STOCK OF FINISHED PRODUCT BY PIR NOT CONSIDERING WHILE TAKING MRP RUN

DEAR SAPGURUS,
       I have finished product stock of 50 nos through planned independent requairement. now i am creating sales order for finished product but mrp run generate the planned order for finished product. I dont have planned order for finished product because material already have stock. what can i do please give solution.
thanks.
Regards
Atul

Hi Atul,
Please describe your problem better, it's not easy to understand...
Strategy 10 is net reqirement planning:
- SAP considers only PIRs as requirements, SOs are not considered
- SAP considers stock levels
- requirements should be LSF (check in MD04)
If you input sales order SAP won't create PldOrd for it. If you have stock and you want to create more to fulfil you SO, you have to input PIR accordingly and run MRP.
Please clarify your problem...in a way that we may understand it.
http://help.sap.com/saphelp_47x200/helpdata/en/60/9ea1536fbd11d191820000e8a5f6e6/frameset.htm
http://help.sap.com/saphelp_47x200/helpdata/en/e0/71bb199c9f11d191920000e8a5f6e6/frameset.htm
Thanks,
Csaba

Similar Messages

  • Process order should not take part in MRP run

    Hello Colleagues
    I looking for a way how to exclude not released process orders (we have PP-PI) from MD04 report. Not released process order should not take part in MRP run. I was trying to do it using OPJJ for availability check 02 and checking rule PP but I was not able to get result. Could you please help, probably there are other settings?
    Best Regards
    Eduard

    Hi,
    Settings in OPJJ will take effect only when you create or release process orders.
    As a work around you can try to exclude process order is
    1. Create a Storage location and make it not relevant for MRP-OMIR
    2. In Material master for the material in MRP assign storage location MRP as 1 (exclude storage location stock)
    3. Create the process order, in the GR tab enter the storage location (not MRP relevant)
    In the MRP run it will not take the process order into account.
    After releasing change the storage location to the normal sotrage location.
    In this process flow, the control is with the storage location.
    Check it in your sandbox.
    Thanks,
    JK

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • On Order Stock not considering while Replenishment planning in IS-Retail

    Hi SAP Gurus,
    I am running Replenishment planning in IS -Retail system, but it's not considering On order Stock (e.g  Purchase order - schedule receipts). could you please tell me the config where system can consider on order stock.
    Thanks in Advance.
    Sagar.

    Hi Mayank,
    I had already done the steps that you have mentioned. i.e. Changing the error processed records to
    "Not Processed" and running the initial load again, but it does not help as the exception still continue to be the same i.e. No Product or Location can be found in the database" whereas these details are already present in the system i.e.if you check /FRE/MASS_LOC or for product.
    After checking the help (F1) for TEMPRPFROM, it clearly specifies that if a date is mentioned in the field, it will activate the blocking on the date and if no value is present in the field, then the temporary blocking will not be enabled.
    Also, a surprising fact is that whenevr I transfer the product or location details on a particular date, the TEMPRPFROM reflects that particular date even in the interface tables. So wondering whether some customizing field is present in IS-Retail side which is causing this issue
    Best regards
    Prashant Kedare

  • Infotype 0008 wage types are not considered while payroll

    Hi Experts,
    When i am running the payroll, all the wage types of infotype 0008 is not considered. Neither it is being stored in RT. But all the wage types of infotype 0014 and 0015 are correctly being considered in the payroll. Plz help
    Regards
    Tarun

