STO picking standard price though the pirce control in Mat Master is V

Hi All,
I have for a certain material while creating STO, always the standard price is being picked up through pricing condition into STO though moving average price is defined in te materil master.  Can somebody throw a light on the issue? Thanks
Sravan

Hi,
please check the Condition in M/06 in that see the condition category what it is maintained.
0      Charges - condition recor
1     Tax JurDic level 1 (with l
2     Tax JurDic level 2
3     Tax JurDic level 3
4     Tax JurDic level 4
5     Customer reserve 5
6     Customer reserve 6
7     Customer reserve 7
8     Customer reserve 8
9     Customer reserve 9
A     Packaging
B     Delivery costs
C     Insurance
D     Tax
E     Cash discount
F     Freight
G     Internal price
H     Basic price
I     Price for intercompany bil
J     Customer expected price /
K     Base amount excluding tax
L     Generally new when copying
M     Sales tax w/license-checki
N     Input Tax not Deductible
O     Variants
P     Base amount including tax
Q     Costing
R     Invoice list condition
S     Standard cost
T     Moving cost
So just check whether "S" indicator is there
Regards
Amey

Similar Messages

  • Finished Goods valued at Future Standard price at the time of Delivery .

    Hi,
    My client requires the Finished Goods to be valued at Future Standard price at the time of delivery from Production order. This is required because in case there are frequent changes in the material prices, i can mark my material several times.. and change the future standard price.
    I have checked and found that it is always valued at Current standard price only.. and not at the future standard price.
    1) i have tested by changing the costing variant in OPL1 ( Planned costing variant for Production orders).. such that the valuation variant picks up the Future price... it seems it will work only for the Raw materials and SFG's consumed in the Production order and not for the Finished goods.
    2. Define valuation variant for Goods received option in the IMG - It seems it is relevant only when your FG is valued at Moving average price only.. so not relevant for my case.
    My question :
    Can i value my Finished goods at future standard price ( i.e Marked standard cost estimate ) at the time of receiving goods from Production order ? If yes how ?
    Thanks in advance for your answers.
    Njoy
    Siva

    Hi Siva
    It is very much possible, but you need to use exit... I think exit COPCP002 should be the relevant....
    Usually, this is used to valuate the GR in case of Valuated sales order stock... I guess this should work in MTS also...
    The reason why I feel it should be possble, is that if you read SAP text for the IMG Step Define Goods Received Valuation for Order Delivery, it says at the end
    For materials with price control S, on the other hand, the credit posting is always made at standard price.
    If you deliver to stock at a price that is not the standard price, the system will report an output price variance in variance calculation
    Hence, it should be very much possible to achieve what you want.. Only thing is it will hit a PPV and that you need to find relevant exit if the one abov does not work
    Regards
    Ajay M

  • How to enable the standard price in the accounting -1 view of material mast

    Hi,
    When i was trying to create a material of material Type: FERT, Iam unable to enter the price of the material in the accounting -1 view-> standard price.
    The field has been disabled.
    So please tell me how to enable the standard price.
    Regards,
    Rudra Prakash. S

    hi
    go to OMS2  double click FERT
    in valuation check which price control is allowed
    it should be std. price
    go to OMSR  check MBEW-STPRS  note field group
    in OMS9 for this group and material combination check whether that field is maintained as display
    Vishal...

  • How to download  Standard Price of the Previous Months

    Hi,
    I have a request to download the standard prices of the previous month.
    Below is the Example:
    Material A having the current standard price of $ 100 in Jan,2011 and $ 90 in Dec,2010.
    I can see the standard price of  $90 under Accounting View 1 against "Period 12.2010" Tab.
    I would like to know how can I download the previous month standard prices for the whole list of Materials using Tables or any standard Report.
    Pandu

    Hi Pandu,
    You can meet your requirement through SAP standard report. Find more details:
    Use t-code: S_P99_41000111 - Analyze/Compare Material Cost Estimates.
    Enter the below details in selction screen:
    Plant,
    Material................ To ................
    Costing Variant,
    Costing Date, Valid From (enter the range of dates. e.g. 01.10.2010 to 01.01.2011)
    Costing Status = FR (Released Without Errors).
    Execute the above selction.
    Check in your output layout/change the layout to get Costing date (Key), Costing Status. Material, Plant, etc.
    You will be able to view/download the current month & previous month standard prices.
    Thanks & Regards,
    ADI

  • Material Ledger  - release actual price as the standard price for the next-

    Hi Gurus, Sap Library /documentation about Material Ledger says:
    "At the end of the period, an actual price is calculated for each material based on the actual costs of the period. This actual price is called the periodic unit price and can be used to revaluate the inventory for the period to be closed. In addition, you can use this actual price as the standard price for the next period."
    How Can I do that?  i've calculated the new actual price but i could release it as a new standar costo.
    Kind Regards
    André

    Hi Both,
    I think there is something else to add to this, the new PUP price can only be applicable in the period N+2 where N=Period of closing. This is something that is not specifically mentions in SAP documents.(not that I know of ) but I found it the hard way!
    Cheers

  • Releasing the Standard price for the co product.

