STO or PO for multiple line items and multiple destinations

I am working in retail enviornment and I have folloowing two questions:
1- we need to push articles( materials) to approx 1400store- we need to create STO with approx 10 line items and send materails to 1400 stores- this happens several times a year.
what is the easiest way to create this document without having to create either 1400 documents or create one  document for all stores and enter 14000 lines? (Sames items/ and qty going to all stores)
2- We also have to send approx 600 items to one or two stores at a time ( when a new store is opened)- these items are same.
Is there a way to create this STO/ PO and keep reusing this document again and again withoiut entering 600 line items everytime this requirement comes up ( this requirements comes up anywhere from 10 times per year to 50 times/yr
Does anyone have any idea on how to simplyfy this process. Any help/ idea would be of great help.
Thanks
Raj

A PO once entered can be copied in ME21N, by drag-n-drop into the shopping cart.  The problem might be changing delivery dates and delivery plants.
Another option is to use BOMs.

Similar Messages

  • Cash Discount Calculated for One Line Item and not for Other

    Hi All,
    We have devloped a Z program which is used to Write of InterCompany AR and AP recon Account to another GL Account. In this program to clear line item we have created a BDC which calls t-code FB05. Thsi program is running perfectly fine for all company codes.
    There is new company code SG20 for which it is not clearing the line items. It has created a Session in SM35, when we analysed the seesin we found that for some line items system is calculating Cash Discount and for some other line items it is not but the payment Term is same for all the douments with 3% 14days.
    I need your help in understanding that why for some line items system calculates the Cash Discout where as for others it is not calculation..also the Posting Date is same for all the documents.
    Please advise what could be the reson for this.
    Thanks!
    Regards,
    VIvek Srivastava

    Hi
    Cash discount is calculated based on the combination of baseline date and payment term conditions.
    Hence please check the baseline date for all the documents, in which the cash discount is not appearing.
    In your case, the possible reasons could be that 1) baseline date is different between these documents or 2) payment terms cash % is manually modified in the line item of the documents.
    Regards

  • GR Printing For Single Line Item With Multiple Account Assignment.

    Hi All,
    There is PO for projects (Account Assignment -P - Network) in which in a single item consist of multiple account assignment.
    Noe while entering the GR I select "Collective Slip" option but when the GR is posted system automatically select option "Individual slip" and seprate line item are printed for each account assignment.
    The printing program is standard SAPM07DR. The SAP version is 4.7. Can anyone tell what is ther any setting in configuration or is it problem in program or smart form
    Thanks & Regards,
    Omkar

    hi
    please check your form and routine used to print.

  • Multiple Service Entry Sheet For PO Line Items and One GR Document

    Dear All,
    We have just migrated from ECC 5.0 System to ECC 6.0 System. We are facing a problem while processing service entry sheets and the GR against them. The scenario is:
    1. We create a maintenance plan
    2. Upon saving the Maintenance Plan, a Purchase Requisition (PR) is generated
    3. The PR's are combined into one Purchase Order
    4. Against the Purchase Orders, multiple service entry sheets are created
    In ECC 5.0 System, we used to accept the service entry sheets and only one material document used to get generated as GR document. But now in ECC 6.0, we observe that with the same configuration, individual material documents are getting generated for individual service entry sheets. Is there a configuration in ECC 5.0, that enables clubbing of service entry sheet items in one GR document?
    Your help will be sincerely appreciated.
    Thanks and Sincere Regards,
    Amitabha

    Hi,
    If this can be of help I can report the list of the programs that                    
    are executed:                                                                               
    Before the popup "FUNCTION POPUP_TO_CONFIRM_STEP" appeares in ML81N,                          
    following programs are executed:                                                                               
    5  FUNCTION POPUP_TO_CONFIRM_STEP SAPLSPO1                                           
    4  FORM SELECTION_CHANGED_PO SAPLMLSR                                                
    3  FORM FCODE_SEL_PO SAPLMLSR                                                        
    2  FORM FCODE SAPLMLSR                                                               
    1  MODULE (PAI) FCODE SAPLMLSR                                                                               
    Unfortunately at this time it is not planned to change the current                   
    functionality.
    Regards,
    Edit