    Hi,
    Plz see the XVAL log that i am getting while running payroll. Do let me know if you need any other information. I can call you now if you say.
    PIT   XVAL P10            Valuate pay elements
        Input
            IT
    Table IT
    PCRlGr Wage salary type               WC  C1 C2 C3  Assign: AltPa  CA  BT Abs.
    Var s. Unit    Rate                      Number       Amount
    3      /806 Partial period factor 6   01
                             100,000.00
    3      2000 BASIC SALARY-NEW          01
                                                                      8,000.00
    3      3000 BUS DEDUCTION-HPL         01
                                                                      1,000.00-
    Processing
         /806 Partial period factor 6
    /806 Partial period factor 6
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   0        ADDWT *
    2000 BASIC SALARY-NEW
    2000 BASIC SALARY-NEW
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   1        ELIMI *
    XVAL      3   1        RESET RA
    XVAL      3   1        RTE=  /801
    XVAL      3   1        RESET *
    XVAL      3   1        MULTI RAA
    XVAL      3   1        AMT/KGENAU
    XVAL      3   1        ZERO= R
    XVAL      3   1        ADDWT *
    3000 BUS DEDUCTION-HPL
    3000 BUS DEDUCTION-HPL
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   0        ADDWT *
    Output
    IT
    Table IT
      PCRlGr Wage salary type               WC  C1 C2 C3  Assign: AltPa  CA  BT Abs.
      Var s. Unit    Rate                      Number       Amount
      3      /806 Partial period factor 6   01
                              100,000.00
      3      3000 BUS DEDUCTION-HPL         01
                                                                       1,000.00-

  • Plannned Delivery time not considered while calculating delivery date

    Hi PP Gurus,
    We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines
    It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.
    We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.
    Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?
    Thanks & Regards,
    Sandesh

    Hi Sandesh,
    Is this happening for particular materials or for all materials
    Couple of checks -
    1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..
    2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not
    Best Regards
    K.Madhu Kumar

  • Order reservation should not get planned in mrp run

    Hello friends,
    Actually for a finished material i have created one production order by CO01.Because of it for semi finished material system created order reservation.I dont have any stock of semi finished material.Now i want while running the mrp run system should not planned this Order reservation of semifinished material.For these in configuration of availability check (Scope of check T.C  OPJJ), I  made the settings that system should not consider reservation (i deactivated the tick for include reservation) and for include depend reservation , i selected Donot check.And all these settings i made in checking group 02 and checking rule PP.After doing all these settings than also system is considering the order reservation for semifinished material and generating the planned order for it.
    Do i need to do any other configurations?
    Thanking you guys in advance.

    Hi Jitendra,
    Checking Control (OPJJ) has no relation with MRP.It is useful in the case of Plan and Production / Process Order only to find out Missing part.
    Now come to MRP again.
    You have a choice of only 3 type of stocks to include or exclude them during MRP run while rest of the things like (PO,PR,Reservation etc are consider by default)
    Go to OPPQ and after selecting Plant go to Available Stock.You will find that options,
    - Stock in Transfer
    - Block Stock
    - Restricted Stock.
    And one more thing Reservation is not a available stock but its one kind requirement and if there is no stock then system will activate the Planning file entry and during next MRP run it will generate Planning proposal also.
    Regards,
    Dhaval

  • Did not propose PR during MRP run for raw mats

    Hi All,
    Please help us in our issue for MRP. I have created planned order for SFG(semi finished goods).
    Scenario:
    SFG Planned Order:  170,000,000 pcs
    raw mats A in MMBE: 1,110.546 with reservation: 656.017
    raw mats A PO to be GR'ed : 5,025.798 MTN
    BOM base quantity: 10,000 pcs
    raw mats A qty in BOM per 10,000 pcs : 3.709 MTN
    Info of raw mats A in material master:
    MRP Type: VB (manual reorder point planning)
    Reorder point: 1,950
    Lot size: EX (lot-for-lot order quantity)
    Maximum lot size: 3,850
    Manual computation:
    = 170,000,000/10,000
    = 17,000 * 3.709
    = 63,053 MTN (quantity of raw mats needed to produce 170 million pcs of SFG
    But then after the MRP run it does not propose any PR. Do we have to change any info in our raw mats A? Or change in the configuration?
    Thank you
    Jesielle

    Hi Jessille,
    The raw material A is set for reorder point planning,
    U already have a stock of 1100
    & a PO to be GRed for 5025
    & ur reorder point is 1950
    as the stock & PO fulfill your reorder point ,no requisition would be generated.
    When a material is set for reorder point planning dependent requirement from FG materials
    will not be considered. If you want the system to calculate the qty based on the dependent
    requirements you need to change the MRP type to PD, but before changing check why
    the material was set for reorder point planning.
    Regards
    Mithun

  • Demand not getting generated on MRP run.