    Hi All,
    In my scenario , we have configure co product config and is that i have made the respective settings for the co - product in the material master with the joint production and the apportionment structure defined in the suitable ratio.. The cost estimate has been executed and the cost apportionment are resulted as per defined and it is perfect...
    But when i tried to release the standard price using CK24, the price of the main product (FERT) is getting updated in the material master whereas the price of the co- product (FERT) is not updating in the material master.  Is any settings has to be made from controlling aspect or settings in material master...
    regards,
    Mahesh

    Hi Mahesh,
    If you want to mark and release the non-leading co-product, you
    need to create a cost estimate for it seperately. Then goto CK24,
    the marking will be OK.
    Regards,declan

  • BAPI to change the standard price of the material

    Hello Friends ,
    I am struggling to find a BAPI to change material standard price. I found 2 BAPIs mentioned below. But was not able to make use of them.
    1) BAPI_MATVAL_PRICE_CHANGE
    2) BAPI_MATERIAL_SAVEDATA
    Can any of you help me in finding right BAPI?

    BAPI_MATVAL_PRICE_CHANGE
    PRICES_CHANGE & PRICES_POST
    BAPI_M_REVAL_CREATEPRICECHANGE
    BAPI_MATERIAL_SAVEDATA
    These are the fm's to save or change material price.

  • Is it possible for the posting COGS another price then standard price

    < MODERATOR:  Message locked.  Please post this message in the [Controlling forum|SAP ERP Financials - Controlling;. >
    Is it possible for the posting of the goods sold (delivery sales order) to use another price then the standard price when the price control of the material is S.

    Yes. Is it a third-party scenario?
    In a typical Third-Party sale (where the vendor delivers the goods directly to the customer, with no/notional GR in our books), the system uses the PO price and not the Std Price from MM.
    Cheers.

  • To update the standard price of a material

    Which transaction is used to update the standard price of a material

    Hi,
      Use the transaction CKMLPC to update the standard price of the material.
    Thanks,
    Naren

  • Process will not be created with zero standard prices in material master

    Hi,
    I have two type of material;
    1.     In process material say A1
    2.     Finished Goods say B1
    Both materials price control are standard price.  I do not run costing. So , after creation of material master , standerd price has to update through MR21 in the account1 tab before start production .
    Suppose, if I forget to update standard price in material master and prepared process order, it will carry zero value of production cost.
    Hence, I want to restrict the creation of process order with zero standard prices in the material master.
    In order words, as long as standard price will not be updated after creation of the material master, user will not be allowed to create process order, if wrongly try, system will give message u201Cwith zero standard price creation of process order will not be allowedu201D.
    Please let me know either standard configuration or name of User exit or Badi.
    Regards,
    Amit

    Hi,
    You need to use BADI: workorder_update.
    Method: At release.
    check MBEW-STPRS field in the code ..and flag error and reject error if STPRS = 0.
    Regards,
    Santosh Sarda

  • Material Master - Standard Price

    Please suggest - how to change(update) the "Standard Price" of the material in Accounting view of the Material Master ?

    Hi,
    (do reward if this is useful)
    Price Update:
    In the R/3 menu go to the screen view by the following path:
    Accounting-Controlling-Product Cost Controlling -
    Product Cost Planning MaterialCosting----
    Price update
         On the Price Update: Mark Standard Price Screen, choose Other Prices.
       The Other Price Update: Release Other Prices screen appears.
    Enter data to restrict the cost estimates whose results you want to copy to the Material master
    In the Update Prices in Material Master Record group box, set the Commercial Price 1 checkbox.
    Choose Execute (F8) to carry out the update.
    On the Price Update screen, the system provides a short log for the test run. The log contains green traffic lights and the message “Of 1 materials, 1 cost estimates were updated successfully.”
    Choose Back until you get to the Price Update: Release Other Prices selection screen.
    Use the same selection parameters as in the test run for the price release. Scroll down to the bottom of the screen. Deselect the Test Run indicator in the Processing Options group box.
    Update the prices in update mode and choose Back.
    Call up transaction MM03 and check that the prices have been updated in material master C10150.
    The lowest value is determined in inventory costing when the prices are updated in the material master record. The system compares the valuation price according to price control for the current period or previous period with the costing result. If the valuation price is lower, this price is updated, rather than the value determined in inventory costing, as the tax or commercial price.
    Result
    Commercial price 1 has been updated in the Accounting 1 view in the material master.
    <b><<<PLEASE REWARD POINTS IF THIS IS USEFUL>>>
    </b>
    Regards
    AK

  • MTO - get finished goods receipt to post at standard price?

