Stock Transfer Reservation

Hello Experts
   Can any one please elaborate what are pre reqisites for Stock Transfer Reservation?
Thanks
Ankit

Kailash
  Replenishment via Stock Transfer Reservation is possible, you need to maintain data in MRP4 view. Here is defination for Stock Transfer Reservation. But I dont know how to set it.
Triggering Replenishment via Stock Transfer Reservations
Use
This procedure shows you how you can stage components for production using stock transfer reservations. It makes sense to use stock transfer reservations if you do not want to carry out direct stock transfer, you do not use KANBAN (you have maintained no supply areas or control cycles) and the issue storage location is not managed using Warehouse Management. Replenishment using stock transfer reservations differs from direct stock transfer in that, for stock transfer reservations, the pull list only creates a reservation for the components required. You carry out the actual stock transfer posting in a separate step.
For a direct stock transfer, the pull list posts the stock transfer immediately. A stock transfer reservation, therefore, provides you with an opportunity to check the actual stock situation more accurately.
Thanks
Ankit

Similar Messages

  • Stock Transfer Reservation in spite of Purchase Requisition in MRP run

    Dear SAP gurus,
    We are running MRP heuristic on the PP/DS and we have different results comparing our development and productive environments.
    In our productive environment purchase requisitions are generated and in our development environment stock transfer reservations are generated as result of the MRP run.
    Where can I check differences of configuration that would be causing this?
    Thanks and BR
    Mauricio

    Mauricio,
    I guess I was not clear in my suggestion, I apologize.  Differences in T001W between ERP dev and prod will not necessarily generate your problem, differences in sourcing within APO between APO dev and APO prod will generate the differences.  I only mentioned the vendor number because a transportation lane can exist 'source plant > destination plant', but also you can have a transportation lane 'vendor of source plant > destination plant' which would also have an impact on the type of req created.
    Easier to check the sourcing, //PWBSRC1, mentioned earlier.  Your dev system should contain no objects that relate to Stock Transport orders.  You can delete the STO sourcing records within that transaction, which will also delete the material assignment to the Transportation lane.  Hopefully you will then get the default external supply proposal, which is normally a Purchase req.
    Also check for presence of quota arrangements //SCC_TQ1.  Delete any that unnecessarily refer to an STO object.
    Best Regards,
    DB49

  • Creation of Stock transfer reservations

    Can any one please tell me how to create stock transfer reservations?

    Hi yamuna,
    Do u mean to say, stock transfer reservation is to be created at Plant level while Material has assigned  storage loaction  MRP area.
    If not, please come with simple example sothat we can understand more better and help
    regards
    pardeep

  • Creating stock transfer reservation instead of P.req

    Folks,
    We have two materials ,both are external procurement and both are the same master data but one materials creating P.req and another materials is creating Stock transfer reservation(category BD) instead of P.reqs,Is there any specific setting which we missed to create P.reqs.
    Please through some lights on this.
    Regards,
    Prabhu

    Hello all,
    The issue was resolved,In the transportation lane the source location is maintained as 1007 location type(Storage location MRP area).
    Regards,
    Prabhu

  • Change default mvt 311 for stock transfer reservation generated by system

    Dear SAPper,
    I used storage location '0003' planned seperately in material master MRP4 and set reorder point 100 and replenishment 100 too.
    After the stock fall below 100 the system will create stock trasnfer to '0003' the 'from storage location' is still blank. the system used movement type 311
    i want to used two step transfer 303 - 305 for this transfer.
    of course 303 can not be used to reservation so i create customized mvt type 903 (copy from 303 and modify it)
    but something still trouble is when the MRP generate reservation it always use 311 movement tpe
    can i customized that when storage location planned seperately stock fall below reorder point, MRP generate resevation transfer with mvt 903 (not standard 311)
    Please kindly help
    Best regards,
    Freddy Ha

    hi,
    actually there is 2 problems here
    1. 303 two step is prohibited for reservation so i create 903 to be used in reservation for two step transfer with reservation
    2. reservation is created automatically for storage location plan seperataly if the stock fall below reorder point, this problem is system always use movement type 311 sloc to sloc
    i want to used two step sloc to sloc, so the reservation created using 903
    can i configure it?
    Best regards,
    Freddy ha

  • MF60 : Rounding up stock transfer reservation

    Dear guru ,
    Pull List is used to create reservation for the missing quantity of materials for producing a product.
    The system purposed the exact missing quantity to transfer from a storage location to another.
    Can I automatic rounding up this quantity to a minimum quantity ?
    Thanks a lot.