    Hi All ,
    We have an trouble ticket. For a particular sales order , the user has run the MRP , but no planned order is generated . So she cannot convert the planned order to production order .
    When she tries to create a production order with T-code CO01 , She gets the error message ," Sales order does not allow Make to Order production"
    Diagnosis :- Sales order entered is not to be included in Make to Order Production.
    System response:- Account assignment can only be carried out with sales order created with requirement type for Make to Order production.
    Please note :- We have many other production orders running for the same material in the same plants for different sales order . There is no problem with them except this sales order.
    Following are the details for the material :-
    Planning strategy:- 25
    Procurement type :- E
    Kindly advise  . Thanking you.
    Kind Regards
    Ayaz A Khan

    Dear,
    Are you getting Message no. 61155?
    In particular, the above-mentioned error messages are displayed  if a planned order is not  assigned to a sales order but the sales order number or the sales order item is not yet known when the account assignment data of the planned order is checked.
    Check the requirement type in sale order and account assigment.
    Create a production order with T-code CO08 with reference to sales order.
    Then please refer this link,
    Sales order does not allow make-to-order production

  • Contract number is not being picked during MRP run

    Hi,
    I have a contract with vendor as V1.
    This contract is MRP revelant with source list maintained with MRP revelant.
    Source list maintained with vendor V1, contract and with fixed indicator and with MRP relevant indicator set.
    Step 1
    Now I am executing MRP, system is creating PR with contract vendor V1 as source of supply is V1 in source list.
    This step is OK.
    Step 2
    After this I am maintaining sub contracting vendor V2 in contract.
    Again I am executing MRP run, system is creating PR, but the PR is not picking the contract details.
    I am expecting this PR, which supposed to be created in this Step 2 should have vendor V2 as source of supply.
    Am I correct?
    Note: Source list is still having vendor as V1, same contract number, with fixed indicator and MRP relevent option set.
    Any input if process is OK or if some thing wrong is apprecited,
    Thanks
    Dipak

    Hi,
    Ok.
    I am following this  way -
    In ME32K, there is a delivery address button available is transaction tool bar, there I am maintaining the subtracting vendor number and enabling the SC vendor check option so that this vendor flows to PR which gets created during MRP run and comes to PR delivery address tab i.e., in vendor field as subcontracting vendor with SC vendor check option selected.
    Am I correct ?
    Thanks
    Dipak

  • LTP consider production version and not consider selection id for routing

    Dear guru.
    I run mrp long term planning for a material.
    The material have a production version linked to a specific bom and routing.
    In trx OPU5 I have defined that the planning scenario consider a specific selection id for routing  , this routing is different from the  routing of production version.
    The result is that for this material ltp donu2019t consider any routing and no evaluation activity is possible.
    Do you know a solution in order that for LTP the system donu2019t consider production version and instead only consider OPU5 settings ?
    Thanks for your interesting.

    Dear CONS SAP,
    Create a new planning scenario in T Code MS31 and then maintain the scheduling parameters for this planning scenario and
    assign this selection Id and then execute and check.
    Check and revert
    Regards
    Mangalraj.S

  • Re: STOC . not considered while running MRP

    Hi Experts,
    I having one doubt in the following scenario.
    Plant1000  needs 5 qty of  AB Material from 1001 , requiremnt given thro Stock transfer order ME21N. date :21.03.2008
    1001 is producing the goods based on PIR. Presently,  plant 1001 have stock qty of 10 Nos. as on 21.03.2008
    If I run the MRP , instead of considering the stock 10 nos.
    It's throwing new requiremnt of 5 Nos.
    Please guide me to sort out this issue.
    Thanking you
    Regards
    Chandru

