T-Code XK01.
2. In the purchasing data view assign the supplying plant and the schema group
3. Create customer with the sales area of the vendor.
4. The shipping conditions, the delivering plant and the transportation zone determine the route in the STO.
5. In the pricing procedure determination relevant to the STO assign document pricing procedure and customer pricing procedure to get the pricing in the invoice.
6. Maintain condition records for pricing condition.
7. Maintain carrier as a partner in the customer master.
8. In OMGN select the supplying plant and assign the company code and sales area. Similarly select the receiving plant and assign the company code and sales area (The company code to which the plant is assigned to).
9. Assign the delivery type and checking rule to the document type.
10. And finally, assign the purchasing document type to the supplying plant and the receiving plant.
11. Create the STO using T-Code ME 21N and save.
12. Check for release strategy if any and release using T-Code ME 28.
13. Create delivery in background using VL10G.
14. If delivery is created, it is an indication of correct configuration and master data creation.
Stock transfer between two plants in different company codes is known as inter company stock transfer.
Material should be maintained in both supplying and receiving plant MM01
Stock should maintain only in supplying plant MB1C
Create receiving plant as a customer in supplying plants company code and sales area XD01
Assign this customer number in receiving plant details OMGN
Assign supplying sales area in supplying plant details OMGN
Assign delivery type NB for in combination of supplying/ receiving plants.
Create STO ME21N
As it is normal there in the item details we should get shipping date i.e. customer number
Go for Delivery VL10B
Shipping point *****
Select PO go for execute
then select the delivery then go for delvy ............create delvy,,,, delvy number generated.
Goods Issue VL02
Delvy doc **********
Click on picking
enter the picking qty
Click on PGI
in the mean time check in the PO history you will get the details
Goods receipt MIGO
Stock transfers that include deliveries and billing documents/invoices are only possible between plants belonging to different company codes.
If you want to carry out a cross-company-code stock transport order with delivery but without a billing document, you must set the Relevant for Billing (data element FKREL) indicator in Customizing of the item type to "blank" (Not relevant for billing).
The following applications are involved in this type of stock transfer:
? Purchasing (MM-PUR) in entering the order
? Shipping (LE-SHP) in making the delivery from the issuing plant
? Billing (SD-BIL) in creating the billing document for the delivery
? Inventory Management (MM-IM) at goods receipt in the receiving plant
Invoice Verification (MM-IV) at invoice receipt in the receiving
Transfer of goods from one location to another location, it may be between plants within the same company code or in different company code's plants.
within the company code, but plants,
receiving plant will raise the STO in Supplying/issuing plant-ME21n,
Supplying plant will deliver the goods to receiving plants ,
then we need to pick n post the Goods Issue-VL02n,
now when we can observe that the STO qty will be added into receiving plant and reduced in Delivering plant,
To do this, we need do prior customization in SPRO-IMG,-
material should be created in both plants( receiving & Supplying)
-maintain the stock only in supplying plant
-create a dummy customer in supplying plant's sales area(if u have one sales area, create in tat comp code n sales area)
-assign this customer number to receiving plant's details along with the sales area,
-Assign the STO doc type(UB) to Supplying plant, along with checking rule
-Assign the Del type (NL/NLCC) to Supplying n receiving plant.
Stock Transport Order:
http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b911d43ad11d189410000e829fbbd/content.htm
http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b917843ad11d189410000e829fbbd/content.htm
http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b918543ad11d189410000e829fbbd/content.htm
u can also use the SAP building block
with delivery
http://help.sap.com/bestpractices/BBLibrary/html/P36_IntStockTransDel_EN_IN.htm
without delivery
http://help.sap.com/bestpractices/BBLibrary/html/P38_IntStockTransWithoutDel_EN_IN.htm
Regards,
Mahesh Wagh -
STO not working for plants of same company code assigned to a Purchase Org
We have two company code ( A & B ) assigned to a single Purchase Org .
when we are trying to do STO of company code A , we are getting an error message like that
The plant you have entered does not belong to the company code that was
determined via the purchasing organization.
Any suggestion please. we assigned all the plants to the Purchase Org .
Thanks
JJHi,
While creating STO you are entering the plant.
Please check whether that Plant is assigned to the Company code A Error message clearly tells you have assigned the Plant to the company code A
G.Ganesh Kumar -
Stock Transfer Between two plants within same company code
Hello,
We are using scenario-'Stock transfer between two plants within same company code. Scenaro is like Plant A is receving plant and Plant B is delivering Plant.
Plant A release PO for 100 nos to Plant B
Plant B issues 100 nos (via delivery) to Plant A
But Plant A receives only 50 nos physically so they do Goods receipt for 50 nos , but document got generated for 100 nos (when plant B issues material).
Now Plant A do not want to receive remaining 50 nos physically, but wants to reduce material document which got created when goods issue posted by plant B
Now stock in transis (mb5t) is 50 nos.
How to reduce this material document. or any another alternative solution for this?
Thanks,
ShaileshHi There
Reversal of partial is not possible ,
But you can use the Mov Type 557 and 558 to do the adjustments in Stock in transit qty
Few more details on STO adjustments
Hi There
it can be settle in many ways,,,
1. Receive the goods as 100 and Scrap the 50 nos from the received plant,,- If the receiving plant is responsible
2.Revert the PGI/Transfer movement(Vl09) and send the 50 nos again from the supplying plant- of the Supplying plant is responsible,
3.Also we have the movement type 557 and 558 without doing the above two steps you can correct the qty from stock in transit itself,,
4. also you can check the below similar thread
STO - material lost during tranfer from plant A to plant B
5. If above are not ok, then receive the goods as 100, And raise the STO as your plant as supplying plant and receiving plant is (Supplied 50 nos less) plant,, Do the process without sending the material.. in this way that 50 nos can be adjusted,,
6.Here is some more details
557 Issue from stock in transit (adjustment posting)
Only use this movement type (also the reversal movement type) under the following circumstances:
Using movement type 557, you can correct purchase-order-independent stock in transit if
- a good receipt cannot be posted to a purchase order without stock in transit, even though there is still stock in transit according to the purchase order history
- stock in transit still exists, even though there are no open stock transfer orders for the particular material
This movement type may ONLY be used in the cases mentioned above after careful analysis, to correct stock in transit that has rounding errors.