    Is it ABSOLUTELY NECESSARY to activate the user exit in order to get Round Up Replenishment Proposals to function?  I would prefer not to activate this user exit if possible (due to temporary limited ABAP resources in my company).

  • MRP creates STO-reservation in stead of Stock Transfer PO (s.loc-s.loc)

    Hi All,
    I hope you can help me!
    I am setting up STO, stock transfer order, between two storage locations within the same plant. I have activated the relevant customizing settings (the standard STO-set up located in the PO-part of the MM area) and I have maintained the master data needed (MRP 4-view: MRP indicator u201C2u201D, added replenishment values and entered no value in the special procurement type field).
    When I enter a STO manually in ME21N everything works fine.
    My problem is that instead of getting a stock transfer purchase requisition triggered by the MRP I get a stock transfer reservation u2013 which is utterly useless to me. I would like to run a scenario with MRP driven STO-replenishment of specific storage locations, not use reservations.
    MRP area is activated for the plant in question (MRP area type 01, plant). I am in doubt if this influences my issue.
    Looking forward to hear from you all.
    Kind regards,
    /Dag

    Hi Rob,
    Thanks for your suggestion - i have actually played around a bit with the spec.proc.key.
    When I enter the procurement key in the MRP4-view of the material I get an error saying something with "recursiveness". Meaning, I believe, that I cannot assign the same plant in the spec.proc.key as the one the material master is referring to when creating the MRP4-view.
    Does the above make sense to you?
    Kind regards,
    Dag

  • 2 Step Stock Transfer Using WM Transport Order??

    Dear SAP expertes,
    I have a problem, I think a lot of you too; that is stock transfer in 2 steps from one storage location to another (mov. types 313-315), but using o referencing a reservation.
    SAP says that is not possible create reservations for 2 step stock transfer in MM, but also says use "Stock Transfer Orders" instead, that means use module WM.
    Do anyone could transfer stock from one storage location to another using WM Stock Transfer Orders? I tried, but couldn't make it. In anyone have documention to do this I will appreciate it a lot.
    Best regards,
    Favio.

    Hi Jürgen L.
    I was checking SAP Note  "28692 - MMIM: Reservation for a two-step stock transfer", and you were right, they say "Use the stock transport order instead of the stock transfer reservation".
    I confused with WM stock tranfer order, but I want to ask you if you have used UB transport order between storage location of the same plant?
    Best regards,
    Favio.
    Edited by: Favio Del Castillo on Sep 22, 2010 5:01 PM

  • Stock transfer using PICK LIST / PULL LIST

    Hi Friend,
    We have two storage locations in the plant say 1000 - Main store which is ware house managed and 2000 - Production storage location.
    The goods issue needs to be done from production storage location 2000. How to transfer the material from 1000 - Main store which is ware house managed to 2000 - Production storage location using PICK LIST / PULL LIST concept.
    Kindly give the solution.
    Regards,
    Narendra Bora

    Hello Madhu,
    If you can suggest me as well. I am moving the goods to production storage location from raw material storage lcoation,
    While executing the MF60 it creates the reservation and display log
    RMPU     stock transfer reservations 00000412 22.03.2010 created successfully
    But does not move the goods using 311 movement type and stock is still in the raw material storage location.
    2ndly in MMBE, if i found the stock in Produciton location, it shows me
    Reserved                     20.000
    GR blocked stock         20.000
    Rcpt reservation          20.000
    If you can enlighten me in this area please, Would it move the stock or I need to make some other  steps also.
    Regards,
    JPS

  • Requirement date in reservation for Stock transfer from one storage locatio

    Hi ALL,
    I have activated the resevration creation  by MRP for stock transfer from mail ware house to service storage location  by creating MRP area for service storage location  when there is requiremnt from service and when MRP is run on the MRP area the resevration in created and trasnfer order is created .but the requiremnt date in reservation is not the same asd of on service order.so kindly let me know why it is ahppening.