    Hi,
    Alreday I have a PIR of 10 Qty in that production plant. Now i'm  rasing one  STOC from some other plant for 5 Nos.
    It should consider the PIR as like sale order consumption on PIR. Then it should throw the PLnd order for 5 Qty.
    Here tis is not happening, it's giving plnd order for 15 qty.
    Please guide me.
    Thanking you
    Regards
    Chandru

  • PR,s not getting generated after MRP run

    Dear All,
    I'm running MRP through MD51 for WBS element where RM's are attached to WBS.
    It is MTO scenario where no stocks of RM's are maintained. I have checked all relevant settings of Masters.
    After running MRP through MD51, system is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    Please suggest & help.
    Thanks in Advance.
    Shaiz

    Little confused on your statement
    System is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    I would like to Know, whether the FG is attached with WBS or RM?

  • PO item not appearing while taking GR

    Dear Gurus,
    While doing GR- PO one PO line item is not appearing.This is a repairs PO with acct-K and it is raised through P.R.This PO consist of 6 line items out of which GR has been done for all line items except 3 &4.Now while doing GR the 4th line item is coming but 3rd is not reflecting. Both line items are same except the description and the price, as it is uncoded PO.The release strt.is affecting if i am making changes to the 4th line item but no changes take place for the 3rd line item.
    Pls suggest.
    Regards,
    Prasad.

    Hi,
    First you checked that Po is released or not.
    2 Delivery date of po.
    3 any inbound delivery exist according to confirmation
    4 delivery completed indicator
    5 Goods already received
    6 Check authorization on MIGO screen by entering /nSU53 that all authorizations available.
    Thanx
    Reward if useful