  • Single/ Consolidated  GR/IR entry for a PO having multiple line items

    Hi,
    In a PO there are couple of line items for materials of similar type and class. While making the Goods Receipt, the Accounting Document is making two no of line items for GR/IR accounts as credit and two no of inventory accounts as debit. Same is happening to GR/IR account while making Invoice Receipt document also.
    Informatively, both the materials above have been assigned to one GR/IR account in the OBYC table.
    My question is, is it possible to consolidate the value of both these materials and post one line item for GR/IR account. This is required as in our case in a PO, normally, we do have multiple line items and hence it is resulting multiple no of GR/IR and inventory accounts in a single accounting document. As we are getting details of the line item from PO history, we do not require it in the accounting document.
    Requested to kindly help.
    Regards
    B.Mohanty

    Hi
    This is not possible (you will compleet los the link between the Invoice and GR)
    The reason is that when you receive an invoice that this is based on a G/R line and the way arround when you receive first the invoice(s).
    The system need this for the automatecly clearing from the  G/R - I/R account, that is based on PO an PO line item number.

  • To make service entry sheet for multiple line items of the service PO.

    Hello MM Gurus,
    Please help me for the following
    I create a service PO with say 10 line items. Then while doing the service entry sheet the system automatically picks the line item 10 by default. When I try to enter the other items it throws an error" unplanned services cannot be entered"
    So how to make a service entry sheet which shall include all the line items of the service PO at the same time.
    So if I have 100 items in the PO do we make the service entry sheet 100 times against each item? Is there any seeting/solution on this?
    Please help.
    Regards,
    Prasanna.

    Dear,
    I have two solution for u.
    1) Create different service entry sheet -ML81N for each line item and create single invoice verification for all service entry sheet - MIRO
    2) Create service purchase order - ME21N for only one line item.
    And include all services in service tab available at item detail level of service purchase order. Enter it's quantity and rate.
    Than create one service entry sheet for purchase order.
    So you can create one service entry sheet for all line item of services.
    Note: - Use option 2 for easy process.
    Regards,
    Mahesh Wagh.

  • Difference in amount in sales order and billing for one line item

    Hi experts,
    User created one sales order with three line items say line item10, line item20
    Line item 30.Line item 10 value is 5024.26 EUR in sales order. He did delivery for three line item and invoiced. But the problem is that the line item 10 value is changed i.e. 5024.28 EUR in Billing and the remaining line item values are correct. All the line items having same item category.
    I asked the user to cancel the invoice and PGI. He did that. And again he created the PGI and Invoice. But the value of line item 10 become 5024.27 EUR and again he cancels the invoice and the PGI. and again he created the PGI and Invoice. Now the value of line item 10 is correct i.e. 5024.26EUR in invoice.
    Note: No changes are carried out from sales order to billing and even in material also.
              I checked copy control settings also all are correct.

    Is the Item Category of that item different from the rest. If yes for that item probably pricing is redetermined. However if its the same somebody might have changed it manually.
    If all the item have same category then it is possible that repricing is carried out for all the items however it found new condition record only for that perticular item.
    Rings a bell ?
    Regars

  • Amount Difference in sales order and billing for one line item

    Hi experts,
    User created one sales order with three line items say line item10, line item20
    Line item 30.Line item 10 value is 5024.26 EUR in sales order. He did delivery for three line item and invoiced. But the problem is that the line item 10 value is changed i.e. 5024.28 EUR in Billing and the remaining line item values are correct. All the line items having same item category.
    I asked the user to cancel the invoice and PGI. He did that. And again he created the PGI and Invoice. But the value of line item 10 become 5024.27 EUR and again he cancels the invoice and the PGI. and again he created the PGI and Invoice. Now the value of line item 10 is correct i.e. 5024.26EUR in invoice.
    Note: No changes are carried out from sales order to billing and even in material also.
              I checked copy control settings also all are correct.

    Hi
    I think this is standard SAP issue of rounding the condition records at item level. Can you please share the netvalue for all the three items and the header net value at sales order and invoice level.
    kind regards
    sandeep

  • Can it not possible that i can retrive it for all line items in a single qu

    I have to make report for my application in which I am facing a following problem:
    In the application there are multiple suppliers and each supplier having multiple line items and each item having multipale events. each evant having three status GREEN,RED and BLUE.
    When a user select 'all suppliers' to show the the status time span for a supplier (i.e. for a supplier how many parts and upto how much time parts are in blue, red and green status)
    to show the cumulative status time span I have to find out a event for each line item which is having nearest lower entry time from the lower part of the given time span.for this i have write following query
    SELECT * FROM parts_events
    WHERE vendorid = ? AND partid = ?
    AND visible = 'visible' AND active = 1
    AND entrytime = (SELECT MAX(entrytime) as
    entrytime from parts_events
    WHERE vendorid = ?
    AND partid = ?
    AND entrytime < ?
    AND visible = 'visible'
    AND active = 1)
    the problem is that i have to fire this query for each line item, can it not possible that i can retrive it for all line items in a single query?

    maybe if you can post some sample data and output will help us analyze more youre requirement.