    Hi,
    check the GR processing time for the material . System may be adding GR processing time with reservation requirement to arrive at the service delivery date.
    Regards,
    Mrinal

  • Stock transfer from Reservation stock to Unrestricted

    Hi
    Is it possible to post stcok transfer Reservation stock to unrestricted stock..
    Please suggest

    Hi
    it is possible to transfer stock with help of reservation ,from storage location to storage location,
    plant to plant
    but from one stock type to other stock type ( ex.Quality to unrestricted )
    i don't think so
    Regards
    Kailas ugale

  • Stock Transfer by movement type 301 referring STO

    Dear Experts,
    I am unable to generate a stock transfer referring an STO in MB1B or MIGO by movement type 301. I am successfully doing whenever I refer a Reservation. Please advice.
    Regards,,
    Subhro Chakravarty

    Hi,
    i have to ask you to read the SAP Documentation for 'Stock Transfer Using a Stock Transport Order'.
    It is explained there how to post a goods movement for STO.
    http://help.sap.com/erp2005_ehp_04/helpdata/en/4d/2b90dc43ad11d189410000e829fbbd/frameset.htm
    br, G

  • Storage Location MRP - transfer reservations

    We have this set up and are creating 311 reservations to transfer SLOC to SLOC.  Is there any way to set this up to use a 2 part process (like 313, 315)?  We need one location to "issue" when they post and the other location to be able to "receive" post.  It's a problem that posting the 311 moves the goods immediately to Unrestricted.  We'd also be open to any process that would automatically move the goods to blocked stock when the 311 was posted with MB1B.  Any help would be appreciated.  Thanks in advance.

    Hi,
    You cant create 2 reservation in the system for stock transfer b/w slocations.
    Automatic reservations are only created using Mvt type 311,not 313 and 315.
    For your second query,you cant post the stock to blocked because 311 is one step procedure and from URS tyo URS.For that to happen use 343/344 mvt types for your business scenario.
    Regards,
    Deepak.

  • Material Ledger for Stock Transfer Postings

    Hi All,
    I have a question about the way material ledger is calculated for stock transfer postings (movement type 641). I will give an example to illustrate this issue:
    Material A has a Standard cost of $10
    Material B has a Standard cost of $8
    During the month 100 units were transferred from material A to Material B. This created a financial posting as follows:
    Credit Material A -          $1000                               
    Debit Material B -           $800
    Debit Price Difference    $200
    This price difference of $200 was used in the calculation of Actual cost for material B
    However, the Actual Cost for Material A was $9. I would have expected the system to use this actual cost to calculate the difference to be posted to material B. Hence the difference used in Material B should have been $100 {(9 – 8) X 100} and not $200.
    Has anyone had a similar issue, or know how the system resolves this (if at all)?
    Points will be rewarded for relevance.
    Thanks

    Dave, I see that your process is slightly different to mine. We do not revalue inventory at month end, instead the material ledger program posts the revalued amount to a reserve account and the actual cost is only a statistical entry. The material ledger calculation is reversed automatically in the new month and the standard price is used for valuation.
    I think this might make it difficult for the system to value STO's at actual. I may need to check with SAP.
    Thanks

  • How to organise stock transfer in scm-erp

    Hello all!
    There is a plant. there are many stocks inside plant. we use sap erp .we are plannig integrate sap scm. i don't know how to organise stock transfer between stock. what is better: using sto converted from stock tranfer requisition or using reservations created from planning in apo. maybe i am wrong..

    Hi Mildar,
    You can integrate sto between erp and scm via coreinterface
    through creating integration models and get it planned via APO
    in deployment
    In deployment run of APO, using the stocks, system converts
    the stock transfer requisitions to stock transfer orders and
    push it to SAP R/3 system which you can use it for
    executing purpose. 
    Regards
    R. Senthil Mareeswaran.