    Hi
    I have a MTO process. The standard price of the FERT is 10 in the material master. The total of the BOM is 8.  When I goods receipt the finished product, it posts a value of 8, i.e. the calculated cost in the sales order.
    How do I get it to post at the standard price from the material master?

    Dear,
    In MTO sales order base manufacturing system do the valuation not on the basis of  standard price of product instead of the value of the valuated sales order as per standard SAP.
    Go to SPRO--Controlling -Product Cost Controlling Cost Object Controlling --Product Cost by Sales Order --Control of Sales-Order-Related Production/Product Cost by Sales Order --Check Requirement Classes:
    In your req class, Check from your planning strategy OPPS IF 20 the it is KE
    Use Acct assignment category M
    Valuation indicator as A
    W/o Val strategy X (Check) But F1 and read the deatils
    You can use this customer exit COPCP002 to do the valuation on the standard price. Also refer OSS  Note 557582 - User exit and valuated sales order stock
    Hope clear to you.
    Regards,
    R.Brahmankar

  • A Function or BAPI to get Material Standard Price?

    Hi All,
    I need a Function or BAPI to get the Material Standard Price when the following Criteria is given;
    1. Material Code
    2. Plant
    3. Period
    4. Year
    5. Company Currency (Optional)
    I need only the Standard Price and Price Unit. Please give me a example with sample values.
    Thanks,
    Kishan

    Sri:
    I need only the Standard Price and Price Unit
    there is no specific FM for that.
    you need to write small select query in FM than use this custom FM into your program.
    Amit.

  • Process order when standard price zero

    Hi Gurus,
      Is there any way to restrict the goods movement of the finished material (101 mvmt) for a process order when standard price for the same material has been maiantained ZERO.
    Thanks
    Anil

    I think you can restrict the confirmation if the costs are not correct..
    In OPK4 for your order type and plant combination, in the general individual entry tab, terminatef for incorrect costs...
    karthick

  • Accounting view:Moving avg price and standard price

    Dear Friends,
    Can anyone explain what for these two fiels are maintained?.....also what difference it makes with the price we maintain thru pricing procedure(considering only PR00)?......can both the prices be at the same value?......Thanks in advance

    hi
    The system calculates the moving average price automatically by dividing
    the material value in the stock account by the total of all storage
    location stocks in the plant concerned. It changes the price with each
    valuation-relevant movement.
    The system changes the periodic unit price if you settle the material
    ledger and then save the data.
    The valuation of stocks at moving average price or periodic unit price
    means that the price of the material is adapted to the continual
    fluctuations in the procurement price.
    Standard price
         Standard price of the material
    Use
         The valuation of material stocks at standard prices means that all goods
         movements are valuated at the same price over an extended period.
    Procedure
         Price variances (for example, purchase price higher than standard price)
         upon goods receipt or invoice receipt are posted by the system to price
         difference accounts. This does not affect the standard price.

Maybe you are looking for

  • Error while adding user after customizing form in 11gR2

    Hi Experts, I have worked on customizing my User view form. I followed steps as: Navigated to View user form--> clicked customize (top left) --> view --> source --> selected area --> clicked edit on popup box I made certain changes on labels names an

  • Videos no longer playback after upgrade to itunes 7

    Yesterday I upgraded to itunes V.7. Now none of my videos or video podcasts play. I Also upgraded my Ipod and none of the videos show up. The error messege when connecting my ipod is as follows "The video format is not supported on this ipod" All my

  • Backing up Zen MicroPhoto (8

    In reviewing all material that came with my new MicroPhoto (ZMP8GB) as well as reviewing this forum, I haven't found anything dealing with how to do a total backup of the Zen. I'd like to make a copy of the complete image of all my music and playlist

  • How to revert to iPhone OS 3.0

    I have an iPhone 3G 16 GB which I recently upgraded to OS 3.1. How can I revert to OS 3.01 or 3.0?