  • PO multiple line items -multiple currency

    Hi,
    I had one issue.
    Can I create PO with multiple line items ,with multiple currency ?
    E.g 2 line items one line item with INR and second with USD.
    I tried I am not able to create PO , But its allowing to create the same for Scheduling agreement and Contracts.
    E.g I create a Contract with two line items.
         one line item with INR and second with USD.
        But the Header Currency is fix  either INR or USD whatever u select before creating the contract remanins same and cannot be changed later.
    Q :Is this correct ?
    Q: what will contract vaule in this case in USD or INR .
    Please see if u can add some in puts.
    Thank you
    Regards
    Amar

    Amar,
    You can create a PO with multiple line item, but you can not create the PO with multiple currency.
    Regards,
    Manish

  • Secatt Recording Multiple line items

    Hi all,
    Iam new to secatt.
    Iam having couple of doubts:
    1) We having the scenerios :Creating  script for Purchase,Order. P.O had multiple line item's.I want to creat the script for P.O ,that should work for all line items,each line items had deliery schedule date's
    (The scripts should work for Multiple line items and schedule dates )
    2) How to link the transactions
    ( Eg: In one scripts : creating P.O > Gr Migo > invoice )
    Is it possible?.If its possible pls guide me.I would appriciate, If any input.
    Regards,
    Hareesha k

    Hi Hareesha,
        I don't have any document particularly to this but you can refer to SAP standard eCATT documentation on http://help.sap.com/saphelp_erp2004/helpdata/en/1b/e81c3b84e65e7be10000000a11402f/frameset.htm.
    In case of any specific doubts you can write to me. I am also working on eCATTs.
    Best regards,
    Deepthi

  • Pass Idoc PO Multiple Line Items to file

    Hello All,
    we are using Message Type ORDERS and ORDERS1 as Basic type to pass PO and sales data. I have configured IDOC to File scenario. I'm able to successfully place a file in file folder.
    But my issue is some of the PO's have multiple line items and saved file has one first line item information. I have even tried unbounded for line item but no luck.
    <b>How do I pass all the line item values to the file ?.</b>
    The output structure should be
    1. PO Number
    2. PO ITem
    3. Material No
    4. Delivery Date
    5. Vendor Number
    the data type I created is
    Pur_Ord
    |__ EBELN
    |__ EBELP  0..Unbounded
    |__ MATNR
    |__ AEDAT
    |__ LIFNR
    the current output is
    <?xml version="1.0" encoding="UTF-8"?>
    <ns0:Pur_Ord_Out xmlns:ns0="http://PO_TO_FILE">
      <EBELN>0004500066</EBELN>
      <EBELP>00001</EBELP>
      <MATNR>000000000000010027</MATNR>
      <AEDAT>20051215</AEDAT>
      <LIFNR>0001005780</LIFNR>
    </ns0:Pur_Ord_Out>
    Im looking for an output with all line items
    Thanks in advance
    Praveen

    Praveen
    Try this
    Pur_Ord
    |__ ORDERS 0.. Unbounded
      |__ EBELN
      |__ EBELP
      |__ MATNR
      |__ AEDAT
      |__ LIFNR
    Here ORDERS is the parent node.
    KK
    Message was edited by: KK

  • Header Details to be Printed only for the line item details.

    Hi All,
    I have the following requirement.
    I have Page1 with the Logo, Header Window, Vendor Window, Send Invoice To, Delivere Invoice To and Main Window. Main Window Starts from the middle of the page. In the Page2 i have Logo, Header window and Main Window. In the Page3 i have only Main Window.
    In the Footer of the Main Window i have Placed the Terms and conditions which should always be Printed in the New Page. So in the footer i have given a command "Go to New Page " and given the page as Page3.
    The requirement is Logo,and Header Window should appear only for the Line items and not for the Terms and conditions.
    For the Page1 i have given the Next Page as Page2. Suppose if there is only one line item then it Prints in the first Page itslef and the control flows to the Page2 and since in the page2 i have given the condition for the Logo and header window to print only if line item is more than 1 and since Main Window is starting from the middle there is a blank Space appearing in the start of the page.
    The command i have given in the footer to trigger new page that is page3 is not getting triggered. If there are more than one line item then its printing the logo and header window and so there is no blank space appearing and it is working fine.
    Please let me know how to avoid this blank space and move my main window to the start of the Page if there is only one line item.
    Thank you.