This movement type may not be copied.
Note!
Before using this movement type, note the following:
- 392205 Analysis stock in transit / Correction if split valuation
Possible special stock indicators:
E, Q
7. As previous post says if you have the note for this issue you can use that also
You can use any one of the way to solve the issue, Hope it helps
Cheers
Senthil P -
Stock transfer order between 2 plants in same company code
Dear All,
We have the requirement, where in the stock tranfer order (between 2 plants in same company code) instead of Material valuation price, MAP/Standard (depends on Price Control) gets picked up from supplying plant ,user should be able to enter its own price while creating stock transfer order.
For fullfilling this requirement, I have created new condition type(where i have changed condition category from internal price "G" to "H" - Basic Price)
Instead of using condition type- P101 in the stock transfer pricing,I have used above created new condition type, in pricing procedure then also while doing the post good issue against the outbound delivery( move type-"641", moving average is getting picked up.
Can you please tell,where is the setting where we can make the system to consider manual given price while creating the stock transfer order instead of picking moving average price.
Its very Important requirement ,please Provide valuable Inputs else provide some alternative.
Thanks & Regards
Nitin ChhabraStock Transfer Order between Plants in the same Company Cpde are not relevant for pricing, as there is no billing. Billing only takes place between company codes. As same company code it would be like selling something to yourself - it doesn't make sense. The stock value in the receiving Plant depends on the price contol there. If standard price, then you must enter the price when creating the material or use material revaluation to change it. When you transfer the material from the issuing plant, the value there will be transferred. In case of standard price any difference is posted to stock transfer differences. If using MAP then the value will be transferred from the issuing Plant in full.
If you use costing with standard price in main plant, then it is possible that you can transfer the cost from the main plant to the second plant, by using special procurement key for costing.
Rgds
Richard -
Restrict PO creation for multiple plants for same company code
Hi Gurus,
We want to restrict PO creation for multiple plants in the same company code. Based on Standard SAP settings for Purchasing organization assignment with multiple Plant and multiple Plant assignment with single company code, this is happening. Is there a way that we can restrict by doing some customization change.
Any thoughts or ideas will be highly appreciating.
Thanks and Best regards,
Karun KumarHi,
Said functionality is not available in SAP standard.
To avoid the same ,i can suggest implement release strategy for PO,and then higher authority / commercial team can check created PO,if multiple plants available in single po then they have the option of rejection for the same.
Or else check BADI-ME_PROCESS_PO_CUST,take the help from abapor and apply the restriction to select multiple plant in PO.
Hope this will resolve your query,
Thanks & Regards,
Sandesh Sawant -
Different plants at different country in same company code
Dear Experts,
My clients require to define another plant which is located at Italy should be in same company code (currancy type inr) having already 8 plants. Is it possible to configure the same.
Pls give some focus on it
Thanks.
Regards
Atul ZodAny Replies.........................
Atul -
Can we give same Excise Group to two diff. Plant within same company code
Hi,
Can anyone please tell that whether we can assign same Excise Group to two different plants within the same company code in SAP.
Regards,Yes you can use but, you shouldn't use same excise group for two different plants in one company code, if their physical location is different.
As many excise report are fetched on the basis of excise group, there it will show combined values for both plants, whcih may not be acceptable to exices authorities.
Regards,
Sachendra Singh -
Restrict proforma invoice without doing pgi in STO(same company code)
Hi Gurus',
I am creating STO (same company code) from Exciseable Plant to Non Exciseable Plant.
For that i am creating ME21N> VL10B>VL02N(PICKING & PGI)>VF01(Proforma Invoice)>J1IIN>
Now problem arises ---
I am able to create Proforma Invoice without doing PGI.
Now i want to restrict proforma invoice creation with out doing PGI.
What config require for this.
Regards
SantanuCheck your copy controls fromT. Code: VTFL - Copy-Control Settings b/w Delivery-to-Pro forma say, F8 -- LF
Settings at Header for the combination equal copying requirements 003 Header/dlv.-related and at Item category copying requirements 004 Deliv-related item
Maybe you are looking for
-
Os upprade 5.8 to 5.9 - big deal?
Is the OS upgrade from 5.8 to 5.9 a big deal? I would think not (maybe just patches), but would like your input. Thanks!
-
Does anyone know how to cancel a newspaper subscription i downloaded on my ipad now that my ipad is not working? Can this be done via my computer?
-
Apache Plugin in linux for WLS6.0 sp1 and (?sp2?)
This message is a little long, The following message is arranged in 4 parts where: 1. Conclusion and Sugestions. 2. Tests Environment 3. Simple plugin environment 4. Virtual Hosting with apache Any comment and help will be welcome Conclusion The plug
-
Urgent Tricky problem... I challenge you all....
I'm working on a very cool freeware Java text editor, that is working beautifully, except for the code used to change the color of reserved words, etc, on the fly... At the moment, I use a documentlistener. When text is inserted, I need to color some
-
Nokia Lumia 730 Dual Touch with Nail
Hi, I purchased Lumia 730 Dual Sim but my touch is not wokring with Nail but its working with Gloves. I read on many sites that Lumia 730 has super sensitive touch which works with Nail and Gloves. Please tell me that your Lumia 730's touch is workin