  • CR4E "file not found" while trying to run CR project

    The only way I can run the .jsp file which calls my crystal report is by stopping Tomcat6 then right clicking on the .jsp file and clicking "run on server".  Of course when I do this none of my other java servlets or .jsp files work.
    If I start up Tomcat6 first then all of my other java web projects are fine, but the Crystal Reports project will not work.
    Here are the errors:
    Please help.
    HTTP Status 500 -
    type Exception report
    message
    description The server encountered an internal error () that prevented it from fulfilling this request.
    exception
    org.apache.jasper.JasperException: javax.servlet.ServletException: com.crystaldecisions.sdk.occa.report.lib.ReportSDKException: Report file /CrystalReport1.rpt not found---- Error code:-2147215356 Error code name:fileNotOpened
         org.apache.jasper.servlet.JspServletWrapper.handleJspException(JspServletWrapper.java:522)
         org.apache.jasper.servlet.JspServletWrapper.service(JspServletWrapper.java:398)
         org.apache.jasper.servlet.JspServlet.serviceJspFile(JspServlet.java:337)
         org.apache.jasper.servlet.JspServlet.service(JspServlet.java:266)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
    root cause
    javax.servlet.ServletException: com.crystaldecisions.sdk.occa.report.lib.ReportSDKException: Report file /CrystalReport1.rpt not found---- Error code:-2147215356 Error code name:fileNotOpened
         org.apache.jasper.runtime.PageContextImpl.doHandlePageException(PageContextImpl.java:850)
         org.apache.jasper.runtime.PageContextImpl.handlePageException(PageContextImpl.java:779)
         org.apache.jsp.test_jsp._jspService(test_jsp.java:113)
         org.apache.jasper.runtime.HttpJspBase.service(HttpJspBase.java:70)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
         org.apache.jasper.servlet.JspServletWrapper.service(JspServletWrapper.java:374)
         org.apache.jasper.servlet.JspServlet.serviceJspFile(JspServlet.java:337)
         org.apache.jasper.servlet.JspServlet.service(JspServlet.java:266)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
    root cause
    com.crystaldecisions.sdk.occa.report.lib.ReportSDKException: Report file /CrystalReport1.rpt not found---- Error code:-2147215356 Error code name:fileNotOpened
         com.businessobjects.reports.sdk.d.byte(Unknown Source)
         com.businessobjects.reports.sdk.JRCCommunicationAdapter.a(Unknown Source)
         com.businessobjects.reports.sdk.JRCCommunicationAdapter.request(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.x.a(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.q.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.do(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.if(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ClientDocument.open(Unknown Source)
         com.crystaldecisions.reports.sdk.ReportClientDocument.open(Unknown Source)
         org.apache.jsp.test_jsp._jspService(test_jsp.java:77)
         org.apache.jasper.runtime.HttpJspBase.service(HttpJspBase.java:70)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
         org.apache.jasper.servlet.JspServletWrapper.service(JspServletWrapper.java:374)
         org.apache.jasper.servlet.JspServlet.serviceJspFile(JspServlet.java:337)
         org.apache.jasper.servlet.JspServlet.service(JspServlet.java:266)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
    root cause
    com.businessobjects.reports.sdk.d: Report file /CrystalReport1.rpt not found
         com.businessobjects.reports.sdk.c.a(Unknown Source)
         com.businessobjects.reports.sdk.b.v.if(Unknown Source)
         com.businessobjects.reports.sdk.JRCCommunicationAdapter.request(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.x.a(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.q.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.do(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.if(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ClientDocument.open(Unknown Source)
         com.crystaldecisions.reports.sdk.ReportClientDocument.open(Unknown Source)
         org.apache.jsp.test_jsp._jspService(test_jsp.java:77)
         org.apache.jasper.runtime.HttpJspBase.service(HttpJspBase.java:70)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
         org.apache.jasper.servlet.JspServletWrapper.service(JspServletWrapper.java:374)
         org.apache.jasper.servlet.JspServlet.serviceJspFile(JspServlet.java:337)
         org.apache.jasper.servlet.JspServlet.service(JspServlet.java:266)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
    root cause
    java.io.FileNotFoundException: \CrystalReport1.rpt (The system cannot find the file specified)
         java.io.FileInputStream.open(Native Method)
         java.io.FileInputStream.<init>(FileInputStream.java:106)
         java.io.FileInputStream.<init>(FileInputStream.java:66)
         com.crystaldecisions.jakarta.rpoifs.RandomAccessPOIFileSystem.<init>(Unknown Source)
         com.crystaldecisions.reports.common.ae.a(Unknown Source)
         com.crystaldecisions.reports.common.ae.if(Unknown Source)
         com.crystaldecisions.reports.reportdefinition.bi.if(Unknown Source)
         com.crystaldecisions.reports.reportdefinition.bi.C(Unknown Source)
         com.businessobjects.reports.sdk.c.a(Unknown Source)
         com.businessobjects.reports.sdk.b.v.if(Unknown Source)
         com.businessobjects.reports.sdk.JRCCommunicationAdapter.request(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.x.a(Unknown Source)
         com.crystaldecisions.proxy.remoteagent.q.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.do(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.if(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ReportClientDocument.a(Unknown Source)
         com.crystaldecisions.sdk.occa.report.application.ClientDocument.open(Unknown Source)
         com.crystaldecisions.reports.sdk.ReportClientDocument.open(Unknown Source)
         org.apache.jsp.test_jsp._jspService(test_jsp.java:77)
         org.apache.jasper.runtime.HttpJspBase.service(HttpJspBase.java:70)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)
         org.apache.jasper.servlet.JspServletWrapper.service(JspServletWrapper.java:374)
         org.apache.jasper.servlet.JspServlet.serviceJspFile(JspServlet.java:337)
         org.apache.jasper.servlet.JspServlet.service(JspServlet.java:266)
         javax.servlet.http.HttpServlet.service(HttpServlet.java:803)

    Hello guys,
    The configuration steps described by Hep Dev works and solve my problem.
    Thank you.
    Best regards,
    Ivo Kotev