    Dear Vasudha,
    I am a little bit confused regarding your query,
    "In the Footer of the Main Window i have Placed the Terms and conditions which should always be Printed in the New Page. So in the footer i have given a command "Go to New Page " and given the page as Page3. "
    When you say footer of main window does it mean , that you are using a table inside your main window and the command node your have inserted is in the footer of the table ?.I hope it is, because my suggestion is based on this assumption.
    Well my suggestion for your issue is,
    1.I  hope you are aware we can trigger a next page in two ways, one by setting the next page static attribute & second using  the command node which you have used.In your case you will have to use a combination of both.
    2.I feel your First page design is ok. Set its static next page attribute to PAGE2. Similarly set the static next page attribute for PAGE2 as PAGE2 itself. This should take care of your table which you have placed in the main window. If the table contains only one lineitem it will get over in the first page itself. If the lineitems are more in the table, it will automatically triggerPAGE2 (since static next page attribute for PAGE1 is PAGE2)  and the remaining line items will be displayed. Now no matter how many lineitems you have ,PAGE2 will be triggered repeatedly(since static next page for PAGE2 is PAGE2 itself) until the entire data in your table is displayed.
    In this way your requirement of printing the logo and header windows for the data lineitems only will be fulfilled.
    3.Now the last catch in your case is the printing of PAGE3(The terms and condition page) on an entirely new blank page.
       In the footer section of the table which you have used,  use a command node set to PAGE3.  After the command node and under the same  footer section now insert your terms and condition lineitem.
    Also Check the "at End of table" checkbox and uncheck " AT PAGE BREAK" under OUTPUT OPTIONS tab for the footer section.
    So now this footer section will be triggered only once after all the data in the table is displayed
    4. So now if there is only one lineitem, before the default second page is triggered the command node will trigger the PAGE3 and the terms and condition will be displayed.Else if there are more lineitems the page2 will be triggered again and again and finally when all the lineitems are over, the footer of the table will get triggered. So the command node will take you to the PAGE3 wherin the terms and condition will only be displayed.
    Hope this helps.
    Regards,
    Riju

  • URGENT: Multiple line items in delivery document created for a STO

    Hi Gurus,
    We ar ecreating deliveries using VL10b for a STO. Teh TSO has 40 - 50 line items. But the delivery is created with one line item only an dit creates a delivery for each line item. How cna we allow the inclusion of multiple line items in delivery?
    We are using delivery type NL an ditem categor is NLN.
    Geratly appreciate any help in that.
    Thanks,
    KHAN

    Hi Gianpaolo,
    Thanks for your suggestion I have 5 shedule line itmes for one material and two shedule line for another material and when i changed the material by selecting one line for each sales document no and creates the delivery it is howing three line itmes for the 1st material and line items for the second and quantities equal to the changed quantity in VL02N. and I have value "1" in field "Split per sched.line" in "user role" view of VL10E.
    Kindly help.
    Thanks and Regards
    Tanweer

  • URGENT: Delivery with multiple line items for a STO

    Hi Gurus,
    We ar ecreating deliveries using VL10b for a STO. Teh TSO has 40 - 50 line items. But the delivery is created with one line item only an dit creates a delivery for each line item. How cna we allow the inclusion of multiple line items in delivery?
    We are using delivery type NL an ditem categor is NLN.
    Geratly appreciate any help in that.
    Thanks,
    KHAN

    The problem you face is called 'Delivery split'.
    For the STO scenario, one common cause is different delivery dates (in the past) in the STO line items. If so, then you should refer to SAP Note 377501 (from where I quote below):
    You can implement the source code specified in the correction instructions in copy routine 301 (or a copy of this routine in the customer namespace). This correction ensures that when you transfer data form the preceding document, backlogged delivery dates or goods issue dates are set to the current date. This prevents the system form performing a delivery split.
    Then a rescheduling of the delivery occurs. Since forward scheduling occurs for backlogged delivery items (that is, the picking date or the transportation planning date is set to the current date), the manipulation of the delivery date or goods issue date in the copy routine does not affect the result of the scheduling.
    If the dates are not the problem, then this Note refers to other Notes which deal with this problem, and should definitely solve your problem.
    Regards
    Nikhilesh